Addendum 1_ ITB_ 26_09_005 Construction of Ro.pdf

PDF 226 KB Posted

Attached to
Construction of Roundabout at Colham Ferry Road & Astondale Road
Solicitation number
PE-70800-NONST-2026-000000035
Issued by
Oconee County, Georgia

About this file

This is Addendum 1 to Invitation to Bid (ITB) 26-09-005 issued by the Oconee County Board of Commissioners for construction of a roundabout at the intersection of Colham Ferry Road and Astondale Road. The addendum, dated October 24, 2025, modifies the original solicitation documents from September 30, 2025, and addresses 20 questions submitted by prospective bidders prior to the October 20, 2025 deadline at 5:00 pm. The project requires construction of a roundabout with associated roadway improvements on four legs, including paving, graded aggregate base installation, truck apron concrete (stamped red), and median work. The project duration is 180 calendar days, with work hours unrestricted Monday through Saturday and no work permitted on Sunday. The project disturbs less than 1 acre and therefore does not require a Notice of Intent filing with the Georgia Environmental Protection Agency. Oconee County will provide material testing and construction inspection services; contractors are not required to hire Construction Quality Assurance services.

Key clarifications in the addendum address paving scope, materials, and construction methodology. Rumble strips shown on the drawings have been removed from the project scope with no pay item added. Full-depth paving is required only for new paved surfaces outside existing pavement limits, while variable-depth surfacing applies within existing paved areas to meet line and grade requirements; the Schedule of Values quantities account for these conditions. Graded Aggregate Base (GAB) item 0015 will be measured and paid per compacted square yard of 8-inch thickness. The contractor may remove the existing corrugated metal pipe and backfill the trench or alternatively plug and fill it with flowable fill. Variable message boards will be provided by Oconee County. Contractors are responsible for inspecting field conditions and pricing fence replacement in-kind, anticipating new fence installation. The contractor maintains responsibility for traffic maintenance and staging paving work to sustain traffic flow throughout construction. CAD files are available at a designated Hightail link.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Oconee County Board of Commissioners

Addendum 1

DATE: October 24, 2025

TO: All Prospective Bidders

FROM: Procurement Officer

RE: ITB# 26-09-005 Construction of Roundabout at Colham Ferry Road & Astondale Road

The following changes are to be incorporated into the solicitation documents dated September 30, 2025. All those receiving this addendum should modify their documents to show the below described changes.

Responses to questions received prior to the deadline of October 20, 2025 at 5:00 pm.

All questions shall be directed to Ms. Jessica Ellis, Procurement Officer via email at ocbids@oconee.ga.us

1. Page C401 shows rumble strips, can a pay item be added?

The Bidder is instructed to not include pricing for rumble strips. The proposed rumble strips shown on the drawings have been removed from the project scope.

2. Page C201 hatching shows most of the road being "Full Depth Paving," can this be clarified since the typicals call for overlay?

The typical sections on Sheet C003 are not comprehensive. Full depth replacement is not required for the full limits hatched in grey on Sheet C201. Full-depth replacement is only required for all new paved surfaces outside the limits of the existing paved areas. Variable depth surfacing is required within the limits of the existing paved surfaces to meet line and grade of the proposed roadway improvements. The quantities provided in the Schedule of Values are intended to provide for these conditions.

3. Can a pay item be added for variable message boards?

Variable message boards will be provided by Oconee County.

4. What is the estimated utility adjustment schedule?

There are no known significant utility conflicts.

5. Is a NOI required for this project?

The proposed improvements are less than 1 acre of disturbance and therefore does not require a Notice of Intent (NOI) to be filed with the Georgia Environmental Protection Agency (GAEPD).

6. Can item number 0015 GAB be changed from square yards to tons?

No. This quantity will be measured and paid for 8” thick of GAB per square yard, compacted, installed, and accepted.

7. Page C101 calls out the existing CMP as remove, but there is a flow fill item. What is the intent of the existing pipe and what is the flow fill intended for?

