Addendum #1-Q&A-Settles Floor.Bleacher Replac.pdf

PDF 605 KB Posted

Attached to
PUBLIC ANNOUNCEMENT FOR Settles Gym Floor/Bleacher Replacements-RFP-27-053
Solicitation number
RFP-17023
Issued by
St. Johns County, Florida

About this file

This is Addendum #1 (Questions and Answers) for RFP-27-053, issued by the Florida School for the Deaf and the Blind (FSDB) Purchasing Department on September 28, 2026, regarding the Settles Gymnasium Floor and Bleacher Replacements project. The solicitation seeks qualified firms to replace athletic wood flooring and telescoping bleacher systems at the facility. The project scope encompasses demolition and replacement of second-floor athletic flooring across approximately 11,416 square feet with 671 seating capacity. A mandatory pre-response meeting and site visit are scheduled for November 17, 2026 at 11:00 a.m., with attendance limited to qualified teams; drawings and specifications will be available at this site visit. Pre-bid qualification submissions are due October 30, 2026 at 1:45 p.m., and formal proposal submissions are due December 4, 2026 at 1:45 p.m. The selection committee will conduct its review by December 7, 2026, with intent to award advertisement posted by December 8, 2026. Installation is scheduled to commence February 15, 2027, with substantial completion targeted for June 11, 2027 and final completion by July 31, 2027.

The addendum addresses six inquiries from interested vendors regarding project information, plans, specifications, and design parameters. FSDB clarified that the existing gym floor height is 3 inches and confirmed that the flooring basis of design is the Robbins Bio-channel SB system with specified components; any substitution requests must be submitted in writing to the FSDB Purchasing Analyst for approval. Acceptable bleacher manufacturers are limited to Hussey Seating Company, Interkal Inc., and Irwin Seating Company, with other manufacturers requiring FSDB Contract Manager approval. Respondents must be properly licensed in Florida at time of submittal and demonstrate financial capability. A mandatory 5% bid bond or equivalent security is required with proposal submission, and the selected vendor must provide a 100% payment and performance bond prior to contract execution. Certification of compliance with minority and veteran business enterprise participation requirements and non-discrimination certifications are mandatory.

View the file

Other files

File Type Posted
Settles Gym Floor.Bleacher Rplc RFP-27-053.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PURCHASING DEPARTMENT

207 SAN MARCO AVENUE

ST. AUGUSTINE, FL 32084

PHONE (904) 827-2364

WWW.FSDBK12.ORG

REQUEST FOR PROPOSAL (RFP)

SETTLES GYM FLOOR/BLEACHER REPLACEMENTS

RFP-27-053

Addendum #1

Commodity Code(s):

30161700 Flooring 30161702 Wood flooring 30241600 Grandstand bleacher and stair structure components 72152500 Floor laying services 72152508 Wood floor installation and refinishing services 72153100 Athletic and recreational facility construction service

September 28, 2026

Addendum #1, RFP-27-053 – SETTLES GYM FLOOR/BLEACHER REPLACEMENTS

Page | 2

Submission of Questions and Written Responses

The following questions were submitted by Joel Torres Lopez:

Q. “I am interested in the job needed could you please provide some information?”

A. “Firms interested in being considered for this project should access the Solicitation document on our website, Purchasing | FSDB.”

The following questions were submitted by Southeastern Seating, Inc.:

Q. “I’m reaching out regarding the project referenced above and was wondering if it would be possible to obtain a copy of the plans and specifications?”

A. “All necessary information is provided in the solicitation document, which may be obtained on our website, Purchasing | FSDB. Any plans or specifications will be available to qualified vendors at the mandatory site visit.”

The following questions were submitted by Action Floor Systems:

Q. “Please advise the total height of existing Gym floor so we may determine the basis of design system height dimensions to allow for a substitution request for a competitive gymnasium flooring system.”

A. “The height of the existing gym floor is 3 ½ inches. Qualified vendors must submit any substitution requests in writing to FSDB Purchasing Analyst for approval.”

The following questions were submitted by Monteith:

Q. “We are interested in bidding your upcoming renovation project and was curious when the drawings would be available.”

A. “The drawings will be available to qualified vendors at the mandatory site visit, as noted in the Schedule of

Events and Deadlines.”

The following questions were submitted by Florida Commercial Construction LLC:

Q. “Could you direct us to the active project folder containing the complete solicitation, published schedule, required forms and addenda?”

A. “The solicitation document can be found on our website, Purchasing | FSDB and clicking on ‘View Active

Competitive Solicitations’ and navigating to the project folder.”

The following questions were submitted by Specialized Fitness Resources:

Q. “Would be able to provide me access to the plans for this project?”

A. “The drawings will be available to qualified vendors at the mandatory site visit, as noted in the Schedule of

Events and Deadlines.”