Addendum 1, RFP 125353.pdf
PDF 235 KB Posted
- Attached to
- Concept Feasibility Study, Fairfax Circle
- Solicitation number
- RFP-125353
- Issued by
- Fairfax County, Virginia
About this file
Summary of Addendum 1, RFP 125353
This document is Addendum 1 to RFP 125353 issued by the City of Fairfax, Virginia, Office of Procurement Services, for a Concept Feasibility Study of the Fairfax Circle intersection. The addendum, dated October 29, 2026, provides clarifications, corrections, and modifications to the original Request for Proposal. Consultants selected for this feasibility study will not be precluded from competing on subsequent final design phases. The study scope includes developing approximately 10% design plans suitable for a Smart Scale funding application, conducting comprehensive traffic analysis for forecast years 2037 and 2047 with 1% growth assumptions, evaluating nearby intersections within defined study limits (Fairfax Boulevard from Draper to Pickett, Route 29 north to City Limits, and Blenheim Boulevard south to Ridge Avenue), and establishing multiple build alternatives beyond a no-build scenario. The consultant shall provide detailed survey data including horizontal and vertical control, right-of-way boundaries, property lines, and utility locations, along with traffic modeling capable of replicating existing and future conditions across multiple peak periods. The Notice to Proceed is anticipated around January 2027 following consultant selection through interviews. No overall project budget was established, and offerors should not submit cost proposals with their initial submissions; pricing will be negotiated after ranking and selection. Required documents to be completed and submitted by the proposal deadline include Attachment 2 (Proposal Submission Form) and acknowledgment of all posted addenda.
Proposal submission requirements include Exhibit 1 (five examples of qualifications and past involvement totaling 10 pages maximum, with organizational charts permitted at 8.5" x 11" size), Exhibit 2 (proposed methodology, 5 pages), Exhibit 3 (quality assurance plan, 2 pages), and Exhibit 4 (schedule, 2 pages), with title pages, tables of contents, dividers, resumes, and required forms excluded from page counts. Minimum 10-point font and 8" x 11" paper size are required; double-sided printing counts both sides against limits. Primary team members are individuals, not firms, and example projects must be different from those used in other exhibits. The project manager is required to hold a Virginia Professional Engineer license. Professional liability insurance must be $2,000,000 per occurrence and $6,000,000 aggregate. Geotechnical investigation is limited to desktop soils map review only. The City will provide existing signal timings and accident data; traffic counts at other locations must be collected by the consultant, and new traffic models must be created as existing files are outdated. All submissions are electronic through eVA, and vendors employing an average of more than 50 employees must comply with E-Verify requirements. No firms are precluded from submitting, and no set-asides are identified for this solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2, Proposal Submission Form.docx | DOCX document | |
| RFP 125353 Pre-Proposal Attendance List Update 10.23.26.docx | DOCX document | |
| Attachment 1 RFP 125353 Concept Feasibility Study Fairfax Circle 10.20.26.pdf | ||
| Attachment 0, Appendix A.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP 125353, ADDENDUM #1 PAGE 1 OF 6
City of Fairfax, VA
Office of Procurement Services 10455 Armstrong Street
Fairfax, VA 22030
Date: October 29, 2026 Addendum #1
Reference: RFP 125353
Title: Concept Feasibility Study, Fairfax Circle
This addendum is issued to make the following changes, corrections, clarifications, and additions to the Request for Proposal document. The information in this addendum modifies and changes the original Request for Proposals and takes precedence over the original document.
Q1. Will pursuing and winning this RFP for a concept plan preclude a consultant from working on the final design of the Fairfax Circle intersection?
A1. No.
Q2. Can the City please provide a complete checklist of documents required with the proposal and the official Proposal Form and SCC Form referenced in Section 9. Please identify which documents must be completed, signed, and returned; how offeror information and signatures should be provided on the RFP cover sheet; and whether Appendix A requires a separate acknowledgment.
A2. The required documents that shall be completed, signed and uploaded with your proposal on eVA are Attachment 2, Proposal Submission Form and any posted Addendum. Appendix A does not require acknowledgement.
Q3. Can the City please confirm that Exhibit 1 permits separate limits of 5, 10, and 6 pages, respectively, and that Exhibits 2-4 permit an additional 5, 2, and 2 pages. Do covers, contents pages, dividers, forms, resumes, and other appendices count toward these limits? Please specify permitted page sizes, minimum font size, and acceptability of 11” x 17" schedules.
A3. Yes, each section is permitted an allocated amount of pages.
• The page limit does not include title pages, table of contents, divider tabs, resumes, and required forms do not count toward page limit.
• Proposal should use a minimum of 10-point font.
• Paper size is 8 ½ X 11.
• Proposals shall not contain brochures, promotional or display materials.
• If a Proposal is submitted in double-sided format, both sides of the page will be counted against the Page Limit.
• Offeror shall not submit brochures or hyperlinks as additional materials.
