Addendum 1.pdf
PDF 276 KB Posted
- Solicitation number
- MK00206
- Issued by
- Alleghany County, North Carolina
About this file
This is Addendum 1 to a proposal issued by the North Carolina Department of Transportation, Division Eleven, for an ID/IQ Tree and Brush Removal contract in Avery, Caldwell, and Watauga Counties (Contract No. MK00206). The addendum, dated September 14, 2026, adds special provisions for tree and brush cutting/trimming and stump grinding work on primary and secondary routes within District 2. The bid opening is scheduled for October 1, 2026, at 2:00 PM. The contract becomes available November 1, 2026, with a completion date of October 31, 2027. Work includes cutting and removing various sizes and types of trees and brush from right-of-way areas as directed by the Engineer, with all debris removed daily and properly disposed of in accordance with 2024 Standard Specifications. The contractor must provide qualified personnel and equipment, including a four-person tree crew with minimum two chainsaws, aerial bucket truck (75' minimum working height), chipper, dump truck with cover, skid steer equipment, and truck with grapple, all maintained to current DOT and OSHA safety standards.
Compensation is based on hourly rates measured to the nearest 0.25 hour for each piece of equipment and personnel while actively engaged in work, with no payment for idle equipment. Pay items include Tree Crew (hours), Aerial Bucket Truck (hours), Chipper (hours), Dump Truck with Cover (hours), Skid Steer with Attachment (hours), Skid Steer with Rotary Cutter (hours), Truck with Grapple (hours), and Stump Grinding (hours). Payment includes mobilization, labor, equipment, maintenance, fuel, and incidentals. Stump grinding work, performed to 6 inches below ground level with subsequent area leveling, seeding, and mulching as directed, is also compensated on an hourly basis. This is a state-funded project (not federal aid), and bidders must comply with North Carolina General Statutes Chapter 87 regarding contractor licensing for non-federal projects with bids of $40,000 or more. A bid bond is not required for this roadway project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
JOSH STEIN DANIEL H JOHNSON
GOVERNOR SECRETARY
Mailing Address:
NC DEPT. OF TRANSPORTATION
DIVISION ELEVEN
P. O. BOX 250
NORTH WILKESBORO, NC 28659
Telephone: (336) 903-9101
Website: www.ncdot.org
Location:
NC DEPT. OF TRANSPORTATION
DIVISION ELEVEN
801 STATESVILLE RD
NORTH WILKESBORO, NC 28659
September 14, 2026
ADDENDUM NUMBER 1
Contract No.:
WBS:
County:
Location:
Type of Work:
Bid Opening:
Division Eleven
MK00206
TBD
Avery, Caldwell, and Watauga Counties ID/IQ Tree and Brush Removal Primary/Interstate and Secondary Routes Within Avery, Caldwell, and Watauga Counties (District 2) ID/IQ Tree and Brush Removal October 1, 2026
To Whom It May Concern:
Reference is made to the proposal furnished to you for this project.
The following revisions have been made to the Proposal:
Page Number Revision Proposal Cover Note added that reads: “Includes Addendum
Number 1 Dated 9-14-2026 Pages R-11 through R-13 Added Tree & Brush Cutting/Trimming and
Stump Grinding Special Provisions
This revision is reflected on the Proposal currently on the Division 11 Letting Page.
The contract will be prepared accordingly.
If you have any questions about bidding on this project or any other questions concerning this project, please contact me at (336) 903-9115 or belmore@ncdot.gov
Sincerely, Bethany Elmore, PE Division Contract Engineer
CC: Michael Poe, PE, Division Engineer Brandon Whitaker, PE, Deputy Division Engineer Ivan Dishman, PE, Division Construction Engineer Matthew Evans, PE, Division Maintenance Engineer Ramie Shaw, PE, Division Program Development Engineer Jamie Wood, Division Roadside Environmental Engineer
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
HIGHWAY DIVISION 11
ID/IQ PROPOSAL
INCLUDES ADDENDUM NUMBER 1 DATED 9-14-2026
DATE AND TIME OF BID OPENING: OCTOBER 1, 2026 AT 2:00 PM
CONTRACT ID: MK00206
WBS ELEMENT NO.: TBD
FEDERAL AID NO.: STATE FUNDED
COUNTY: AVERY, CALDWELL, AND WATAUGA COUNTIES
MILES: TBD
ROUTE NO.: VARIOUS
LOCATION: ID/IQ TREE AND BRUSH REMOVAL PRIMARY/INTERSTATE
AND SECONDARY ROUTES WITHIN AVERY, CALDWELL,
AND WATAUGA COUNTIES
TYPE OF WORK: ID/IQ TREE AND BRUSH REMOVAL
NOTICE:
ALL BIDDERS SHALL COMPLY WITH ALL APPLICABLE LAWS REGULATING THE PRACTICE OF
GENERAL CONTRACTING AS CONTAINED IN CHAPTER 87 OF THE GENERAL STATUTES OF
NORTH CAROLINA WHICH REQUIRES THE BIDDER TO BE LICENSED BY THE N.C. LICENSING
BOARD FOR CONTRACTORS WHEN BIDDING ON ANY NON-FEDERAL AID PROJECT WHERE THE
BID IS $40,000 OR MORE, EXCEPT FOR CERTAIN SPECIALTY WORK AS DETERMINED BY THE
LICENSING BOARD. BIDDERS SHALL ALSO COMPLY WITH ALL OTHER APPLICABLE LAWS
REGULATING THE PRACTICES OF ELECTRICAL, PLUMBING, HEATING AND AIR
CONDITIONING AND REFRIGERATION CONTRACTING AS CONTAINED IN CHAPTER 87 OF THE
GENERAL STATUTES OF NORTH CAROLINA. NOTWITHSTANDING THESE LIMITATIONS ON
BIDDING, THE BIDDER WHO IS AWARDED ANY FEDERAL - AID FUNDED PROJECT SHALL
COMPLY WITH CHAPTER 87 OF THE GENERAL STATUTES OF NORTH CAROLINA FOR
LICENSING REQUIREMENTS WITHIN 60 CALENDAR DAYS OF BID OPENING.
