Addendum #2 for Request for Proposal (RFP) 2024-CD-02 is issued by the Town of Pagosa Springs, Colorado, addressing the Yamaguchi South River Improvement Design-Build Services project. The addendum modifies the original RFP due to negative environmental testing results in the wetland/lagoon area, resulting in the removal of the irrigation diversion structure and associated wetland/pond improvements. The revised timeline extends the proposal submission deadline to April 29th, 2024, with a site visit scheduled for April 10th, 2024. Key dates include consultant interviews from May 1st-3rd, 2024, Town Council approval on May 23rd, 2024, contract execution on June 12th, 2024, final design completion by June 1st, 2025, and project construction completion by December 1st, 2025.
The changes to the RFP stem from environmental testing complications, which have necessitated significant modifications to the original project scope. The addendum specifically deletes Section 3 of Appendix A related to wetland area/pond improvements and updates the project timeline to reflect these changes. The design-build services will focus on the recreational and ecological enhancement of the San Juan River through Yamaguchi Park, with an emphasis on improving public access, fish habitat quality, and sediment movement, while adapting to the newly discovered environmental constraints.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP_Yamaguchi South River Improvement 2024.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Town of Pagosa Springs 551 Hot Springs Boulevard Post Office Box 1859 Pagosa Springs, CO 81147 Phone: 970.264.4152
Request for Proposal 2024-CD-02 Yamaguchi South River Improvement: Design-Build Services Town of Pagosa Springs
Responses Due By 4 p.m. on April 29th, 2024
Addendum #2 identifies changes within RFP 2024-CD-02. The changes to the advertised RFP are due to negative results found during environmental testing within the wetland/lagoon area identified within Appendix A and Appendix C of the RFP.
The results of the testing will now dictate the removal of the irrigation diversion structure identified in Appendix C and associated Wetland/Pond improvements described in Appendix A.
This addendum also addresses identified timeline discrepancies and extends the RFP response due date to April 29th, 2024.
The RFP addendums are as follows:
1. Section “VII. Timeline for Selection and Critical Dates” This existing section is hereby deleted and replaced with the following:
VII. Timeline for Selection and Critical Dates RFP release date: March 29th, 2024
Site Visit: April 10th, 2024 Request for Clarification Deadline: April 18th, 2024 Response to Clarification: April 19th, 2024 Proposal Submission Deadline: April 29th, 2024 Consultant Interviews (if needed): May 1st through May 3rd, 2024 Town Council Approval/Award Selection: May 23rd, 2024 Contract Fully Executed: June 12th, 2024 Notice to Proceed: June 12th, 2024 Final Design Completion: June 1st, 2025 Construction Completion: December 1st, 2025
2. Section 3 of Appendix A, “Wetland area/Pond Improvements.” This existing section is hereby deleted.