Addendum 1-Addendum No. 1.pdf
PDF 135 KB Posted
- Solicitation number
- B27000724
- Issued by
- Kauai County, Hawaii
About this file
This Addendum No. 1 is issued by the State of Hawaii Department of Land and Natural Resources, Division of Boating and Ocean Recreation, Engineering Branch, for HIePRO Solicitation No. B27000724/Job No. KA26-03, the Port Allen Small Boat Harbor Hurricane Lowell Water System Repair and Lighting project located in Eleele, Kauai. The addendum modifies the original solicitation requirements and extends the bid deadline to November 16, 2026, at 2:00 PM. The project scope includes connection to existing 4-inch water mains, installation of 415 linear feet of 2-inch HDPE pipe (Waterline "A") and 145 linear feet of 1.5-inch HDPE pipe (Waterline "B"), four hose bibb pedestals, four pedestal assemblies, and ten solar-powered area light assemblies with footings and poles. The addendum provides additional technical clarifications and attachments, including revised questions and responses received through HIePRO, a revised Bid Proposal form with changes indicated in blue, solar light assembly and asphalt pavement repair details, and specific clarifications on hose bib and pipe bollard requirements at designated waterline stations.
The addendum specifies that the hose bib at Waterline "A" Station 2+35 shall have four pipe bollards and the hose bib at Station 4+15 shall have two pipe bollards, while hose bibs along Waterline "B" do not require pipe bollards. The original solicitation indicates an estimated construction cost of $400,000, with bidders eligible for a 10 percent price preference for recycled products and a 5 percent preference for apprenticeship agreement participation with the State Department of Labor and Industrial Relations. Bidders must hold a valid State Contractor's License Class "A" General Engineering and perform at least 20 percent of contract work with their own organization. The contract period is 30 consecutive calendar days from written notice to proceed, with liquidated damages of $100 per calendar day for delayed completion. Required insurance includes Commercial General Liability of not less than $1,000,000 per occurrence and $2,000,000 aggregate, and Comprehensive Automobile Liability of not less than $1,000,000 combined single limit. Performance and payment bonds are required at 100 percent of the total contract price.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HIePRO Solicitation No. B27000724 / Job No. KA26-03 Port Allen Small Boat Harbor Hurricane Lowell Water System Repair and Lighting Addendum No. 1 November 13, 2026 Page 1 of 1
State of Hawaii
DEPARTMENT OF LAND AND NATURAL RESOURCES
DIVISION OF BOATING AND OCEAN RECREATION
ENGINEERING BRANCH
4 Sand Island Access Road Honolulu, Hawaii 96819
ADDENDUM NO. 1
HIePRO Solicitation No. B27000724 / Job No. KA26-03 Port Allen Small Boat Harbor Hurricane Lowell Water System Repair and Lighting
Eleele, Kauai, Hawaii
November 13, 2026
The items listed hereinafter are hereby made a part of the contract for the above project and shall govern the work, taking precedence over previously issued plans, specifications, permitting documents, and other documents governing the items mentioned.
BID DEADLINE EXTENSION
This addendum extends the bid deadline to November 16, 2026 at 2:00PM.
QUESTIONS RECEIVED VIA HIePRO
Attached to this addendum are questions received via the question/answer section of the HIePRO Solicitation and responses.
PROPOSAL
Attached to this addendum is a revised Bid Proposal form. Changes to the bid proposal form will be shown in blue color.
SOLAR LIGHT ASSEMBLY AND PAVEMENT REPAIR DETAILS
Attached to this addendum are additional details for the solar light assembly and asphalt pavement repair.
HOSE BIB AND PIPE BOLLARD CLARIFICATION
The hose bib at Waterline “A” Station 2+35 shall have four (4) pipe bollards. The hose bib at Waterline “A” Station 4+15 shall have two (2) pipe bollards. The hose bibs along Waterline “B” do not require pipe bollards.
ADDENDUM NO. 2 ATTACHMENTS
1. HIePRO questions received and responses.
2. Revised Bid Proposal per Addendum No. 1 dated November 13, 2026.
3. Solar Light Assembly and Asphalt Pavement Details.