Addendum No. 2 for Invitation to Bid No. FW-008-25 is issued by the Kentucky Department of Fish and Wildlife Resources for the FILO - Rolling Fork Floodplain Stream and Wetland Restoration Project located in Nelson and Larue Counties, Kentucky. The addendum includes responses to five bidder questions related to tree planting specifications, including soil amendments, mulch requirements, tree tube alternatives, vegetation management addendum dates, and planting schedules. The questions and responses provide clarification on planting techniques, survival guarantees, and project timeline considerations, with specific guidelines for bare root saplings, 3-gallon container trees, and planting timeframes.

The document indicates that the project involves ecological restoration work with specific requirements for tree planting and vegetation management. The responses emphasize that any deviations from the original specifications must be approved by the Engineer and Owner, with a focus on maintaining the specified survival rates for planted vegetation. The addendum suggests two potential additive alternates for invasive species management, with anticipated work during the 2025 and 2026 growing seasons, subject to approval by the Kentucky Department of Fish and Wildlife Resources. The project appears to have detailed specifications for planting techniques, protection methods, and long-term vegetation survival.

View the file

Other files

File Type Posted
Final_RFB_660_2500000700_2_SO_FORM.PDF PDF
Final_RFB_660_2500000700_1_SO_FORM.PDF PDF
Addendum 1.pdf PDF
Final_RFB_660_2500000700_3_SO_FORM.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

KENTUCKY DEPARTMENT OF FISH AND WILDLIFE RESOURCES

INVITATION TO BID NO: FW-008-25

FOR: FILO - Rolling Fork Floodplain Stream and Wetland Restoration Project Nelson and Larue Counties, Kentucky

DATE: June 18, 2025

RFB 660 2500000700

ADDENDUM NO. 2

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: See the attached responses to questions and site visit sign-in sheet.

END OF ADDENDUM

Invitation to Bid No. FW-008-25 For: FILO - Rolling Fork Floodplain Stream and Wetland

Restoration Project Nelson and Larue Counties, Kentucky

Kyla Satterly Kentucky Department of Fish and Wildlife Resources

Rolling Fork Floodplain Stream and Wetland Restoration Project 660-C9D2

Responses to Bidder Questions

Questions in black text, responses in red text.

1) Will soil amendments be required for the tree planting?

Acceptable amendments are included in the specifications. Ultimately the tree planting work and any associated soil amendments, etc. is governed by the guarantee included in the specifications (a minimum of 83.3% two-year survival for bare roots, 75% two-year survival for container stock, and 50% two-year survival for live stakes).

2) Will mulch be required for the 3-Gallon Containers? I see mulch in the drawing listed as "per owner's representative", but no mulch required in the details and specifications.

Per the detail in the drawings, mulch may be required by the Owner’s representative, but ultimately the tree planting work and any associated mulch, etc. is governed by the guarantee included in the specifications (a minimum of 75% two-year survival for container stock).

3) Can Plantra SunFlex 5 ft. tree tubes be used in replacement of a 4 ft. tall galvanized wire shelter for container trees?

Any alternatives must be approved by the Engineer and Owner. Plastic alternatives will not be considered.

4) What are the target dates of the two additive vegetation management addendums? I only have found “in the growing season".

If either of the additive alternates for invasive species management are awarded, it is anticipated that Alternate 1 will take place during the 2025 growing season prior to breaking ground and Alternate 2 will take place during the 2026 growing season; however, the project schedule, including completion dates, must be approved by KDFWR in advance of the work.

5) Per the proposal, 1) Bareroot saplings are to be planted between December and April, and 2) 3- Gallon Containers are to be planted between September 15-December 15 during a maintenance timeframe. Will there be flexibility to plant Bareroot and 3G Containers at the same time in the spring?

Refer to Section 32 93 00 paragraph 1.08 for other planting schedules considerations. Any deviations from the required schedule must be approved by the Engineer and Owner and will not affect the guarantee. Ultimately the tree planting work is governed by the guarantee included in the specifications (a minimum of 83.3% two-year survival for bare roots, 75% two-year survival for container stock, and 50% two-year survival for live stakes).

Addendum 2
Rolling Fork Floodplain - Response to bidder questions
20250605 RFFP PreBid Visit SignIn Sheet