Addendum 1 - Driveway Replacement - 10 Primer Court.pdf

PDF 199 KB Posted

Attached to
CD24092 Primer Court Driveway Replacement
Solicitation number
2121609
Issued by
Saratoga County, New York

About this file

This document is an Addendum 1 issued by the New York State Office for People with Developmental Disabilities (OPWDD) for a driveway replacement project located at 10 Primer Court in Clifton Park, NY. The addendum, dated May 2, 2025, addresses a specific vendor question from a site visit on 04/29/2025 regarding the driveway installation. The solicitation was released on 04/21/2025, with bids due on 05/19/2025. The addendum clarifies that vendors can pave a straight line from the garage to the main road instead of following the existing driveway's curve, with instructions to saw cut the sidewalk and pave straight to the road as indicated on the site plans.

The addendum provides technical guidance for bidders, specifically instructing them to incorporate the revised driveway layout into their project estimates. The document is part of a larger procurement process for a driveway replacement project, which requires vendors to be registered with the New York State Department of Labor and submit detailed quotes. While no specific budget is mentioned in this addendum, it is part of a broader solicitation that emphasizes compliance with state procurement guidelines, prevailing wage requirements, and the need for precise project execution within a 45-day contract term.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

KATHY HOCHUL

Governor

WILLOW BAER

Acting Commissioner

Developmental Disabilities Business Office

500 Balltown Road, Schenectady, NY 12304 │ TEL: 518-388-3648, FAX: 518-347-3451│www.opwdd.ny.gov

May 2, 2025

Addendum 1

Driveway Replacement 10 Primer Court Clifton Park NY 12065

Solicitation Date: 04/21/2025 Bid Due Date: 05/19/2025 Date of update: 05/02/2025

Good morning, The following question was asked by vendor that attended the site visit on 04/29/2025 and Capital District PSES response:

Q1. Can we pave a straight line from the garage to the main road instead of following the curve of the existing driveway?

A1. Yes, Saw cut the sidewalk pave straight to the road. See the attached yellow highlighted area on the site plans.

Please make sure to include this information in your estimates.

Best Regards, Vashti Kowlessar Office Assistant 1

NYS OPWDD – Brooklyn DDSO

750 Vandalia Avenue

Brooklyn NY 11239

Tel: 718-264-3915 vashisti.d.kowlessar@opwdd.ny.gov http://www.opwdd.ny.gov/ mailto:vashisti.d.kowlessar@opwdd.ny.gov