This is an Addendum 1 to the bid documents for the Sweeney Water Treatment Plant 4MG Clearwell Rehabilitation project, issued by the Cape Fear Public Utility Authority in North Carolina. The addendum announces a change to the bid opening date, which has been rescheduled to Tuesday, June 16, 2026, at 11:00 AM in the Jordan Conference Room, 2nd Floor of 235 Government Center Drive, Wilmington, NC 28403. This is a single prime contract with no pre-bid conference scheduled. Prospective bidders must register with the Bid Manager, Teresa McPherson, by emailing bids@cfpua.org to obtain an official set of contract documents via OneDrive. Registration is mandatory, and bids received from unregistered bidders will not be opened or considered. All other terms and conditions from the original bid documents remain unchanged, and bidders must acknowledge receipt of this addendum in their bid submission to avoid disqualification.

Bidders must submit a bid bond or cash deposit equal to five percent (5%) of the total bid amount as a guarantee of contract execution. Bidders must hold a North Carolina General Contractor's license with a Limited Classification in either Public Utilities or Building to qualify for this work. The successful bidder will be required to furnish construction performance and payment bonds each in the amount of 100 percent of the contract value. Bids must be received by the official clock in the Jordan Conference Room by the deadline; late bids will not be accepted. The Cape Fear Public Utility Authority reserves the right to reject any and all bids and may deem bids that do not meet all stated requirements as nonresponsive, resulting in forfeiture. All inquiries regarding the bid should be directed to the CFPUA Purchasing Division at bids@cfpua.org.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AD-1

Addendum 1

Sweeney WTP 4MG Clearwell Rehabilitation

June 9, 2026

BID DATE: Bid opening has changed to Tuesday, June 16, 2026, at 11:00 AM. A revised advertisement is attached.

TO ALL BIDDERS:

Below are changes and or clarifications to the bid documents for this project. This Addendum forms a part of the Contract Documents and modifies the original bidding documents as noted below. Acknowledge receipt of this Addendum as required in the bid documents. Failure to do so may subject Bidder to disqualification.

ACKNOWLEDGEMENT BY BIDDER. Bidder shall acknowledge receipt of this

Addendum No. 1 in the space provided in the Bid Form.

All other terms & conditions remain unchanged.

Ben Guerrieri Wesley Foy

Cape Fear Public Utility Authority Cape Fear Public Utility Authority

Procurement Manager Project Manager

End of Addendum 1

RE-ADVERTISEMENT FOR BIDS

Sealed bids will be received by the CAPE FEAR PUBLIC UTILITY AUTHORITY addressed to the

Procurement Manager, 235 Government Center Drive, Wilmington, NC 28403 and marked Sweeney

Water Treatment Plant 4MG Clearwell Rehabilitation. Bids will be received until Tuesday, June 16, 2026, at 11:00 AM in the Jordan Conference Room, 2nd Floor of 235 Government Center Drive at which time they will be publicly opened and read.

This is a single prime contract.

Pre-Bid Conference will NOT be held.

Bid Opening: Bids must be in by Tuesday, June 16, 2026, at 11:00 AM in the Jordan Conference Room, 2nd Floor of 235 Government Center Drive. Bids must be received by Ben Guerrieri, Procurement

Manager or designee in the Jordan Conference Room. The official time will be by the clock in the Jordan

Conference Room, 2nd Floor at 235 Government Center Drive and no late bids will be accepted. The

Bidders are responsible for allowing time for traffic and parking prior to delivering the bids to the Jordan

Conference Room. It is the bidder’s responsibility to ensure that the bids are received on time.

Contract Documents: Plans and specifications relevant to the bid may be viewed at the following locations listed below. Cape Fear Public Utility Authority cannot guarantee the accuracy of documents and information at the plan rooms. Official sets only available from Cape Fear Public Utility Authority.

