This document is an addendum to an Invitation for Bid (IFB) for the installation of a solar PV system at the Range Road Armory in Rapid City, South Dakota. It is issued by the Department of the Military, State of South Dakota.
The addendum includes updates to the instructions to design-builders, such as a requirement for BABA-compliant products, information on power usage and availability at the site, and details on the proposal submission and evaluation process. The project is to be awarded based on a "best value" selection formula considering the design-builders' qualitative, management, and price proposals. Bidders must provide proposal security, and the successful design-builder will be required to furnish performance and labor/materials bonds. The project is subject to South Dakota procurement laws and regulations, and bidders must comply with applicable standards and codes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IFB Document.pdf | ||
| Attachment- Electrical Interval Data 2021 thru 2024.xlsx | XLSX spreadsheet | |
| Addendum 2-IFB Document.pdf | ||
| Project Manual and Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE
MILITARY
STATE OF SOUTH DAKOTA
ADDENDUM #1
Project: Install Solar PV – Range Road Armory Rapid City, SD
CFMO# 466405
Letting: 4:00 P.M. MT, Thursday August 22, 2024 Attn: Kyle Roe https://www.sd.gov/cs?id=sc_cat_item&sys_id=b9975ff21b7bca506cbca93be54bcb73
Public Viewing:
https://state-sd.zoom.us/j/2373768141?omn=98211341286
Meeting ID: 237 376 8141
Owner: State of South Dakota Department of the Military Construction and Facilities Management Office
SCOPE OF THIS ADDENDUM:
The following becomes a part of the original Project Manual, taking precedence over items that may conflict. The bidder shall note receipt and make acknowledgment of the addendum in their bid and incorporating its provisions in their bid price.
ITEM NO. 1:
ADD – Specification 00 00 05 – INSTRUCTIONS TO DESIGN-BUILDERS to the project manual. The specification is attached to this addendum.
ITEM NO. 2:
Pre-bid meeting attendance is attached.
Questions asked and responses given:
1. All products used on this project must be BABAA COMPLIANT.
2. Have there been any conversations with Black Hills Power on interconnection agreements and bi-directional meters? Answer: NO
3. When was the wooden power pole closest to the building last tested? Answer: UNKNOWN
4. Is WIFI available at the building: Answer: No commercial internet is or will be available for this project to interface with ever. Solar monitoring system and energy meter must interface with existing Schneider Electric Automation Server.
5. Can the power usage be shared? See below peak demand chart over the past two years Month / Yr Electricity kWh Demand kW
Jul-24 8960 38.4 Jun-24 9440 43.2
May-24 6560 28 Apr-24 7520 31.2
Mar-24 6800 28 Feb-24 7360 25.6 Jan-24 8880 31.2 https://www.sd.gov/cs?id=sc_cat_item&sys_id=b9975ff21b7bca506cbca93be54bcb73 https://state-sd.zoom.us/j/2373768141?omn=98211341286
DEPARTMENT OF THE
MILITARY
STATE OF SOUTH DAKOTA
Dec-23 7600 31.2 Nov-23 6400 32 Oct-23 7680 25.6 Sep-23 8960 44.8 Aug-23 10000 41.6
Jul-23 8960 24.8 Jun-23 9360 36.8
May-23 8000 28.8 Apr-23 8240 28
Mar-23 8880 32.8 Feb-23 9840 31.2 Jan-23 9760 22.4 Dec-22 8960 31.2 Nov-22 7120 30.4 Oct-22 7920 27.2 Sep-22 9120 32.8 Aug-22 11600 50.4
DEPARTMENT OF THE MILITARY
CULLEN B. JORGENSEN
Engineering Manager
Cullen Jorgensen (Aug 15, 2024 15:01 MDT)
00 00 05 – INSTRUCTIONS TO DESIGN-BUILDERS 1 June 2024
INSTRUCTIONS TO DESIGN-BUILDERS
1. Examination of Plans, Specifications and Site.
Design-Builders should carefully examine the site of the proposed work, existing conditions, and the performance criteria governing the project. The submission of proposals is conclusive evidence that the Design-Builder has investigated and is satisfied as to the conditions to be encountered; the character, quality, and scope of the proposed work; the quality and quantity of the materials to be furnished; and the requirements of the proposal.
