About this file
This is Addendum #1 issued by the City of Dublin, Georgia for RFP #25-0113-01 regarding Groundwater Plant Roof/Wall Renovation, dated February 5, 2025. The addendum outlines eight additional requirements for the renovation project, including: repair of step nosings between first and second floors; installation of louvers capable of passing 7,000 cfm (Greenheck ESD-435 or equivalent); addition of a 7,000 cfm wall ventilation fan in the filter room with associated electrical work; cleaning and painting of existing steel roof trusses; provision of a "Jig" for ceiling panel removal; wall repair and replacement of 750 square feet of plaster with additional touch-up painting required for remaining walls; proper roof drainage; and repair of four elevator wall floor connections.
The addendum includes specific technical requirements such as the ventilation fan specifications (1/4 hp, 110 volt) and installation height (12 feet from floor). Bidders must acknowledge receipt of this addendum by signing and returning it with their proposal, as failure to do so may result in disqualification. The document includes the City of Dublin logo featuring a shamrock design dated 1812.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP _25_0113_01 _ Groundwater Plant Roof_Wall.pdf | ||
| Addendum _2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF DUBLIN
ADDENDUM #1
RFP #25-0113-01
GROUNDWATER PLANT ROOF/WALL RENOVATION
DATE: February 5, 2025
TO: Groundwater Plant Roof/Wall Renovation Proposers
FROM: David Sawyer, Purchasing Director
SUBJECT: Addition to the Renovation
Addition: The following additions are needed for this proposal:
1. This job is to also include repairing the step nosings between the first and second floor at the groundwater plant.
2. Proposers will need to provide one or a combination of louver(s) that can pass 7,000 cfm. A Greenheck ESD-435 louver (or equivalent) shall work for this job.
3. Add ventilation fan(s) to the filter room. (7,000 cfm wall fan) (1/4 hp) 110 volt. Provide wall opening for fan approximately 12 feet from the floor of the filter room and all conduit, wire, etc to operate the fan to the nearest electrical panel. Fan shall be switch operated.
4. Clean and paint the existing steel roof trusses to preserve them as required.
5. Contractor to provide a “Jig” to remove ceiling panels and use all caution necessary to prevent panels or pieces from falling into the filters.
6. Wall repair shall require removal of plaster and replacement, while wall touch up will be basically cleaning and painting the surface. Wall repair quantity is 750 square feet, and the remainder of walls will require touching up/paint to all existing painted walls.
7. Contractor must make sure the roof is properly drained.
8. Contractor must repair four elevator wall floor connections.
Be sure to submit this signed form with your proposal to acknowledge your receipt of the addendum. Failure to return signed addendum may result in disqualification of proposal.
I have read the above change to the original bid and will submit my bid accordingly.
Bidder: __________________________________________________