1. iSqft + bidclerk Plan Rooms: View online at: www.isqft.com or www.bidclerk.com

2. Dodge Data & Analytics/Dodge Plan Room: View online at:

www.dodgeprojects.construction.com

3. Construction Journal: View online at: www.ConstructionJournal.com

4. Carolina AGC and Hispanic Contractors Association of the Carolinas: View online at:

www.isqft.com

5. North American Procurement Council, Inc.: View online at www.NorthCarolinabids.com

6. The Blue Book Building & Construction Network: View online at www.thebluebook.com

7. H2bid, Inc.: View online at www.H2bid.com

Prospective bidders must register and obtain an official set of the relevant contract documents from

Teresa McPherson (Bid Manager). To register and obtain bid documents, prospective bidders will be required to email the Bid Manager at bids@cfpua.org and provide contact information. A OneDrive file share link containing an official set of relevant bid documents for download will then be provided to prospective bidder via email. If you send an email to bids@cfpua.org and do not receive a response with two (2) business days, please call 910-332-6472 or 910-332-6651. Bids received from bidders who cannot prove registration at time bids are due will not be opened or considered.

http://www.isqft.com/ http://www.bidclerk.com/ file://///cfpua-shares/Departments/Engineers/2003_Project%20Management%20Division/2015%20Projects/312908.001%20Kerr%20Ave%20Water%20Main%20Ext.%20Line%20D%20&%20E/03-Bidding/01-FEDs/www.ConstructionJournal.com http://www.isqft.com/ http://www.northcarolinabids.com/ http://www.thebluebook.com/ file://///FS02/Departments/Engineering/2003_Project%20Management/01-Administration/04-Construction%20Specification%20Documents/2-SPEC%20DOCUMENTS/Current%20Spec%20Docs%20NON%20MBE/www.H2bid.com mailto:bids@cfpua.org

Section 00111

Advertisement for Bids

CFPUA Page | 2

Rev. 05/05/21

Bid Bond: A deposit is required with the submission of the bid. When a deposit is required, the bidder must submit with the bid cash or a certified check, drawn on a bank or trust company authorized to do business in the State of North Carolina, payable to Cape Fear Public Utility Authority, in an amount at least equal to five percent (5%) of the total amount of the bid, as a guarantee that a contract will be entered into and that satisfactory performance and payment bonds will be executed. In lieu of making the cash deposit above described, a satisfactory bid bond in the amount of five percent (5%) of the total bid, executed by a corporate surety licensed under the laws of the State of North Carolina to execute such bonds, shall be submitted with each bid, conditioned that the surety will upon demand forthwith make payment to the obligee upon said bond if the bidder fails to execute the contract in accordance with the bid bond. This deposit shall be retained if the successful bidder fails to execute the contract within ten (10) days after the award of the bid or fails to give satisfactory surety as required in North

Carolina General Statutes Section 143-129.

Affidavit and Certification of Non-Collusion, Non-Suspension and Non-Conviction: The Affidavit and

Certificate of Non-Collusion, Non-Suspension and Non-Conviction provided with bid documents must be completely executed and submitted with bid.

Each bidder must show evidence that it is licensed as a contractor under Chapter 87 of the North

Carolina General Statutes. The bidder must have the following NC General Contractor’s license to be qualified to perform the work associated with this bid:

Limitation: Limited

Classification(s): Public Utilities or Building

No bid may be withdrawn after bids have been opened, except as provided in the North Carolina

General Statutes.

The successful bidder will be required to furnish a construction performance bond and a construction payment bond as security in the amount of one hundred percent (100%) of the contract amount for the faithful performance and the payment of all bills and obligations arising from the performance of the

Contract.

If the bidder fails to complete and submit all requirements stated in this Advertisement for Bids and those further requirements stated in the Instruction to Bidders included with the relevant contract documents, the Cape Fear Public Utility Authority may deem such failure nonresponsive and therefore a forfeiture of the bid.

Cape Fear Public Utility Authority reserves the right to reject any and all bids.

All inquiries concerning this bid shall be directed to CFPUA Purchasing Division by e-mail to bids@cfpua.org.