Addendum #1 - Site Visit Notes Summary
This document is an Addendum to Invitation to Bid (ITB-27-049) issued by Florida School for the Deaf and the Blind (FSDB) for transformer replacement services. The project scope involves the removal and disposal of two existing transformers and the supply and installation of replacement units: one 300 KVA three-phase pad-mounted transformer behind Wilson Music Center (Building #50) and one 500 KVA three-phase pad-mounted transformer by Settles Gymnasium (Building #17). The mandatory pre-response meeting and site visit occurred on October 21, 2026, at 11:00 AM at the FSDB campus in St. Augustine, Florida. Sealed bids are due November 5, 2026, at 2:00 PM for opening in Moore Hall, Room 215. The estimated contract start date is November 27, 2026. Bid responses must remain firm for 60 days after opening. Written questions must be submitted by October 23, 2026, at 4:00 PM to Elizabeth Nimitz, with answers issued as Addendum #2 by October 27, 2026. Selection committee review is scheduled for November 6, 2026, at 12:00 PM, with results notification on November 9, 2026, at 4:00 PM.
The bid pricing must include costs for both new and refurbished transformer options for each unit, with associated lead times. Current transformer specifications indicate that both existing units were manufactured in 1999 by Cooper Power Systems with oil-immersed, self-cooled cooling systems and similar voltage ratings (13200 GrdY/7620 V primary, 208Y/120 V secondary). The contractor is responsible for equipment disposal, movement via lull or other approved motorized vehicles, and fence removal and replacement during installation. All personnel working on campus must obtain Jessica Lundsford Act (JLA) badges at a cost of $85 to $100 per person, valid for five years, except delivery drivers who require valid driver's licenses and clearance verification. Work must occur during Monday-Friday, 7:00 AM to 4:00 PM, or Saturday/Sunday with prior arrangement, and must comply with strict campus safety provisions including tobacco, alcohol, drug, and weapons prohibitions. The project is funded through local sources and is classified as a Category Two procurement with an estimated contract value of $35,000 or greater. Price is the primary selection criterion, and the lowest responsive and responsible bidder will be awarded.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum #2-Q&A-ITB-27-049.pdf | ||
| Transformer Replacement (Phase II) ITB-27-049.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PURCHASING DEPARTMENT
207 SAN MARCO AVENUE
ST. AUGUSTINE, FL 32084
PHONE (904) 827-2331
WWW.FSDBK12.ORG
INVITATION TO BID (ITB)
Transformer Replacement (Phase II)
ITB-27-049
Addendum # 1 - Site Visit Notes
October 21, 2026 http://www.fsdbk12.org/
Agenda for Site Visit – Transformer Replacement (Phase II) ITB-27-049
Page | 2
Housekeeping Note: Please silence all phones and radios during meeting.
Meeting promptly began at 11:00 AM
A. Staff Introduction
1. Sign-in
2. Purchasing Director/Procurement Director: Kim Whitwam
3. Purchasing Analyst/Procurement Officer: Elizabeth Nimitz
4. Contract Manager: Greg Peacock
5. Evaluation Committee:
a. Guy Maltese – Committee Lead
b. Greg Peacock
c. James Epke-Kranz
d. Jeffrey Melton
e. Randy Vankirk
B. Bid Response Requirements
1. Review Bid Package Documents
2. Place for Receiving Bids: Bids will be received at Florida School for the Deaf and the Blind, 207 San Marco
Ave., St. Augustine, FL 32084, Purchasing Center, building #28, no later than 15 minutes before the bid opening time, which is noted in the Schedule of Events and Deadlines. If dropping off a bid response in person, please arrive in ample time to allow for security clearance processing and conveyance through the FSDB campus. Time of delivery of bid responses will be noted by arrival time at the Police Center Checkpoint at the Genoply Street entrance.
3. Date, Time, and Place for Bid Opening: Bids will be opened on November 5, 2026, at 2:00 PM in Moore Hall, Room 215. If you attend in person, please allow ample time to allow for security clearance processing and conveyance through the FSDB campus to the bid opening location.
C. REVIEW OF WORK
1. Site working hours – M-F from 7:00 a.m. until 4:00 p.m. Extended hours or days to be arranged with FSDB Project Manager.