The project manual is to be used only with respect to this project and are not to be used for any other project or purposes other than preparing proposals for this project; the project manual will not be disseminated to any person or entity for purposes other than obtaining proposal information without the express written approval of the state; all information contained in the project manual is confidential; and should the Design-Builder disseminate the project manual to an individual or entity for purposes of obtaining proposal information, the Design-Builder will require that individual or entity to adhere to the terms set forth herein. The Design-Builder, however, assumes no liability for the misuse of the project manual by such third party or such third party’s failure to comply with the provisions contained herein.
Any copies of the project manual obtained directly from the State will be returned to the Office of the Engineering Manager immediately after the State provides notice that Design-Builder will not be awarded a agreement, or thirty
(30) days after the price proposal opening for the project, whichever occurs first. Any copies of the project manual made by the Design-Builder will be destroyed immediately after the State provides notice that Design-Builder will not be awarded a agreement, or thirty (30) days after the price proposal opening for the project, whichever occurs first. If Design-Builder does not submit a proposal, Design-Builder will fulfill the requirements previously outlined on or before the date of the price proposal opening. Should Design-Builder be awarded a agreement for construction of the project, Design-Builder does not need to return or destroy project manual until after completion of the project.
2. Submission of Proposals.
Each firm submitting proposals shall submit a Qualitative Proposal, Management Proposal, and Price Proposal.
Proposals shall be segmented into three packages:
A. Qualitative Proposal:
1) A Qualitative Proposal shall include preliminary design drawings, outline specifications, technical reports, calculations, permit requirements, schedule, information based on the performance criteria, and other data pertaining to the Request for Design-Build Proposals.
2) Qualitative proposals may be delivered to the Engineering Manager via hard copy or electronically via email or USB removable storage media with the Design-Builder clearly identified on the removable media.
3) Each firm shall clearly identify the deliverable either on the outside of the sealed envelope or the electronic file with the words “Qualitative Proposal” with information set forth below.
4) The Qualitative Proposals shall not contain any information identifying the Design-Builder or any member of their team. Any Proposal that contains the name of the Design-Build team or any members of that team may be disqualified.
B. Management Proposal:
1) A Management Proposal will include how the Design-Build team intends to manage the project, including but not limited to the firm’s approach to design-build, project management philosophy, plan for executing the project, project schedule development and monitoring approach, project controls and how the firm plans to achieve the project requirements, timeline, team members, and contingencies for emergencies.
2) Management proposals may be delivered to the Engineering Manager via hard copy or electronically via email or USB removable storage media with the Design-Builder clearly identified on the removable media.
3) Each firm shall clearly identify the deliverable either on the outside of the sealed envelope or the electronic file with the words “Management Proposal” with information set forth below.
C. Price Proposal:
1) Each firm shall submit its Price Proposal via the electronic bidding platform (details can be found in the Price
Proposal Form).
2) Price Proposals shall include one lump sum cost for all design and construction of the proposed project.
3) Price Proposals shall be submitted via electronic bidding platform.
D. Disqualification:
1) Any proposer may be disqualified due to breach of proposal procedures.
00 00 05 – INSTRUCTIONS TO DESIGN-BUILDERS 2 June 2024
3. Modification of Proposals.
A. Qualitative and Management Proposals may be modified by mail or email before the time set forth in the Request for Design-Build Proposals. No proposal shall be changed or altered by telephone. No oral changes, alterations or conditions will be accepted under any circumstance.
B. Price Proposals may be modified, via the electronic bidding platform, at any time not later than the time set for the opening of price proposals. No Price Proposal shall be changed or altered by telephone. No oral changes, alterations or conditions will be accepted under any circumstance.
