Addendum _1 SS4A.pdf
PDF 136 KB Posted
- Attached to
- City of Cedartown Safety Action Plan
- Solicitation number
- PE-71551-NONST-2024-000000007
- Issued by
- Peach County, Georgia
About this file
This document is an addendum to a Request for Proposals (RFP) issued by the City of Cedartown, Georgia for the development of a comprehensive roadway Safety Action Plan. The addendum clarifies that the City has no preference on whether proposals are submitted via hard copy or email, confirms that cost information is required as part of the proposal but not a detailed breakdown, and states that there are no required forms to be filled out. The City is seeking cost information, including hourly rates, for building the Safety Action Plan that complies with USDOT requirements.
The related state and local contract opportunity is for the City of Cedartown Safety Action Plan, which is located in Polk County, Georgia. The City is inviting proposals from qualified firms to develop this comprehensive roadway safety plan.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP Advertisement _ SS4A City of Cedartown.pdf | ||
| RFP Selection Criteria __ Cedartown Safety Ac.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. # 1
CITY OF CEDARTOWN, GEORGIA
REQUEST FOR PROPOSALS
CEDARTOWN SAFETY ACTION PLAN
Question #1: Can you please confirm that the City does not have a submission preference whether we mail a hard copy or email a digital copy?
The City has no preference on the receipt of the submission
Question #2: Per page 5 of the RFP, can you please confirm that in Section “3.2 Project Costs” we do not need to provide any cost proposal or cost information? Can you please confirm that this section is for information only and is not a required section in the proposal response?
The City does want to receive cost information, with the understanding that it is following the guidelines/agreement set forth in Section 3.2 Project Costs.
Question #3: Can you please confirm there are no forms that need to be filled out by the submitting firm?
There are no forms that need to be filled out.
Question #4: Can you please clarify what kind of cost information you would like to receive? Do you want a broken-down budget? Did you need any hourly rates?
Hourly rates (in case of a Change Order) are fine. We are ultimately looking for cost information on building the Safety Action Plan that complies with USDOT's requirements. It will be up to the submitter to determine how best to present the cost of building this Action Plan.
This addendum will be posted to the City of Cedartown, Georgia website:
http://www.cedartowngeorgia.gov/ on August 21st, 2024 http://www.cedartowngeorgia.gov/