2. Access to Campus – security clearance is needed (Level 2 Background screening), instructions can be found on the FSDB website in the Purchasing Competitive Solicitations Dropbox folder.
3. Special Safety Provisions for working on campus:
a. No tobacco – FSDB has designated smoking areas on campus. Smoking in any other area on campus or in buildings is prohibited.
b. No alcohol, drugs, or weapons.
c. Provisions for protecting deaf and blind people passing nearby worksite.
d. Strict adherence to safety rules by Contractor’s employees.
4. Review the Scope of work, plans, and specifications; site plans given out (if applicable)
5. Time frame for completion of project
D. Discussion: Questions & Answers
Q: What are the voltages?
A: Please refer to Exhibit A attached to this Addendum.
Page | 3
Q: Is FSDB looking for new or refurbished transformers?
A: FSDB would like pricing for both options. An updated Appendix H – Vendor Price Proposal has been attached to this Addendum.
Q: (FSDB) What is the lead time for a new transformer?
A: Based off lead times for generators, possibly 30 weeks.
Note: Do not let the time of performance in the sample agreement draft prevent you from submitting a bid. It will be adjusted according to the selected vendor’s project schedule and timeline.
Q: If transformers are shipped to the campus, would FSDB have a lift to move the equipment?
A: FSDB does NOT have a lift, but a lull. The vendor is responsible for moving equipment for this project.
Q: Is this project funded by federal money?
A: No.
Q: (Regarding the transformer located behind Wilson Music Center, building #50) Would FSDB like to level this pad?
A: Yes.
Q: Are vendors able to take down the fence during removal and installation?
A: Yes, however, vendors are responsible for putting in back up.
Q: Will the wiring remain the same?
A: Yes.
Q: Why is FSDB replacing these transformers?
A: Due to age and condition.
Q: Do you want to modify for an external port, for your oil sample report?
A: No modification, as another company provides FSDB that report.
Q: Are replacements to be consecutive?
A: Yes, or can be scheduled for different days.
Note: Work is to take place on Saturday or Sunday.
Q: Is there road access (regarding the transformer located by Settles Gymnasium, building #17)?
A: Yes, there are multiple access points.
Note: Vendors were shown the main access point which would require the least amount of navigation between buildings.
Q: If the awarded vendor has a lull, are they allowed to drive it through campus to reach the transformers?
A: Yes.
Q: If the awarded vendor needed to schedule an alternative date for replacements, how long would that process take?
A: Approximately a month.
Q: Are vendors able to bring other motorized vehicles onto campus (besides lulls)?
A: Yes, subject to FSDB approval.
Page | 4
E. Site Visit
Walk through project locations with FSDB Project Manager.
Site Discussion Notes:
• A word document version of Appendix G (titled PUR 7801) is posted to the FSDB website: Purchasing | FSDB
• Vendor is responsible for the disposal of the old transformers. FSDB does not have a place to store them for refurbishment.
• Storage is available for vendors and will be coordinated between the awarded vendor and FSDB project manager.
• Transformer specs and photos have been attached as Attachment A of this Addendum.
• All staff working must have Jessica Lundsford Act (JLA) badges. The only exception being deliver drivers, however; drivers still need to have a valid Driver’s License and no warrants or anything else that would prohibit them from being on school grounds.
The awarded vendor should also send their badging information to the project manager, Greg Peacock as well; we have had some difficulty with our electronic filter holding emails.
Q: Cost? A: Between $85 to $100 per person. The badges are good for 5 years.
F. Conclude
1. Minutes of the Site Visit will be issued as Addendum #1 and posted to the FSDB website in the Purchasing Competitive Solicitations Dropbox folder by October 21, 2026.
2. Submit all questions in writing to the attention of Elizabeth Nimitz no later than October 23, 2026, at 4:00PM by e-mail: nimitze@fsdbk12.org.
3. Answers to written questions to be issued as Addendum #2 and posted to the FSDB website in the Purchasing Competitive Solicitation Dropbox folder by October 27, 2026.