RFP 125353, ADDENDUM #1 PAGE 2 OF 6
Q4. Within Section 9's required submission structure, will exhibit headings and a compliance cross-reference table satisfy Section 8.C, or must every narrative paragraph carry an RFP reference and repeat that reference on continuation pages?
A4. RFP reference for each page.
Q5. Can the City please identify which forms, signatures, SCC documentation, and addendum acknowledgments must be completed and submitted by the proposal deadline, and which, if any, may be provided later upon the City's request.
A5. The required documents that shall be completed, signed and uploaded with your proposal on eVA are Attachment 2, Proposal Submission Form and any posted Addendum.
Q6. Section 29 ends with "Work shall meet." Can the City please provide the missing text or confirm that the fragment should be disregarded. The A/E Terms Section 9 deliverables list ends with "Indexed copy of the calculations made by each discipline for the Project; and" without another bullet. Please confirm whether an additional deliverable is required and, if so, identify it.
A6. Section 29: Disregard “work shall meet.” Section 9: disregard “and.” A new RFP document is posted on eVA titled “Attachment 1, RFP 12353 Concept Feasibility Studt Fairfax Circle 10.21.26.”
Q7. Can the City please confirm that, consistent with Sections 10-11, the initial proposal should exclude fees, labor rates, estimated staff-hours, and other service-pricing information, with that information provided during negotiations after ranking. Please clarify how Section 28's cost-proposal language and Appendix A's reference to a Pricing Schedule apply to this submission.
A7. The Offeror should not provide a cost proposal with their proposal submission. The solicitation documents will be considered a part of the resulting contract with the awarded Offeror.
Q8. Can the City please identify the anticipated notice to proceed, desired study duration, target funding program and application cycle, expected number and type of Council and community meetings, and City review periods to be assumed in the proposed schedule. Please also clarify the contractual completion milestone and schedule expectations if Council endorsement or submission of a funding application is delayed.
A8. NTP will be issued after interviews and a selection is made, likely around January. Consultant is expected to provide a schedule for the study as well as assist with determining the appropriate funding program. The number of Council and community meetings depends on the methodology, which is part of the RFP deliverables. Contract completion is upon delivery of a final alternative that meets the Council and community goals. Council will be briefed periodically throughout the process so in theory they will support adoption. If community/Council is not satisfied with the alternative, we should know that way ahead of a final deliverable.
Q9. Can the City please define the required base-scope concept, survey, cost-estimate, and funding-application deliverables, including survey limits and the expected level of utility investigation, and distinguish these requirements from optional advancement from approximately 10% to 30% design. Should the proposal include staffing and methodology for the optional work, and how will that information be evaluated? Please also confirm whether the selected feasibility-study consultant will be eligible to compete for the subsequent project-delivery solicitation.
RFP 125353, ADDENDUM #1 PAGE 3 OF 6
A9. Assume development of approximately 10% plans (level of effort needed to submit Smart Scale application) as the primary deliverable. Given that the scope of work will include evaluation of nearby intersections, the scope should include appropriate survey limits that capture the areas necessary for evaluation. The Consultant shall collect and incorporate comprehensive survey data—including horizontal and vertical control, right-of-way (ROW) boundaries, property lines, existing utility locations, and other relevant site features—into all deliverables. This data must be gathered at a level of detail sufficient to enable accurate risk identification and reliable cost estimation. The selected feasibility study consultant will be eligible to compete for the subsequent solicitation provided they are approved to work with VDOT (if subsequent funding source is VDOT).
Q10. To establish a consistent basis for the proposed work plans, can the City please clarify the following:
A. The required forecast year or years in place of the "future (YEAR)" placeholder, and the growth and development assumptions to be used.
B. The intended study limits, including nearby roadways and intersections to be evaluated for network effects.
C. The expected number of build alternatives to be evaluated in addition to the no-build scenario.
D. The existing data and models the City will provide, including traffic and multimodal counts, crash records, signal timings, and prior-study model files, and any additional data collection expected of the consultant.
E. Minimum analysis requirements, including any required modeling software, microsimulation, and calibration or validation criteria.
A10. A. Analysis should, at the very minimum, look at 10 years out (2037) and 20 years out
(2047). 1% growth should be used along with the projected added trips from any approved or under construction developments in the study area.
B. This will be scoped further once consultant is selected, but as stated above, nearby intersections should be evaluated as part of this effort. The study area should include Fairfax Blvd from Draper to Pickett (inclusive) as well as Rte 29 to north of Fairfax Circle (to City Limits) and Blenheim Blvd to the south (beyond Old Pickett signal to Ridge Ave)
C. There is not a set number.
D. City will be able to provide signal timing for the traffic signals in the area (Fairfax Circle, FFX/Scout, FFX Pickett, Blenheim/Old Pickett, and FFX Draper) and accident data should be available on the state database. Some traffic count information (multimodal counts including trucks, pedestrians and bikes) will be available from existing Miovision camera locations at the two signalized Fairfax Circle intersections (i.e. excluding yield entry points) plus the Fairfax Blvd/Pickett signal. Count data at other locations will need to be collected by the consultant. Existing model files are outdated and thus new files will need to be created by the consultant.
