This document is an Addendum to Invitation to Bid No. RFB-182-23 for Water Infrastructure Upgrades at Lake Barkley State Resort Park in Cadiz, Kentucky, issued by the Commonwealth of Kentucky Department for Facilities and Support Services Division of Engineering and Contract Administration. The addendum provides clarifications and revisions to the scope of work, including restrictions on work within the campground area, limitations on daily work hours, and requirements for restoration of disturbed areas through seeding and mulching. The addendum also updates the pipe schedule, specifying the size and material requirements for various sections of the water distribution system. The work must be completed after July 15, 2023, and the water distribution system must remain in continuous operation during construction, with the exception of the campground area.

The contract requires the successful bidder to comply with all specifications and terms outlined in the addendum. No additional pricing information or set-aside requirements are provided in this document. Interested parties must review the complete bid package to ensure full compliance with all requirements.

View the file

Other files

File Type Posted
Final_RFB_785_2300000380_2_SO_FORM.PDF PDF
Final_RFB_785_2300000380_1_SO_FORM.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

INVITATION TO BID NO: RFB-182-23

FOR: Water Infrastructure Upgrades Lake Barkley State Resort Park Cadiz, Kentucky

DATE: January 18, 2023

RFB-785-2300000380

ADDENDUM NO. One (1)

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: Refer to addendum below for all additions, deletions, and/or changes to specifications and/or drawings.

END OF ADDENDUM

Invitation to Bid No. RFB-182-23 For: Water Infrastructure Upgrades Lake Barkley State Resort Park Cadiz, Kentucky

Kyla Satterly, Statewide Procurement Analyst II Division of Engineering and Contract Administration

Commonwealth of Kentucky Department for Facilities and Support Services Division of Engineering and Contract Administration Water Infrastructure Upgrade Lake Barkley State Resort Park

RFB-182-23

Addendum No. 1

SPECIAL CONDITIONS

1. Paragraph 3. Times of Completion

REPLACE Work Restrictions and “Black-Out” Dates with the following:

“Work within the campground area including Line “J” and services to each campground shall be completed after July 15, 2023.

Removal or trimming of trees 3 inch diameter breast height and larger is prohibited. Trees smaller than 3 inch diameter breast height may be removed between October 15 to April 15, subject to prior approval by Owner.

The water distribution system must remain in continuous operation during construction, with the exception of the campground after July 15, 2023. Any disruptions to the water service shall be coordinated with Park Operations staff. It shall be the responsibility of Contractor to not in any way impair the normal operation of the facilities, regardless of the work under way. Contractor shall provide all temporary piping and temporary construction required to complete the Work.”

REPLACE Limitations on Daily Work Times with the following:

“Unless otherwise approved by Owner, work hours shall be confined to between 8 am and 7 pm, Monday through Friday. These work hour limitations shall not apply to the campground area and Line “J” after July 15, 2023.”

SPECIFICATIONS

1. Page 31 23 00-9, SECTION 31 23 00-EXCAVATION, FILL, BACKFILL AND GRADING, PART 3-EXECUTION

ADD the following:

“3.10 RESTORATION

A. Topsoil shall be placed at completion of finish grading.

B. Seed mix shall comply with Standard Specifications No. II. Seed shall be applied at rates specified in Section 212 of the Standard Specifications.

C. Fertilizer shall be FS O-F-241, Type I, Grade A with the following proportions: Nitrogen 10%; Phosphoric Acid 10%; Soluble Potash 10%.

Fertilizer shall be applied at the rates Specified in Section 212 of the Standard Specifications.

D. All areas receiving seed shall be mulched in accordance with Section 212 of the Standard Specifications.

E. Seeding shall be maintained by CONTRACTOR until grass is well established. Grass is well established when it covers the entire seeded areas to a height of 2 inches.”

DRAWINGS

1. DRAWING G2-INDEX OF SHEETS, TABLES, GENERAL NOTES, SYMBOLS &

ABBREVIATIONS

REPLACE PIPE SCHEDULE with attached PIPE SCHEDULE.

PIPE SHALL BE SIZE AND MATERIAL AS NOTED IN

THE TABLE ABOVE. REFER TO SPECIFICATION

SECTION 330010 FOR PIPE REQUIREMENTS.

PIPE SCHEDULE

LINE PIPE DIAMETER PIPE MATERIAL

LINE A STA 10+00

TO STA 55+10 8-INCH PVC OR DI

LINE A STA 55+10

TO STA 149+17 6-INCH PVC OR DI

B 6-INCH PVC OR DI

C 2-INCH PVC

LINE D STA 10+00

TO STA 29+80 8-INCH PVC OR DI

LINE D STA 29+80

TO STA 64+70 6-INCH PVC OR DI

E 8-INCH PVC OR DI

F 2-INCH PVC

G 8-INCH PVC OR DI

H 4-INCH PVC OR DI

I 4-INCH PVC OR DI

J 3-INCH PVC

LAKE BARKLEY STATE RESORT PARK

WATER INFRASTRUCTURE UPGRADE

ATTACHMENT TO ADDENDUM 1

01.18.2023

Addendum 1
Addendum 1 RFB 182-23