Meeting Concluded at 11:50 AM.
https://nam02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fus-west-2.protection.sophos.com%2F%3Fd%3Dproofpoint.com%26u%3DaHR0cHM6Ly91cmxkZWZlbnNlLnByb29mcG9pbnQuY29tL3YyL3VybD91PWh0dHBzLTNBX193d3cuZnNkYmsxMi5vcmdfcGFnZV9wdXJjaGFzaW5nJmQ9RHdNRi1nJmM9ZXVHWnN0Y2FURGxsdmltRU44YjdqWHJ3cU9mLXY1QV9DZHBnblZmaWlNTSZyPVhuMFhUOUlhRmFxRTdyVWhfNGYybU9WR2xmUUg4b2wxbnluYlRhaVFXLTQmbT1xWW9NQWJFQVVlbzc0RHJvQ3g3REFrWUpvZ0xFUVRDY2ZzTklNdndUc25JYVVBOWotbnI2cVdqWEFmM29BdENuJnM9XzlqNGZCRUN5cVU3bnBNQnJsX2w3SlFwZDB6b2Y2bGt6LUkzNUFaYWswNCZlPQ%3D%3D%26p%3Dm%26i%3DNjdkOWM0MjkyMGUyZmU1MDg0ZjM5YzQx%26t%3DWDU4ZzdJODI2ajZOQlE0TW5YODJpNjk3OTlqaUJVbDNoaWJhVGhaSDlWcz0%3D%26h%3Da3584b4ce98a4994b12100c53eeb4371%26s%3DAVNPUEhUT0NFTkNSWVBUSVYI-fAUsWiecQ9t9rfqV2Yy3w93q1IcTI70gujUwG8U5w&data=05%7C02%7Cnimitze%40fsdbk12.org%7C3c2edec696734620851508df2e157303%7Cf5facca9613248a5b62f87d908b506b6%7C0%7C0%7C639280341834275206%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C4000%7C%7C%7C&sdata=2P8f14%2BWOXR746qFQHmIZQMhGsbRfkbzPFtJz8ZtWfQ%3D&reserved=0 mailto:nimitze@fsdbk12.org
APPENDIX H – Vendor Proposal Form
Florida School for the Deaf and the Blind Purchasing Center, building #28 207 San Marco Avenue St. Augustine, FL 32084 Project Name: Transformer Replacement (Phase II) ITB-27-049 To Whom It May Concern:
The undersigned Contractor, hereinafter called “Bidder” proposes to furnish all materials and labor for the project identified in the solicitation documents for Florida School for the Deaf and the Blind in St. Johns County. In full accordance with the described Scope of Work, bidder submits the following cost proposal.
In consideration of the Agreement by the “Owner,” the Bidder has agreed and does hereby agree, (1) that the attached proposal shall remain in full force and effect for a period of sixty (60) days after the time of the opening of this proposal, and that the “Bidder” will not revoke nor cancel this proposal or withdraw from the competition within said sixty (60) day period, (2) that in the event the contract is awarded to this “Bidder, “he/she will within sixty
(60) consecutive calendar days after it is submitted, enter into a written contract with the “Owner” in accordance with the accepted bid.
IN WITNESS WHEREOF, the Bidder has hereunto set his/her signature and affixed his/her seal this _______day of ____________, 20____.
BY: _____________________________________ _____________________________________ _____________________________________ (name of authorized principal) (Signature of principal in firm) (firm name)
(Contractor’s Florida Department of Business and Professional Regulations license number)
State of ________________ County of ________________
PERSONALLY APPEARED BEFORE ME, THE UNDERSIGNED AUTHORITY, __________________________________ who after being sworn by me, affixed his/her signature in the space provided above on this __________day of ____________, 20___.
