This document is an Addendum No. 2 for the Ichetucknee Springs - Replace Restroom project, Bid No. BDC10-23/24, issued by the Florida Department of Environmental Protection, Bureau of Design and Construction. The addendum postpones the bid submittal due date to 3:30 PM (ET) on Tuesday, October 17, 2023, and the bid posting date to 3:30 PM (ET) on Tuesday, October 24, 2023. It also provides clarification on the electrical service requirements, specifying that the electric provider is Duke Energy, not CFEC as previously referenced.

The addendum requires that all pumps, blowers, and their related control panels be standardized to 230V 1P electrical service. Bidders are instructed to confirm whether 208V or 230V is appropriate prior to construction. The electrical service to the proposed restroom will be installed by directional drill, as detailed in the attached plan and notes.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP Bid No. BDC10-23/24, Addendum #2, Page 1 of 5

FLORIDA DEPARTMENT OF

Environmental Protection

Marjory Stoneman Douglas Building 3900 Commonwealth Boulevard

Tallahassee, FL 32399

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

September 29, 2023

NOTICE TO APPLICANTS

ADDENDUM NO. TWO (2)

Ichetucknee Springs – Replace Restroom

DEP BID NO. BDC10-23/24

TO BIDDERS AND PLAN HOLDERS ON THE ABOVE REFERENCED PROJECT:

PLEASE NOTE CONTENTS HEREIN AND INCLUDE, SIGNED, WITH YOUR BID

SUBMISSION.

NOTICE

It will be required that this addendum be signed in acknowledgment of receipt and that it be included with your Bid when same is submitted to Macey Robinson, Contracts Specialist, Bureau of Design and Construction, 3800 Commonwealth Boulevard, MS #520, Tallahassee, Florida, 32399-3000. Failure to do so may be grounds for rejection of the Bid.

Signature of Contractor and Date

The following statements supersede & supplement the corresponding items in the specifications & drawings:

The bid submittal due date and bid posting date for this project have been postponed:

BID SUBMITTAL DUE DATE: No later than 3:30 PM (ET), Tuesday, October 17, 2023, to the below address: Florida Department of Environmental Protection, Bureau of Design and Construction, 3800 Commonwealth Blvd., MS #520, Tallahassee, Florida, 32399-3000, Attention: Macey Robinson, Contracts Specialist, Bureau of Design and Construction, (850) 245- 2737. (For hand delivery: Carr Building, Welcome Desk.) The Department reserves the right to reject any or all bids.

BID POSTING DATE: No later than 3:30 PM (ET), Tuesday, October 24, 2023, unless extended by the Department for good cause.

1. The Engineering Consultant has provided Plans clarification for the Onsite Sewage and Wastewater Treatment System.

Please standardize all pumps and blowers, and their related control panels, to 230V 1P.

Prior to construction, confirm whether 208v or 230v, where appropriate.

DEP Bid No. BDC10-23/24, Addendum #2, Page 2 of 5

2. The electric service to the proposed restroom to be installed by directional drill – see attached plan and notes. The electric provider is Duke Energy, not CFEC (as referenced on sheet E001 and C102).

Please see the attached for further information.

In all other respects, the contract documents of which this is an Addendum, and attachments relative thereto, shall remain in full force and effect.

ICHETUCKNEE SPRINGS, FL

Electrical Load Table for Onsite Wastewater System Rev: 230v

C:\Users\Mark\Documents\1 WTI\1 Active Projects\DRMP\ICHETUCKNEE\Construction ready docs\ICHTUCKNEE OSTS Electrical load table Rev 230v.doc Rev. Date 2023.06.20 Mark D. Repasky, PE

REVISION 2023.09.20

ATTENTION ALL CONCERNED:

Please standardize all pumps and blowers, and their related control panels, to 230V 1P.

Prior to construction, confirm whether 208v or 230v, where appropriate.

Mark D. Repasky, PE 2023.09.20

Highlighted electric load table follows.

Power options .

Item Description Single Phase 110/115V

Single Phase 200-230V

3PH 208-

230V/460V

Lift Station Pumps

Goulds WS0512B

2 EACH

0.5 HP pumps, 2” solids

20A circuits 2 each

7.3 FLA

16.5 LRA

Duplex Control Panel for lift pumps

230v

Controls and alarms for pump station (pump circuits separate, per above)

15A circuit Match pumps

Treatment plant

MicroFAST 1.5 2 each Blower, ½ HP

5.6FLA

20A circuit

2 each

2.8A FLA;

Locked Rotor Amps: 11.6

Goulds WS0512B

Drainfield dosing pumps

2 EACH

0.5 HP pumps, 2” solids

20A circuits 2 each

7.3 FLA

16.5 LRA

Duplex Control

Panel for drainfield dosing pumps

230v

Controls and alarms at OSTDS dosing tank (pump circuits separate, per above)

15A circuit

ICHETUCKNEE SPRINGS, FL

Electrical Load Table for Onsite Wastewater System Rev: 230v

C:\Users\Mark\Documents\1 WTI\1 Active Projects\DRMP\ICHETUCKNEE\Construction ready docs\ICHTUCKNEE OSTS Electrical load table Rev 230v.doc Rev. Date 2023.06.20 Mark D. Repasky, PE

Miscellaneous Receptacle GFI courtesy outlet 20A

Refer to site plan for electrical schematic and general description.

The Project Electrician will supply circuits to the blowers, pumps and controls, and a courtesy outlet to be installed at the site of the system.

ELEC. SERVICE PLAN

ICHETUCKNEE STATE PARK RESTOOM

Legend

400 ft

N

N

+/- 550 LINEAR FEET OF 3" SCH. 40 PVC ELEC. CONDUIT.

INSTALL BY DIRECTIONAL DRILL, MAINTAIN 10-FT OR

GREATER DEPTH, AND 3-FT MINIMUM HORIZONTAL

SEPARATION FROM PROPOSED WATER SERVICE

POLE SET BY DUKE ENERGY (APPROXIMATE

LOCATION). COORD. LOCATION OF CONDUIT.

PAD MOUNTED TRANSFORMER

(APPROXIMATE LOCATION)

PROPOSED RESTROOM

(APPROXIMATE LOCATION)

NOTES:

1. IF ANY PORTION OF THE 3" CONDUIT

IS INSTALLED BY TRENCHING,

MAINTAIN 36" MIN. BURY DEPTH.

2. THE SAME ENTRY AND EXIT PITS

FOR THE WATER SERVICE MAY BE

USED FOR THIS ELECTRIC

CONDUIT.

3. APPROXIMATE 12 DEGREE ANGLE

INSTALL.

NOTICE