Addendum 1.pdf
PDF 120 KB Posted
- Attached to
- Highway 49 -Phase 4
- Solicitation number
- PE-68400-NONST-2026-000000017
- Issued by
- Jefferson County, Georgia
About this file
This is Addendum No. 1 to the Plans, Specifications, and Contract Documents for the Highway 49 Water System Extension Phase 4 project issued by Jones County, Georgia. The addendum revises the bid date for sealed bids from the originally scheduled date to January 20, 2025, at 11:00 a.m. local prevailing time due to a government holiday. The project scope encompasses a complete water main extension along a portion of Highway 49 and Childs Road, with major construction items including 16-inch water main, 12-inch water main, 2-inch water main, gate valves, fire hydrants, water services, and miscellaneous appurtenances. Bids will be received at the Jones County Board of Commissioners, 166 Industrial Blvd., Gray, Georgia 31032, and opened publicly in the Commission Chambers. Bidders must be licensed by the State of Georgia, with license numbers required on the bid envelope. No bid may be withdrawn for sixty (60) calendar days after the bid closing time.
Bidding documents are available for review at the Jones County Board of Commissioners and the Dodge Plan Room. Copies for bidding purposes must be obtained from Ingram & Associates Consulting Engineers, L.L.C., at 332 New Street, Macon, Georgia 31201, with a non-refundable cost of $200.00 per hard copy set or $75.00 per digital set. Bidders must acquire all bidding documents from the engineer to be eligible to submit a bid on this project. Contact information for obtaining documents is available through Ashley Chancey at (478) 745-3996 or ashley@ingrameng.com.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00100_Executed Advertisement 12_15_2025 for B.doc | DOC document | |
| Award _ Phase 4 Water System Extension.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 1
PLANS, SPECIFICATIONS, AND CONTRACT DOCUMENTS
PROJECT: Hwy 49 Water System Extension Phase 4
I&A Project No.: 1160-092-01
OWNER: Jones County, Georgia
BID DATE: January 20, 2025 @ 11:00 am (Phase 4)
Item 1: REVISION OF BID DATE: Due to the government holiday, bids for
“Hwy 49 Water System Extension Phase 4” will be received until January 20th at
11:00 am, local prevailing time.
Item 2: This specification and plan set are a complete document dedicated to the
Phase 4 water main extension along a portion of Hwy 49 and Childs Road.
END ADDENDUM NO. 1