Addendum 1_Solar PV.pdf

PDF 185 KB Posted

Attached to
RFQ - Solar Photovoltaic and Battery Energy Storage Systems
Solicitation number
345-06/23/2026
Issued by
New Hanover County, North Carolina

About this file

This is Addendum 1 to a Request for Qualifications issued by the Cape Fear Public Utility Authority (CFPUA) for consulting engineering services related to solar photovoltaic and battery energy storage systems installation at CFPUA facilities in Wilmington, North Carolina. The addendum clarifies key project requirements and maintains the original Statement of Qualifications due date of Thursday, July 23, 2026, at 2:00 PM. The project encompasses design and contract administration services for three facilities at Groundwater Way with a combined solar capacity of 241.87 kW DC and battery energy storage systems sized for three-day capacity for each individual facility's load. The addendum specifies that construction must be substantially completed by December 31, 2027, and establishes the project delivery method as Design-Bid-Build, meaning selected consultants will not be eligible to bid for construction services.

The addendum provides critical clarifications regarding battery energy storage system specifications, requiring three-day capacity to meet each facility's entire individual load requirements. Selected consultants must ensure the system qualifies for ITC Elective Pay under Section 48E of the Internal Revenue Code and support CFPUA in the application process by providing necessary documentation for IRS submissions, though legal or tax advice is not required. The selection process is qualifications-based and will evaluate prime contractors and any proposed subconsultants. All other terms and conditions from the original RFQ remain unchanged, with project management and procurement oversight provided by Sydney Valliant (Project Manager) and Ben Guerrieri (Procurement Manager) of CFPUA.

View the file

Other files

File Type Posted
RFQ_Solar PV_BESS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AD-1

Addendum 1

Request for Qualifications

Solar Photovoltaic and Battery Energy Storage Systems

July 16, 2026

STATEMENT OF QUALIFICATIONS DUE DATE:

Thursday, July 23, 2026, at 2:00 PM (as originally advertised)

RFQ REVISIONS:

Consultant Selection

1. Project Understanding & Approach:

b. Approach to keep the project on schedule and achieve construction by the

December 31, 2027 deadline.

CLARIFICATIONS:

Definition of “Three Day Capacity” for the Battery Energy Storage System:

The battery shall have three-day capacity for entire individual facility load.

Supplemental Information/Data:

The RFQ is a qualification-based selection process intended to evaluate each firm’s qualifications, experience, and capabilities. Project-specific information, including an official site walk-though, supplemental data, site information, and detailed design criteria will be provided to the selected Consultant.

Consultant Involvement in Construction:

The project delivery method will be Design-Bid-Build; therefore, Consultants will not be eligible to bid for construction services under this project.

ITC Elective Pay, Section 48E:

Consultant shall ensure the system qualifies for ITC Elective Pay, Section 49-E, and support CFPUA in the application process, providing necessary information and documentation required for completing IRS applications. The Consultant is not expected to provide legal or tax advice.

Evaluation of Team Qualifications:

This will be a Prime Contract. Submitters may include subconsultants, which will be included in CFPUA’s evaluation criteria.

AD-2

All other terms & conditions remain unchanged.

Ben Guerrieri Sydney Valliant

Cape Fear Public Utility Authority Cape Fear Public Utility Authority

Procurement Manager Project Manager

End of Addendum 1