Addendum 1.pdf
PDF 757 KB Posted
- Attached to
- RFB-101-27 LED Lighting Network Center KET
- Solicitation number
- RFB 785 2700000167 2
- Issued by
- Fayette County, Kentucky
About this file
This is Addendum 1 to Invitation to Bid No. RFB-101-27 issued by the Commonwealth of Kentucky Department for Facilities and Support Services, Division of Engineering and Contract Administration, for LED Lighting Network Center improvements at Kentucky Education Television in Lexington, Kentucky, dated October 28, 2026. The addendum contains four binding modifications to the contract specifications and electrical drawings that bidders must conform to in their proposals. The modifications include provisions for ceiling tile replacement, clarification regarding existing wall switches in corridors, recessed lighting installation requirements, and structural support details for troffer fixtures. No specific project quantities, response dates, site visits, or bidder meetings are detailed in this addendum document.
No pricing terms, set-asides, incumbent information, funding sources, or other financial details are specified in this addendum. The document functions solely as a clarification and modification mechanism to the original invitation to bid, establishing binding changes to the electrical specifications and drawings that apply to the project scope.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Final_RFB_785_2700000167_2_SO_FORM.PDF | ||
| Final_RFB_785_2700000167_1_SO_FORM.PDF |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-101-27
FOR: LED Lighting Network Center Kentucky Education Television Lexington, Kentucky
DATE: October 28, 2026
RFB-785-2700000167
ADDENDUM NO. One (1)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Refer to attached addendum for all additions, deletions, and/or changes to specifications and/or drawings.
END OF ADDENDUM
Invitation to Bid No. RFB-101-27 For: LED Lighting Network Center Kentucky Education Television Lexington, Kentucky
Janis Wilhoite, Statewide Procurement Analyst II Division of Engineering and Contract Administration
ADDENDUM ITEMS
The following items shall be included in the Contract Documents for this Project.
ITEM NO. ONE (1)
SHEET E-1.1 – ELECTRICAL LEGEND
1. Refer to General Notes:
a. Add General Note #21 to read “Owner will provide necessary 2’x2’ and 2’x4’ ACT tiles to Contractor, who shall be responsible for cutting, installation, and alignment to meet or exceed existing conditions”. The intent of this note is for tiles which are necessary due to removal damage, removed light fixtures, removed mounting hardware. Tiles by the Owner will only be provided for contract scope items. Contractor will be responsible for damages beyond the contract scope.”
Attachments: None Drawings: None
ITEM NO. TWO (2)
SHEET E-3.1 – ELECTRICAL NEW WORK PLAN
1. Refer to notes on plan:
a. All existing wall switches to remain. This is a typical note for all Corridors since all corridors do not currently have existing dimming capability in the switches and the New Work Plan does not intent to have dimming for Corridors.
ITEM NO. THREE (3)
SHEET E-3.2 – ELECTRICAL NEW WORK PLAN
1. Refer to notes on plan:
a. All existing wall switches to remain. This is a typical note for all Corridors since all corridors do not currently have existing dimming capability in the switches and the New Work Plan does not intent to have dimming for Corridors.
ITEM NO. FOUR (4)
SHEET E-4.1 – ELECTRICAL SCHEDULES & DETAILS
1. Refer to Detail 1 “ Recessed Lighting Detail”
a. Detail applies to any and all 2’x2’ and 2’x4’ recessed troffers and shall have diagonal support wires connected to structural members.
END
| KET LED Lighting Network Center Addendum One Items.pdf |
| SHEET E-1.1 – ELECTRICAL LEGEND |
| SHEET E-3.1 – ELECTRICAL NEW WORK PLAN |
| SHEET E-3.2 – ELECTRICAL NEW WORK PLAN |
| SHEET E-4.1 – ELECTRICAL SCHEDULES & DETAILS |