_Addendum___1_Playground_Surface_Replacement.docx.pdf
PDF 60 KB Posted
- Attached to
- Playground Surface Replacement
- Solicitation number
- EV00018088
- Issued by
- Suffolk County, Massachusetts
About this file
This is an Addendum to an Invitation for Bids issued by the City of Boston, acting through Boston Public Schools' Planning & Engineering/Facilities Management division, for playground surface replacement and related work at seven school sites. The project encompasses Dudley Street Neighborhood Charter School, James Hennigan K-8 School, Joyce Kilmer K-8 School, Ellis Mendell Elementary School, Joseph P. Manning Elementary School, Donald McKay K-8 School, and Richard J. Murphy K-8 School. Sealed bids are due November 12, 2026 at 12:00 p.m. Boston time, with submissions accepted through the City Supplier Portal (boston.gov/procurement) or hand-delivery to Campbell Resource Center, 1216 Dorchester Avenue, 2nd Floor, Dorchester. Bid documents became available October 28, 2026 at 12:00 p.m. A pre-bid site viewing is planned. Contract award is anticipated within fourteen business days after bid opening, with work commencing March 1, 2027, substantial completion by September 31, 2027, and final completion by December 31, 2028. Bidding inquiries should be directed to Rosamund Bloom at 617-635-9170 or bidderinfo@bostonpublicschools.org.
Contractors must hold a Massachusetts DCAMM Certificate of Eligibility for general construction with appropriate capacity rating, as the project exceeds the $150,000 DCAMM contract threshold. The estimated project cost is listed as $1.1 million in specifications, though the submission confirmation indicates $2.0 million. No minority-, women-, or disadvantaged-business set-asides are identified. Bids require a 5% deposit by certified check, treasurer's check, or bid bond, and the successful bidder must furnish performance and payment bonds at 100% of the contract price. Bidders must submit three or more references from similar contracts completed within the past two years plus bank references on Bid Response Form CM-07. Massachusetts prevailing wage rates apply throughout with weekly certified payroll requirements. The Boston Jobs, Living Wage, and Prevailing Wage Ordinance applies, requiring covered vendors with 25 or more full-time employees to pay at least $19.36 per hour effective July 1, 2026, and to complete Form WAGE-2 at award. All employees must complete a 10-hour OSHA construction safety course before starting work. Material Safety Data Sheets must accompany bids for hazardous-substance materials. Vehicles exceeding weight thresholds must carry side under-ride guards, convex blind spot mirrors, cross-over mirrors, and warning signage under City of Boston Ordinance Chapter IV, Section 4-8.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BOSTON PUBLIC SCHOOLS
OFFICE OF FACILITIES MANAGEMENT
1216 Dorchester Avenue Dorchester, Massachusetts 02125
ADDENDUM NO. #1
Playground Surface Replacement at various Boston Public Schools
Event ID# EV00018088
11/09/2026
To: Prospective Bidders:
The attention of bidders submitting proposals for the above project is called to the following addendum to the Contract Bid Documents. The items set forth herein, whether of omission, addition, substitution, or clarifications are all to be included in and form a part of the proposal submitted.
THIS ADDENDUM FORMS A PART OF THE CONTRACT DOCUMENTS AND
MODIFIES THE ORIGINAL BIDDING DOCUMENTS DATED October 28, 2026, AS
NOTED BELOW.
ALL BIDDERS SHALL ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPACE
PROVIDED ON THE BID FORM. FAILURE TO DO SO MAY SUBJECT THE BIDDER TO
DISQUALIFICATION.
Clarification:
The project Playground Surface Replacement at various Boston Public Schools bid deadline has been extended to Thursday, November 19, 2026 at noon. All bids must be received by the revised submission deadline. Bids received after the new deadline will not be accepted.
END OF ADDENDUM NO. #1
File details come from the government source that posted it. Updated .