4. Proposal Security.
Each Price Proposal over $100,000.00 must be accompanied by a proposal security as follows:
A. Certified Check, Cashier's Check or Draft. A certified check, cashier's check or draft for five percent (5%) of the amount of the proposal, including all add alternates, such check to be certified or issued by either a State or National Bank and payable to said public corporation or officer. A certified check, cashier’s check or draft shall be received at the Office of the Engineering Manager no later than the date and time of the Price Proposal opening.
B. Proposal Bond. In lieu of a certified check as a proposal guarantee, a proposal bond of ten percent (10%) of the total amount of the proposal, including all add alternates, may be furnished by the Design-Builder. See Exhibit "D" for Proposal Bond form. Such bond to be issued by a surety authorized to do business in the State of South Dakota.
Such bond shall be payable to said public corporation or officer as guaranty that such Design-Builder will enter into a agreement with said public corporation, its Board or officers thereof, in accordance with the terms of such letting and Price Proposal in case such Design-Builder be awarded the agreement. A copy of the proposal bond shall be attached to the Price Proposal, via the electronic bidding platform.
No Design-Builder shall be required to leave his/her certified check or other guaranty, or proposal bond posted for a longer period than thirty (30) days if the proposal is not accepted. The certified check or other guaranty of the successful Design-Builder shall be returned to the Design-Builder forthwith upon the execution of the agreement and surety herein provided for.
5. Withdrawal of Proposal.
Any Qualitative and Management Proposal may be withdrawn by letter, email or in person, at any time before the time specified in the advertisement therefor. Withdrawal of a Qualitative and Management Proposal does not prejudice a Design-Builder’s right to submit a new Qualitative and Management Proposal within the time designated for the submission of proposals. No proposal may be withdrawn after the time designated in the Request for Design-Build Proposals. The email address for withdrawing a proposal is cullen.jorgensen@state.sd.us.
Any Price Proposal may be withdrawn, via the electronic bidding platform, at any time before the time specified in the advertisement therefor. Withdrawal of a Price Proposal does not prejudice a Design-Builder’s right to submit a new Price Proposal within the time designated for the submission of proposals. No proposal may be withdrawn after the time designated in the Request for Design-Build Proposals for the opening of Price Proposals.
6. Request for Interpretation.
Any person who plans to submit a proposal on the project may submit to the Owner a written request for an interpretation of any part of the Performance Criteria. Requests for interpretations shall be made not less than ten (10) days prior to the time set for submission of proposals. Any interpretation will be in writing and furnished to each person receiving Performance Criteria for submitting proposals. The Owner will not be responsible for any other explanation or interpretation.
7. Preference for South Dakota Products, Labor and Materials.
By virtue of statutory authority in SDCL § 5-18A-25 preference will be given to South Dakota products, labor and materials as provided by law.
8. Opening of Proposals.
Proposals and modifications will be received until the time designated in the Request for Design-Build Proposals. The proposals received within the designated time will be numbered and separated by the Engineering Manager. The Qualitative Proposal will be distributed to the Technical Review Committee in accordance with the procedures set forth in this document.
mailto:cullen.jorgensen@state.sd.us
00 00 05 – INSTRUCTIONS TO DESIGN-BUILDERS 3 June 2024
9. Evaluation of Qualitative Proposal.
Procedure A. A Technical Review Committee will be selected to evaluate and score all Qualitative Proposals.
B. Each properly submitted Qualitative Proposal will be assigned a number by the Engineering Manager. The
Engineering Manager will distribute the numbered proposals to the Technical Review Committee. (It is intended that the committee members do not know the identity of the Design-Builder during their review and scoring of the Qualitative Proposal).
