Addendum 1 Powell 003.pdf
PDF 106 KB Posted
- Solicitation number
- RFP-785-2300000173-2
- Issued by
- Oldham County, Kentucky
About this file
This document is an Addendum to a Request for Proposal (RFP) issued by the Commonwealth of Kentucky Department for Facilities and Support Services Division of Engineering and Contract Administration for the KASTOW - Powell County #003 project for the Energy & Environment Cabinet Division of Oil and Gas. The addendum includes a list of questions and answers related to the plugging and reclamation procedures for the wells, invoicing and payment terms, and the timeframe for completion of the work and release of the performance bond. Specifically, the standard cement requirement is Portland Type 1/2 Class A Cement, with variations approved only in special cases. Once a well is plugged and reclaimed, the contractor can invoice for that well, and the Commonwealth will pay invoices as the work is completed. The performance bond will be good for two years after the final payment. Contractors have 24 months to plug and seed the wells, and an additional year to establish vegetation.
The document does not provide information on pricing terms, set asides, incumbents, funding requirements or sources, or any other salient financial details related to the contract opportunity.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
REQUEST FOR PROPOSAL: RFP-141-23
FOR: KASTOW – POWELL COUNTY #003
Energy & Environment Cabinet Division of Oil and Gas
DATE: November 8, 2022
ADDENDUM NO. One (1)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Attached to this addendum is the list of questions and answers.
END OF ADDENDUM
REQUEST FOR PROPOSAL: RFP-141-23
For: KASTOW – POWELL COUNTY #003
Energy & Environment Cabinet Division of Oil and Gas
Kristi Sharp, Strategic Procurement Branch Manager Division of Engineering and Contract Administration
KASTOW
RFP's
Kentucky Energy and Environment Cabinet
Addendum No. 1
QUESTION: RESPONSE:
1. What type of cement is required in the plugging procedure. Is it
Portland Type 1/2 Class A Cement or is a blended cement such as 50/50 Paz (50% Portland Type 1/2 and 50% fly ash) acceptable?
Lawrence
#002
Class A Cement is the standard KDOG requirement, variation can be approved only in special cases (e.g.
H2S well).
2. Once well has been plugged and reclaimed, can that particular well be invoiced? Will state pay invoices as wells are plugged or will it be after all work is completed and reclaimed?
Lawrence
#002
Yes, once the well has been plugged and seeded, an invoice may be submitted. Invoices will be paid per well as long as all required documents are submitted and approved.
3. What is the timeframe for the release of the bond once the work is completed?
Lawrence
#002
The bond shall be good for two (2) years following the date on which the final payment is made.
4. Once bid is awarded, what is timeframe for completion? Lawrence
#002 and all packages in
6th round
In the 6 th round of RFPs (Lawrence #003, Clinton
#001, Lee #002, Metcalfe #001, Muhlenberg #002, Powell #003, Russell #001 and Union #002), contractors have two (2) years (24 months) to plug and seed the wells and another year to establish vegetation.