F. There is not a defined analysis type or software expected (something beyond Synchro will likely be needed to accurately model existing and future conditions at the Circle), but the modeling should replicate existing conditions (through calibration) and
RFP 125353, ADDENDUM #1 PAGE 4 OF 6
future conditions for multiple time periods (AM and PM peak periods, midday peak, and weekend peaks at a minimum).
Q11. If a firm, as a prime consultant or a subconsultant, participated in the Concept Feasibility Study, Fairfax Circle, would they be precluded and/or conflicted out form the 30% to final design contract.
A11. No.
Q12. What role will VDOT have in the project? Will they be a project stakeholder or will this be a City-focused stakeholder group?
A12. VDOT is not a stakeholder at this time. VDOT may be a stakeholder down the road.
Q13. Will there be a short-list and interview?
A13. Yes.
Q14. Do you have an overall budget for the project?
A14. No.
Q15. This is a very ambitious comprehensive project. Are you considering following a sustainability infrastructure metrics process such as ENVISION?
A15. Potentially.
Q16. Can you please clarify the Professional Liability Insurance requirements? Would Professional
Liability coverage of 3M per claim/4M Aggregate be sufficient?
A16. $2,000,000 per occurrence, $6,000,000 aggregate.
Q17. RFP page 1 references the Geotechnical Engineering commodity code; however, geotechnical engineering is not further mentioned in the RFP. Please confirm that geotechnical engineering is not a part of the intended scope of work at the concept feasibility study phase.
A17. Geotech should not be needed in the feasibility study other than a cursory review of soils maps.
It would be different if there were bridges or grade separation considered.
Q18. On RFP page 9, under 9: Specific Proposal Instructions, Section 3: Technical Proposal, Exhibit 1 –
Qualifications and Past Involvement with Similar Projects, the second bullet requests offerors to “Identify example project(s) that demonstrate each primary team member’s prior experience on a similar project(s).” Please confirm that “primary team member” refers to firms rather than individuals.
A18. Primary team members refer to individuals.
Q19. On RFP page 9, under 9: Specific Proposal Instructions, Section 3: Technical Proposal, Exhibit 1 –
Qualifications and Past Involvement with Similar Projects, the second bullet provides offerors with a “Limit of five examples and ten pages.” Please confirm that this is a limit of five examples total, and not a limit of five examples “per primary team member.”
A19. Five (5) examples in total.
RFP 125353, ADDENDUM #1 PAGE 5 OF 6
Q20. On RFP page 9, under 9: Specific Proposal Instructions, Section 3: Technical Proposal, Exhibit 4 –
Schedule, does the City have a targeted timeframe in mind for the project duration?
A20. No.
Q21. Please clarify if any firms are precluded from submitting for this solicitation? Please also clarify whether the City anticipates the successful firm(s) for this RFP to be precluded from future procurements associated with subsequent design and/or construction phase services?
A21. No firms are precluded from submitting a proposal to this RFP. No, a firm will not be precluded from a future procurement for this project.
Q22. Please advise if the Organization Chart should be placed in Exhibit 1? Can it be on 11 X 17?
A22. Yes, Organization Chart can be added in Exhibit 1. Paper size is 8 ½ X 11.
Q23. Is there a time limitation on the example projects timeline.
A23. No.
Q24. In Exhibit 1, we are to include 5 projects under bullet 2, and 3 projects under bullet 3. Should these projects be different or can/should these overlap?
A24. Different.
Q25. The RFP mentioned that we need to submit RFP Attachments. What RFP Attachments is being referred to? Can you provide the forms or indicate where they are located?
A25. Attachment 2, Proposal Submission Form. Addendum 1. Documents are located on eVA.
Q26. Should geotechnical investigation be a desktop effort only? Or would you want us to perform some field investigations as well?
A26. Soils map review possibly.
Q27. Does the PM required to have as VA PE?
A27. Yes, for this project.
Q28. Does a fee for the work need to be submitted.
A28. No.
RFP 125353, ADDENDUM #1 PAGE 6 OF 6
All other terms and conditions remain the same.
ACKNOWLEDGMENT OF RECEIPT:
OFFEROR NAME: __________________________________________________________________
AUTHORIZED SIGNATURE: __________________________________________________________
NAME AND TITLE: __________________________________________________________________
NOTE: This Addendum is acknowledged and considered a part of the subject solicitation. A signed copy of this addendum must be included in the response. Failure to do so may result in rejection of the bid or proposal.
Patricia Innocenti, CPPO Procurement Director / Purchasing Agent
File details come from the government source that posted it. Updated .