This document is Addendum No. 1 for the Florida Fish and Wildlife Conservation Commission (FWC) Solicitation No. FWC 24/25-76, titled "Crew Willow Mulching". The addendum provides clarifications and answers to potential bidders' questions regarding equipment specifications for a vegetation mulching project. All responses to the solicitation must be received by 3:00 PM (ET) on Thursday, April 17, 2025, with strict guidelines on equipment usage. The addendum specifically addresses three key questions about equipment, including confirmation that swamp mats can be used in the marsh, a requirement that only mulching heads (not bush hog attachments) are permitted, and a definitive statement that no skid steers will be allowed to operate in the marsh.
The addendum emphasizes technical requirements for the project, notably that all equipment must have under 6 lbs PSI ground pressure. Bidders are informed that pontoon tracks are not mandatory, but ground pressure remains a critical factor. The document clearly restricts equipment options, rejecting alternative cutting attachments like heavy-duty bush hogs and prohibiting skid steers from marsh operations. These detailed specifications suggest the FWC is seeking precise environmental management techniques that minimize ground disturbance while effectively managing invasive vegetation in sensitive marsh ecosystems.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FWC.24.25.76.ITB.Final.pdf | ||
| FWC.24.25.76.ITB.Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Fish and Wildlife Conservation Commission
Commissioners
Rodney Barreto
Chairman
Coral Gables
Steven Hudson
Vice Chairman
Fort Lauderdale
Preston Farrior
Tampa
Gary Lester
Oxford
Albert Maury
Coral Gables
Gary Nicklaus
Jupiter
Sonya Rood
St. Augustine
Office of the
Executive Director
Roger A. Young
Executive Director
Charles “Rett” Boyd
Assistant Executive Director
George Warthen
Chief Conservation Officer
Jessica Crawford
Chief of Staff
850-487-3796
850-921-5786 FAX
Managing fish and wildlife resources for their long-term well-being and the benefit of people.
620 South Meridian Street
Tallahassee, Florida
32399-1600
Voice: 850-488-4676
Hearing/speech-impaired:
800-955-8771 (T)
800-955-8770 (V)
MyFWC.com
DATE: APRIL 10, 2025
ADDENDUM NO.: 1
BID NO.: FWC 24/25-76
BID TITLE: CREW WILLOW MULCHING
UPDATE: QUESTIONS & ANSWERS
The enclosed addendum has been issued for consideration in the preparation of your response to the Florida Fish and Wildlife Conservation Commission’s
(FWC) Solicitation No. FWC 24/25-76, “Crew Willow Mulching”.
All responses to the subject solicitation must be received no later than 3:00
PM (ET) on Thursday, April 17, 2025.
A response received after the exact time specified will not be considered.
Failure to file a protest within the time prescribed in Section 120.57(3), Florida Statutes (F.S.), or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Written notices, formal requests and proceedings must conform with the requirements set forth in
Chapter 28-110, Florida Administrative Code (F.A.C.). Protests must be filed with the Purchasing Office, Fish and Wildlife Conservation Commission, 1875
Orange Avenue East, Tallahassee, Florida 32311-6160 within the time prescribed in Section 120.57(3), F.S. and Chapter 28-110, F.A.C.
Sincerely, Randy Golightly, FWC Procurement Manager
FWC SOLICITATION ADDENDUM 2
BEGIN ADDENDUM
QUESTION #1
Just want to confirm that swamp mats can be used instead of pontoon tracks?
ANSWER #1
Swamp mats can be used in the marsh but are not required. After careful consideration, pontoon tracks are also not a requirement. All equipment must be under 6 lbs PSI ground pressure .
QUESTION #2
The bid packet requires a mulching head. Would you allow a heavy duty bush hog attachment on the long reach excavator will cut up to 8-inch diameter, due to the head speed and that its 8ft wide it will be far quicker and cover more acres per day.
ANSWER #2
After careful consideration, heavy duty bush hog cutting attachments will not be allowed. Only mulching heads will be allowed.
QUESTION #3
We have a 309 excavator with a fecon mulcher head: its ground pressure is 5.5-6 LBS
PSI. We also have 2 skid steers with 3.4-6 LBS PSI. Would these skid steers be allowed to be used as support for the excavator in areas where conditions are appropriate? The skid steers have a production rate 10X of the excavator. This could reflect on our per acre pricing.
ANSWER #3
No skid steers will be allowed to operate in the marsh.
END ADDENDUM