Evaluation of Qualitative Proposal A. The Technical Review Committee will consider the following parameters when scoring the Qualitative Proposals:
1. Compliance with Performance Criteria. (70 pts)
2. Proposed project schedule. (30 pts)
B. The Committee members will submit their criteria scores for each design-builder to the Engineering Manager. The Engineering Manager will average the scores of the Committee Members for each Design-Builder to arrive at a single score for each Design-Builder. The maximum score for any proposal will be 100 points.
10. Evaluation of Management Proposals.
Procedure A. A Technical Review Committee will be selected to evaluate and score all Management Proposals.
B. Each properly submitted Management Proposal will be distributed to the Technical Review Committee.
Evaluation of Management Proposal A. The Technical Review Committee will consider the following parameters when scoring the Qualitative Proposals:
1. Project approach and methodology to meet the project requirements; (15 pts)
2. Project teams specialized expertise, capabilities, and technical competence to meet the project requirements;
(15 pts)
3. Specialized expertise, capabilities, and technical competence as demonstrated by the proposed approach and methodology to meet the project requirements; (10 pts)
4. Resources available to perform the work, including any specialized services and their roles within the project, within the specified time limits for the project. Resumes of team member’s professional accomplishments and experience with similar projects to be included; (10 pts)
5. Record of past performance, including price, and cost data from previous projects, quality of work, ability to meet schedules, cost control, and contract administration. All projects within the last 5 years with the Dept. of the Military must be included; (10 pts)
6. Availability to the project locale; (10 pts)
7. Familiarity with the project locale; (5 pts)
8. Proposed project management techniques; (10 pts)
9. Ability and proven history in handling special project constraints (Projects of Similar Scope, Time/Schedule, and Cost). (15 pts) B. The Committee members will submit their criteria scores for each design-builder to the Engineering Manager. The
Engineering Manager will average the scores of the Committee Members for each Design-Builder to arrive at a single score for each Design-Builder. The maximum score for any proposal will be 100 points.
11. Best Value Selection and Award for Design-Build Services.
The Engineering Manager will publicly open the Price Proposals, submitted via the electronic bidding platform, and divide each firm’s proposed price by the combined score given by the Committee to obtain an “adjusted price”. The firm selected will be that firm whose adjusted price is lowest. An example of the “best value” selection formula follows:
Firm Average
Qualitative Score
Average Management Score
Combined Score
Proposed Price Adjusted Price
A 90 84 87 $6.9 million $7.93 million (6.9 ÷ 0.87) B 79 67 73 $6.3 million $8.63 million (6.3 ÷ 0.73) C 84 86 85 $6.8 million $8.00 million (6.8 ÷ 0.85)
(Award to Firm A at $6.9 million) (Sample calculation - $6.9 million/.87 = $7.93 million)
00 00 05 – INSTRUCTIONS TO DESIGN-BUILDERS 4 June 2024
12. Award of Design Build Services.
Proposals, Evaluation, Acceptance, Notice: After obtaining and evaluating proposals according to the criteria and procedures set forth in the Request for Proposals, the State may accept the proposal most advantageous to the State as determined above. Acceptance of a proposal will be by written notice to the design-builder which submitted the accepted proposal. At the same time notice of acceptance is delivered, the public corporation will also inform, in writing, the other design-builders that their proposals were not accepted. If the agreement is awarded, it will be awarded to the responsible design-builder submitting the “adjusted” lowest Price Proposal which complies with the Request for Design-Build Proposals and with these instructions. The successful design-builder will be notified within thirty (30) calendar days of the date Price Proposals are opened. After notice of award, the successful builder will be presented with an agreement. The agreement will require the completion of work according to the Plans and Specifications and the Agreement Documents. Conditional Price Proposals will not be accepted.
13. Rejection of Proposals.
The State may reject any and all proposals, except for the purpose of evading the provisions of this section. The State may solicit new proposals using the same or different performance criteria, budget constraints, or qualifications.