The Contractor may choose to remove the CMP pipe, backfill the resulting trench in appropriate lifts and ensure that the final condition meets the compaction requirements of the project. Or the contractor may select to plug and fill the CMP with flowable fill.

8. What are the work hours for this project?

Unrestricted Monday through Saturday, no work on Sunday.

9. Can a detail for the electric fence be provided?

No. The Bidder is responsible for inspecting the field conditions and pricing this item to replace the existing electric fence in-kind as the fence currently exists.

10. Are either the truck apron or medians stamped and/or colored? Please provide detail.

Truck aprons will be stamped red. No color or stamps on medians.

11. Are you able to provide any CAD files?

Yes. CAD files are posted at the following link: https://spaces.hightail.com/receive/KJ2IIw9kPd

12. Is the Roundabout Truck apron concrete to be constructed as per RA-2 details? (Red color cobble pattern stamped concrete) Please refer to the answer to question 10.

13. Please confirm all widening area to be constructed with 4” inch thick binder and 1.5” inch Topping asphalt thickness only?

No. All widening will require the full paving section as shown on Sheet C002, including the required Graded

Aggregate Base (GAB) shown on Sheet C002.

14. Typical section#3 shows full depth paving(under light grey color on sheet no. C-201); around the outer side of truck apron from sta.30 to sta.32+63.

The typical sections on Sheet C003 are not comprehensive. Full depth replacement is not required for the full limits hatched in grey on Sheet C201. Full-depth replacement is only required for all new paved surfaces outside the limits of the existing paved areas. Variable depth surfacing is required within the limits of the

15. C-201 sheet shows (under light grey color area) full depth paving on all four legs(roads) where the current traffic is running. Please advise how County is planning to build full depth sections under live traffic since plan does not show any temp. road widening or traffic shift in order to construct full depth sections around Roundabout truck apron and All on Four legs of roadways?

The typical sections on Sheet C003 are not comprehensive. Full depth replacement is not required for the full limits hatched in grey on Sheet C201. Full-depth replacement is only required for all new paved surfaces outside the limits of the existing paved areas. Variable depth surfacing is required within the limits of the existing paved surfaces to meet line and grade of the proposed roadway improvements. The quantities provided in the Schedule of Values are intended to provide for these conditions. The Contractor will be responsible for maintenance of traffic and staging full depth paving and overlay in a manner that maintains traffic throughout the duration of the project.

16. Please provide exact location of Full depth constructions/sections in plan in relation to current traffic flow.

Full-deep replacement will be required for all areas outside the limits of the existing paved surfaces.

Variable depth surfacing is required within the limits of the existing paved surfaces to meet line and grade of the proposed roadway improvements.

17. Typical section 1 & 2; details for overlay and full depth sections are conflicting with the details given on sheet# C-201 for Full depth sections showing under light grey color area. Please confirm the location of full depth sections showing correct area of Full depth construction around roundabout and on all Four side roads.

The typical sections on Sheet C003 are not comprehensive. Full depth replacement is not required for the full limits hatched in grey on Sheet C201. Full-depth replacement is only required for all new paved surfaces outside the limits of the existing paved areas. Variable depth surfacing is required within the limits of the

18. Please confirm project duration is 180 calendar days.

180 calendar days is correct.

19. Are you able to provide anymore details about the field fence woven wire and field fence smooth wire, electric?

Will the contractor be installing new fencing, or will they be relocating and modifying the existing fencing?

The Bidder is responsible for inspecting the field conditions and pricing this item to replace the existing electric fence in-kind as the fence currently exists. The Bidder should anticipate installing new fence.

20. Will the contractor be required to hire any CQA services for the completion of this project?

The Bidder/Contractor is not required to hire any Construction Quality Assurance (CQA) services. Oconee

County will provide material testing and construction inspection services as needed to accept the work completed by the Contractor.