______________________________ My commission expires:
(Notary Public)
END OF DOCUMENT
Description Cost for a New Transformer Lead Time
Cost for a Refurbished Transformer
Lead Time
300 KVA 3P pad mounted TX-B transformer, located behind the Wilson Music Center, building #50 500 KVA 3P pad mounted TX-E transformer, located by Settles Gymansium, building #17
Proposal Amounts will be the prices listed in Article 3 of the Contract - "Deliverables and Payments"
Submitted by (Company Name):
Exhibit A
Current TX-B Transformer located behind Wilson Music Center, building #50
General Information
• Manufacturer: Cooper Power Systems
• Type: 3-Phase Pad-Mounted Transformer
• kVA Rating: 300 kVA
• Serial Number: 9937000711
• Catalog Number: 0075WP10K62A
• Manufacture Date: February 1999
• Frequency: 60 Hz
• Cooling Class: OA (Oil-Immersed, Self-Cooled)
• Temperature Rise: 65°C
Voltage Ratings
Primary (High Voltage)
• 13200 GrdY / 7620 V o 13.2 kV grounded wye system o 7,620 V phase-to-neutral
Secondary (Low Voltage)
• 208Y/120 V o 208 V phase-to-phase o 120 V phase-to-neutral o 4-wire grounded wye
HV Tap Settings
The transformer is presently set to whatever tap position the internal changer is on; the nameplate does not indicate the current tap.
Insulation / BIL
• HV BIL: 95 kV
• LV BIL: 30 kV
• Neutral BIL: 30 Kv
Impedance
• Impedance: 4.5%
Weights
Tap Voltage % Above/Below Rated A 13,860 V 5.00% B 13,530 V 2.50% C 13,200 V Rated D 12,870 V -2.50% E 12,540 V -5.00%
Component Weight Core & Coil 1,762 lbs
Tank & Fittings 1,207 lbs Fluid 1,362 lbs
Total Weight 4,331 lbs
Fluid
Based on the 1999 manufacture date and the OA classification, this is most likely a mineral-oil-filled unit unless a special dielectric fluid was specified. The fluid type is not shown on the visible portion of the nameplate.
Full Load Current
Using the nameplate ratings:
Primary Current @ 13.2 kV
≈ 13.1 amp
Secondary Current @ 208Y/120 V
≈ 833 amps
Short-Circuit/Fault Current Estimate
With 4.5% impedance, the theoretical secondary available fault current at the transformer terminals is:
• ≈ 18,500 amps symmetrical (18.5 kA)
Actual available fault current at your downstream service equipment will be lower depending on secondary conductor length and impedance.
Current Transformer located by Settles Gymnasium, building #17
General Information
• Manufacturer: Cooper Power Systems
• kVA Rating: 500 kVA
• Serial Number: 9937000616
• Catalog Number: 0075WP11K64A
• Date Manufactured: January 1999
• Frequency: 60 Hz
• Cooling Class: OA (Oil-Immersed, Self-Cooled)
• Temperature Rise: 65°C
Voltage Ratings Primary (High Voltage)
• 13200 GrdY / 7620 V o 13.2 kV grounded-wye distribution system o 7,620 V phase-to-neutral
Secondary (Low Voltage)
• 208Y/120 V o 208 V phase-to-phase o 120 V phase-to-neutral o 4-wire grounded wye
Impedance
• Z = 4.0%
This is slightly lower than the 4.5% impedance on the 300 kVA unit you showed earlier, resulting in a higher available fault current.
BIL Ratings
• HV BIL: 95 kV
• LV BIL: 30 kV
• Neutral BIL: 30 kV
Tap Changer Settings
Tap C is the nominal 13.2-kV setting.
Tap Primary Voltage
Secondary Voltage (Approx.)
A 13,860 V 20.8 V/phase factor B 13,530 V 21.3 C 13,200 V Rated D 12,870 V 22.4
Weights
Full Load Current Primary Current @ 13.2 kV
21.9 amps Secondary Current @ 208 V
1,388 amps Available Secondary Fault Current Using the 4.0% impedance:
≈ 34,700 amps symmetrical (34.7 kA) Actual fault current at the service equipment will be lower due to secondary conductor length and impedance.
Comparison to the Previous 300 kVA Unit
Component Weight Core & Coil 2,365 lbs
Tank & Fittings
1,472 lbs
Fluid 1,539 lbs Total Weight 5,376 lbs
Specification 300 kVA Transformer 500 kVA Transformer kVA 300 500
Secondary Current 833 A 1,388 A Impedance 4.50% 4.00%
Available Fault Current ~18.5 kA ~34.7 kA Total Weight 4,331 lbs 5,376 lbs
Voltage 13200GY/7620 → 208Y/120 13200GY/7620 → 208Y/120