Proposals may be rejected if they show any alteration of form, additions not called for, conditional proposals, incomplete proposals, unexplained erasures, or irregularities of any kind. The State may waive any informality in the proposals received. When proposals are signed by an agent other than an authorized corporate officer or member of a partnership, a power of attorney must be filed with the proposal. Otherwise, the proposal will be rejected as irregular and unauthorized. If there is reason to believe that collusion among the Design-Builders exists, any or all proposals may be rejected. The State reserves the right to reject all proposals if in the judgment of the Engineering Manager it is in the best interest of the State.
14. Relief from Mistake in Price Proposal.
A Design-Builder claiming a mistake in a proposal must give the State written notice of the alleged mistake within five calendar days after the proposals are opened, specifying in detail how the mistake occurred. Relief will only be granted for clerical or mathematical mistakes which can be documented to the satisfaction of the Engineering Manager.
15. Consideration of Bid Proposals.
At the time of opening bid proposals, the State will verify the design-builder is prequalified for the specified work type and the design-builder’s bidding capacity at that time is sufficient to handle the work for which the design-builder submitted a bid proposal. The State reserves the right to refuse to accept a bid proposal for any of the following reasons:
A. Lack of competency or adequate machinery, plant, or other equipment, as shown by the Agreementor’s
Prequalification Statement;
B. Uncompleted work which the State determines, in its sole discretion, may hinder or prevent the prompt completion of additional work;
C. Failure to pay or satisfactorily settle any legal obligation due for labor or material on any agreement at the time of issuance of bid;
D. Failure to comply with the State’s prequalification regulations;
E. Default under any previous agreement or agreements;
F. Debarment by the State or the federal government;
G. Disqualification by the State. The following reasons will be considered sufficient for disqualifying a design-builder and rejecting the bid proposal or bid proposals:
1. Submittal of more than one bid proposal for the same work from an individual, firm, or corporation under the same or different name; or,
2. Evidence of collusion among design-builders. A participant in collusion will not receive recognition as a design-builder for future work with the State until reinstated as a qualified design-builder;
H. Lack of overall bidding capacity as established by the Agreementor’s prequalification statement, considering the uncompleted work currently under agreement;
I. Lack of per agreement bidding capacity as established by the Agreementor’s prequalification statement; or J. Unsatisfactory performance on previous work or any current agreement or agreements consisting of, but not limited to:
1. Noncompliance with agreement specifications, agreement requirements, or Engineer's directives;
2. Failure to complete work on time;
3. Instances of substantial corrective work prior to acceptance;
4. Instances of completed work that requires acceptance at reduced pay;
00 00 05 – INSTRUCTIONS TO DESIGN-BUILDERS 5 June 2024
5. Production of work or materials not meeting required specifications, and when applicable, requiring price reductions or corrective work;
6. Failure to provide adequate safety measures or appropriate traffic control that endangers the safety of the work force and public;
7. Questionable moral integrity as determined by the Attorney General of the State, or the State; or,
8. Failure to reimburse the State for monies owed on any previously awarded agreement including any agreement where the prospective design-builder is a party to a joint venture and the joint venture has failed to reimburse the State for monies owed.
After opening, the State will compare the bid proposals on the basis of the summation of the products of the quantities shown in the bid proposal by the unit bid prices. The State will make results of such comparisons available to the public. In the event of a discrepancy between unit bid prices and extensions, the unit bid price will govern.
The State reserves the right to reject any bid proposal, the right to waive technicalities, and the right to reject all bid proposals and advertise for new bid proposals, if in the sole judgment of the State the rejection or waiver will promote the best interest of the State.
16. Responsibility.
The Owner may make such investigations as he/she deems necessary to determine the ability of the Design-Builder to perform the work, and the Design-Builder shall furnish to the Owner all such information and data for this purpose as the Owner may request. The Owner reserves the right to reject any proposal if the evidence submitted by, or investigation of, such Design-Builder fails to satisfy the Owner that such Design-Builder is properly qualified to carry out the obligations of the agreement and to complete the work contemplated therein.
