This document is Addendum #1 to Request for Qualifications (RFQ) 20-4022 issued by Guadalupe County Purchasing Agent for Engineering Services for Huber Road 2" Asphalt Overlay. The project involves engineering services for a road overlay on Huber Road from FM758 to Rudeloff Road, spanning approximately 34,354 linear feet. The engineering firm will be responsible for preparing plans, specifications, bidding paperwork, monthly pay estimates, and conducting inspections. The proposal submission deadline is 2:00 pm CST on August 5, 2020, with no changes to the original due date.
The project scope includes a 2" asphalt overlay without road widening, and all roadway repairs will be completed by the County Road and Bridge Department prior to project start. Utility considerations include existing Level 3 fiber optics, water mains, telephone cables, and gas lines within the right-of-way, with no required utility relocations. Additional project requirements include Type I and Type II pavement markings in yellow and white, and survey services are required. The engineering firm must also obtain Conflict of Interest Questionnaire (CIQ) forms from listed sub-consultants to include in their Statement of Qualifications (SOQ).
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum #1 to REQUEST FOR QUALIFICATIONS (RFQ) 20-4022
ENGINEERING SERVICES FOR HUBER ROAD 2” ASPHALT OVERLAY
Guadalupe County Purchasing Agent 212 West Nolte Street Seguin, Texas 78155 Phone 830-303-9729
Subject: Addendum #1 to RFQ 20-4022 Date: July 27, 2020
This addendum is being issued to provide additional information for potential proposers.
This addendum is an integral part of the proposal package under consideration by you as a Proposer in connection with the subject matter herein below identified. Guadalupe County deems all sealed proposals to have been proffered in recognition and consideration of the entire proposal package – including all issued addenda.
Receipt of this present Addendum by a Proposer should be evidenced by returning it signed as part of the Proposer’s sealed proposal.
1. This addendum does not change the due date of the proposals. Sealed proposals must be received in the Purchasing Office by: 2:00 pm CST on August 5, 2020.
2. What are the limits of the project?
• Project Limits – Huber Road, FM758 to Rudeloff Rd, approximately 34,354 linear feet.
3. Will there be any roadway repairs as part of this project?
• All roadway repairs will be completed by County Road and Bridge Department prior to start of this project.
4. Will there be any widening of the roadway surface?
• No widening will be involved.
5. Will Engineering firm be preparing plans, specifications, bidding paperwork, monthly pay estimates, and inspections or will the County forces be providing the onsite inspections?
• Plans, specifications, bidding paperwork, monthly pay estimates, and inspections will be required.
6. There are overhead utility poles predominately on the east side of this portion of Huber Road, is the County aware of any subsurface utilities along the Huber Road right-of-way (ROW)?
• Yes, Level 3 fiber optics, water mains, telephone cables and gas lines are all located within the ROW.
7. Are relocation or alteration of overhead utilities desired?
• No, utility relocation or alteration are not required.
8. Along subject portion of Huber Road, slight bar ditch drainage appears present on either side of the existing asphalt with culverts of varying types at property. Is there any intent to analyze or upgrade drainage as part of this project?
• No drainage improvements will be required for this project.
http://www.co.guadalupe.tx.us/
9. Does the county want additional road markings or signage? or is this maintenance of an existing road?
• Yes, Type I and Type II pavement markings, yellow & white and Type II white 12”.
10. Does County need any additional services like geotechnical report?
• No, geotechnical report is not required, but survey service is required.
11. Will engineering firm obtain CIQ forms from listed sub-consultants and include it in their SOQ?
• Yes, CIQ forms from listed sub-consultants need to be provided.
The information included herein is hereby incorporated into the documents of this RFP and supersedes any conflicting documents or portion thereof previously issued.
Receipt of this Addendum is hereby acknowledged by the undersigned Proposer.
Authorized Signature (Proposer)
Title of Person Signing Above
Typed Name of Firm, Corporation
File details come from the government source that posted it. Updated .