THIS IS A ROADWAY PROJECT. BID BOND IS NOT.
NAME OF BIDDER
ADDRESS OF BIDDER
MK00206 R-11 Avery, Caldwell, and Watauga Counties
TREE & BRUSH CUTTING / TRIMMING
Description:
The Contractor shall cut and dispose of various sizes and types of trees and brush from areas within the right of way as directed by the Engineer. The work shall be performed with safeguards in place to protect traffic, utilities, and property. Any debris shall be removed from the roadway and shoulders before opening the road or lane to traffic. The contractor shall ensure that drainage systems and ditches are not obstructed by debris or damaged by equipment and must be restored prior to leaving the work site.
The Contractor shall discuss each assigned project with the Engineer or their representative prior to the commencement of work. At that time the Engineer or their representative will specify the type of work to be performed and the number and type of equipment to supply on site. Failure to provide the required personnel or equipment on the job site may result in suspension of the Contractor’s services.
Each work request shall be prosecuted in a continuous manner once it has been started. All debris must be removed daily unless otherwise directed.
Remove from the site and properly dispose of all vegetation, roots, stumps, tree laps, limbs, timber and debris produced by the tree & brush cutting / trimming operation. All debris, including vegetation, shall be disposed in accordance with Section 802 of 2024 Standard Specification for Roads and Structures. When a chipper is used to dispose of the brush and or trimmings the Engineer may approve the spreading of the wood chips over specific areas within the highway right of way.
Equipment:
For the purposes of this contract a Tree Crew will be defined as four (4) qualified, properly trained, and fully equipped personnel with not less than two gas powered chainsaws.
The Aerial Bucket Truck shall be supplied with one properly trained and certified operator at all times. The operator will not count as a member of the Tree Crew.
The Dump Truck (with Cover) & Chipper will be utilized in conjunction with the Tree Crew and may be operated by a qualified member of the Tree Crew.
The Skid Steer with attachment will be utilized in conjunction with the Tree Crew and may be operated by a qualified member of the Tree Crew.
The Skid Steer with Rotary Cutter may be used in conjunction with the Tree Crew or as separate item in which case a qualified operator will be required.
The Truck with Grapple will be utilized in conjunction with the Tree Crew and may be operated
MK00206 R-12 Avery, Caldwell, and Watauga Counties by a qualified member of the Tree Crew.
Any flaggers necessary to the operation will not be considered part of the Tree Crew.
All equipment must be of sufficient size and horsepower to accomplish the work in a timely manner. All equipment must be in good working order and function according to the manufacturers specifications. All equipment must meet current Department of Transportation and OSHA safety regulations specific to the type of work being performed and hazards that are present in the work area.
Measurement and Payment:
Tree Crew (4 Members – 2 Chainsaws Minimum) will be measured and paid as the actual number of hours, measured to the nearest 0.25 hour, during which the Tree Crew was onsite and working to remove the tree/brush.
Aerial Bucket Truck (Minimum 75’ Working Height) will be measured and paid as the actual number of hours, measured to the nearest 0.25 hour, during which the Aerial Bucket Truck was engaged in use.
Chipper (Min. 75HP and 12” Cutting Head) will be measured and paid as the actual number of hours, measured to the nearest 0.25 hour, during which the Chipper was engaged in use.
Dump Truck (With Cover) will be measured and paid as the actual number of hours, measured to the nearest 0.25 hour, during which the Dump Truck (With Cover) was engaged in use.
Skid Steer With Attachment will be measured and paid as the actual number of hours, measured to the nearest 0.25 hour, during which the Skid Steer With Attachment was engaged in use.
Skid Steer With Rotary Cutter will be measured and paid as the actual number of hours, measured to the nearest 0.25 hour, during which the Skid Steer With Rotary Cutter was engaged in use.
Truck With Grapple will be measured and paid as the actual number of hours, measured to the nearest 0.25 hour, during which the Truck With Grapple was engaged in use.
Payment includes, but not limited, to mobilization, labor, equipment, maintenance, fuel and any other incidental items not specifically described.
Payment will be made as follows:
Pay Item Pay Unit Tree Crew (4 Members - 2 Chainsaws Minimum) Hour Aerial Bucket Truck (Minimum 75’ Working Height) Hour Chipper (Minimum 75HP And 12” Cutting Head) Hour Dump Truck (With Cover) Hour
MK00206 R-13 Avery, Caldwell, and Watauga Counties
Skid Steer With Attachment Hour Skid Steer With Rotary Cutter Hour Truck With Grapple Hour
No payment will be made for idle equipment.
STUMP GRINDING
During tree & brush cutting and removal operations or following maintenance operations the Contractor will be required to grind the stumps of felled trees to a depth of 6” below ground level as directed by the Engineer. The Contractor will then level the area to a uniform contour that matches the surrounding topography and seed and mulch the disturbed area if directed. Stump grinding may be accomplished by a member of the tree crew.
Measurement and Payment:
Stump Grinding will be measured and paid as the actual number of hours, measured to the nearest 0.25 hour, during which the Stump Grinder was engaged in Stump Grinding.
Payment includes, but not limited, to mobilization, grinding, subsequent ground leveling, seeding & mulching and incidentals to perform the work.
Payment will be made as follows:
Pay Item Pay Unit Stump Grinding Hour
No payment will be made for idle equipment.