17. Nonresident Proposals.
SDCL § 5-18A-26, provides that the Agreement shall be let to the lowest responsible Design-Builder; provided, however, a resident Design-Builder may be allowed a preference on any such agreement as against the proposal of any Design-Builder from any other State or foreign province which enforces or has a preference for resident Design- Builders. The amount of the preference given to the resident Design-Builder shall be equal to the preference in the other state.
18. Subcontractor Certification.
SDCL§ 5-18B-6, provides that prior to execution of a public improvement project a successful design-builder shall certify on the prescribed form (Exhibit "G"):
A. That no more than twenty-percent of the cost of labor included in the agreement is being provided by nonresident subcontractors; or B. That more than twenty percent of the cost of labor included in the agreement is being provided by nonresident subcontractors because resident contractors are not available and at competitive prices.
19. Execution of Agreement.
Within ten (10) calendar days after the proposed agreement is presented to the successful Design-Builder for execution, the successful Design-Builder must execute the agreement documents and, if the Agreement is for more than $100,000.00, provide a performance and labor and material payment bond.
20. Performance & Labor and Material Payment Bond.
If the Agreement is for more than $100,000.00, provide a performance and labor and material payment bond produced by a South Dakota licensed insurance producer (agent) and issued by a South Dakota licensed surety in an amount not less than the amount of the awarded agreement. The performance and labor and material payment bond Surety or Sureties shall meet all requirements of South Dakota Law.
This bond is to secure the faithful performance of the agreement and the payment of those to whom the Design- Builder may become legally indebted for labor, materials, tools, equipment, or services of any kind used or employed by the Design-Builder in performing the work. The surety bond shall be on the form attached hereto as Exhibit "E".
(Failure on the part of the Design-Builder to furnish such bond in the time stated shall be cause for consideration by the State of awarding the Agreement to the second low Design-Builder and the retention of the proposal deposit.)
00 00 05 – INSTRUCTIONS TO DESIGN-BUILDERS 6 June 2024
21. Power of Attorney.
Attorneys-in-fact who sign proposal bonds or agreement bonds must file with each bond a certified and effectively dated copy of their power of attorney.
22. Default.
The failure to execute the agreement documents or to furnish bonds required by these instructions within ten (10) calendar days after the proposed agreement is presented for execution constitutes a default. In the event of a default, the State may award the agreement to the Design-Builder with the next lowest adjusted price or may re-advertise for Design-Builder’s. The State may charge against the defaulting Design-Builder the difference between the amount of the proposal and the amount for which a agreement for the work is subsequently executed plus the State’s additional administrative cost necessitated by the Design-Builder’s failure to execute the Agreement Documents, irrespective of whether the amount thus due exceeds the amount of the proposal bond. If a more favorable proposal is received by re-advertising, the defaulting Design-Builder shall have no claim against the State for a refund.
23. Commencement of Work/Time of Completion.
The Design-Builder shall commence work under the agreement within ten (10) consecutive calendar days after issuance of written Notice to Proceed and shall substantially complete all work under the agreement terms noted in the Criteria Package.
24. Liquidated Damages.
See Article 10.3.4 of the General Conditions.
25. Applicable Laws and Regulations.
The Design-Builder’s attention is directed to the fact that all applicable South Dakota laws, and the rules and regulations of all authorities having jurisdiction over construction of the project shall apply to the agreement throughout and they will be deemed to be included in the agreement the same as though herein written out in full.
26. South Dakota Tax Information for Public Agreements.
Design-Builders performing public agreements in South Dakota may become responsible for two types of taxes: the excise tax upon realty improvement agreements and the sales/use tax upon materials.
All Design-Builders must secure a license from the Department of Revenue before engaging in the construction activities in this State. Detailed information on tax requirements may be obtained from the Department of Revenue, Anderson Building, Pierre, South Dakota 57501. Telephone 605.773.3311.
