Addendum #1- Nesmith Building - Student Center Renovation.pdf
PDF 191 KB Posted
- Solicitation number
- 124-SCC04102025
- Issued by
- Clay County, North Carolina
About this file
This document is Addendum #1 for the Nesmith Building - Student Center Renovation Project issued by Southeastern Community College located in Whiteville, North Carolina. The addendum provides clarifying responses to potential bidder questions regarding the Request for Qualifications (RFQ) for a design-build project. Key details include confirmation that this is an RFQ seeking only qualifications, not a Request for Proposal (RFP), with submissions to be made through the electronic vendor portal (eVP). The college currently has no established target timeframe for design-build team selection or project completion, and no preliminary studies or design efforts have been completed for the project.
The addendum specifies that only the primary design-build firm contracting directly with the college needs to submit an SF-254 form, which will not count against the 40-page submission limit. The project will follow standard State Construction Office review processes, and the college emphasizes that no fee information is being requested at this stage. Firms are instructed to submit a letter of interest and SF-254 through eVP only, with an understanding that the project will involve renovating the student center and will be subject to full design review by the State Construction Office under their typical procedures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SCC04102025 Design-Build RFQ Nesmith Renovation Project 2794.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
4564 Chadbourn Hwy • PO Box 151 • Whiteville, NC 28472 sccnc.edu An equal opportunity/ affirmative action institution.
Southeastern Community College
Bid #124-SCC04102025
Nesmith Building – Student Center Renovation Project
Addendum #1
1. Has a study been completed for this project? If so, would it be possible to share the study with us?
a. Response: A study has not been completed for this project at this time.
2. Is there an expanded RFQ available for this project?
a. Response: No, there is not an expanded RFQ available.
3. The eVP listing indicates/requests submittal of an SF-254, however with this being Design-Build, there is also a request for the Design-Build submittal via the vendor portal. Do you want both? or will just the Design-Build portion suffice?
a. Response: You will submit the letter of interest and SF-254 through eVP only.
4. Please confirm that this is an RFQ, not an RFP. So that you are not requesting/requiring any fee information at this time.
a. Response: This is an RFQ, we are only requesting qualifications at this time.
5. Is there a target timeframe for both selection of Design-Build team, and also completion of the project?
a. Response: Currently, there is no established target timeframe for the selection of the
Design-Build team or for the completion of the project.
6. Does a form SF254 need to be provided for every firm on our team or just for the design-build firm that will contract with the community college directly? Also does the SF254 count against the 40 page limit?
a. Response: Just the design-build firm that will contract with the college directly at this
4564 Chadbourn Hwy • PO Box 151 • Whiteville, NC 28472 sccnc.edu An equal opportunity/ affirmative action institution.
time. The SF-254 will not count toward the page limit.
7. Will there be a full design review by the State Construction Office under their typical process?
a. Response: Yes, this project will follow State Construction Office processes.
8. Have there been any pre-design or conceptual design efforts completed for this project?
a. Response: No design efforts have been completed at this time.
File details come from the government source that posted it. Updated .