27. Applicable Standards.
In addition to codes, Standards and Regulations referenced for compliance in the various sections of the Specifications, the work shall be in compliance with the following:
A. South Dakota Codified Laws:
1. Title 5-14-13 - Americans with Disabilities Act Accessibility Guidelines for Buildings and Facilities
2. Title 11-10 – Building Codes & Standards
3. Title 34-28-5 – Glazing Materials in Buildings
4. Title 36-16 – Electrician’s and Electrical Contractors
a. Administrative Rules 20:44 - Electricians
5. Title 36-25 - Plumbers
a. Administrative Rules 20:53 - Plumbers B. The latest edition of The American Society of Heating, Refrigerating and Air-conditioning Engineers’ (ASHRAE)
Energy Efficient Design of New Buildings Except Low-Rise Residential Buildings, C. The latest United States National CAD Standards as they pertain to drawings.
D. The latest edition of the Army National Guard Design Guide 415-1, 415-2, 415-3, 415-4, 415-5 as required by type of facility, E. The latest edition of all DOD Unified Facilities Criteria (UFC) manuals, F. The latest edition of SD Dept. of the Military Technical Specifications, G. The latest edition of Unified Facilities Guide Specifications (UFGS), H. The latest edition of the SDARNG PAM 420-10-3 Design and Project Management Execution, I. The latest edition of the Code of Federal Regulations; Title 14 – Aeronautics and Space, J. The latest edition of FAA Advisory Circulars.
NOTE: Should there be a conflict between any of the above "Codes", Guides, or "Laws" the more stringent shall apply.
00 00 05 – INSTRUCTIONS TO DESIGN-BUILDERS 7 June 2024
28. Affirmative Action Plan.
The State of South Dakota requires that all contractors, vendors, and suppliers, employing fifty or more persons, doing business with any State Agency, Department, or Institution, place on file a statement of Affirmative Action that said contractor, vendor, or supplier does not discriminate in its employment practices with regard to race, color, religion, sex or national origin.
No award of any agreement with the State of South Dakota shall be executed or awarded and approved by the State for any service, supply, or commodity unless the successful design-builder submits such statement.
Above statement may be submitted to the Engineering Manager with the Design-Builder’s Price Proposal, or prior to award of agreement.
29. Procurement Law.
This project is subject to the provisions of SDCL § 5-18A and 5-18B et seq.
30. Federal Registration.
All design-builders shall be registered with SAM.gov.
00 00 05 – INSTRUCTIONS TO DESIGN-BUILDERS 8 June 2024
PAGE INTENTIONALLY LEFT BLANK
466405 RRA Solar Bidding Addenda 1 Final Audit Report 2024-08-15
Created: 2024-08-15
By: Kyle Roe (Kyle.Roe@state.sd.us)
Status: Signed
Transaction ID: CBJCHBCAABAAoOeGTGzsIhd8thIkNPOsSPyrsffuDMST
"466405 RRA Solar Bidding Addenda 1" History Document created by Kyle Roe (Kyle.Roe@state.sd.us)
2024-08-15 - 6:51:58 PM GMT
Document emailed to Cullen Jorgensen (Cullen.Jorgensen@state.sd.us) for signature
2024-08-15 - 6:52:09 PM GMT
Email viewed by Cullen Jorgensen (Cullen.Jorgensen@state.sd.us)
2024-08-15 - 9:00:35 PM GMT
Document e-signed by Cullen Jorgensen (Cullen.Jorgensen@state.sd.us) Signature Date: 2024-08-15 - 9:01:06 PM GMT - Time Source: server
Agreement completed.
2024-08-15 - 9:01:06 PM GMT
| 466405 RRA Solar Bidding Adde 1.pdf |
| 00 00 05 - Instructions to Bidders - DB.pdf |
| 2024-08-15T14:01:08-0700 | |
| Agreement certified by Adobe Acrobat Sign |
File details come from the government source that posted it. Updated .