This is Addendum 1 to a Statement of Qualifications (SOQ) solicitation issued by the Georgia Department of Transportation (GDOT) for Pavement Evaluation services supporting Interstate Maintenance operations. The solicitation is divided into three separate contracts: Contract 1 covers Region 1, District 7; Contract 2 covers Region 2, Districts 1, 3, and 6; and Contract 3 covers Region 3, Districts 2, 4, and 5. Qualified firms and organizations are invited to submit SOQs demonstrating their capability to perform pavement evaluation services across these designated regions and districts. The addendum modifies or clarifies specific requirements, terms, or procedures outlined in the original solicitation documents.
The addendum content itself is not detailed in the provided excerpt, which limits the ability to identify specific modifications regarding pricing terms, contract duration, renewal options, funding amounts, or other material changes. Potential respondents should review this addendum in conjunction with the original solicitation documents to understand all requirements, evaluation criteria, submission procedures, and any updates to previously published information that may affect their proposal preparation and submission.
Text of this file
ADDENDUM NO. 1
ISSUE DATE: 3/29/2022
This Addendum shall become and form a part of the RFQ for:
RFQ-484-041222 – Pavement Evaluations for Interstate Maintenance:
Contract 1 – Region 1, District 7
Contract 2 – Region 2, Districts 1, 3 and 6 Contract 3 – Region 3, Districts 2, 4 and 5
NOTE: PLEASE REVIEW CAREFULLY! THERE MAYBE CHANGES TO THE INFORMATION TO BE PROVIDED.
FAILURE TO ADHERE TO ANY CHANGES ADDRESSED IN THIS ADDENDUM MAY RESULT IN
DISQUALIFICATION.
In the event of a conflict between previously released information and the information contained herein, the latter shall control.
NOTE: A signed acknowledgment of this addendum (this page) MUST be attached to your SUBMITTAL for Phase I.
Firm Name
Signature Date
Typed Name and Title
Georgia Department of Transportation (GDOT) Office of Transportation Services Procurement
One Georgia Center 600 West Peachtree Street, NW
19th Floor Atlanta, Georgia 30308
This Addendum, including all questions and answers, shall become and form a part of the original RFQ package and shall be taken into account when preparing your proposal.
The purpose of this addendum is to provide the answers to the written questions received during the question and answer period of the RFQ Phase as follows.
I. Written Questions and Answers:
Questions Answers
1. Section VI B 2. & 3. p. 6 Since this is an electronic submittal, will a scanned copy of the notarized document (included in the PDF submittal) suffice, or is a hard copy (original by physical mail) also required?
A scanned copy of the notarized document is sufficient to be included your submittal.
2. What amounts ($ value) were disbursed as a part of the last set of contracts?
For RFQ-484-073117, contract amounts are:
Contract 1 - District 1, 6 and 7 = $5,000,000.00 Contract 2 - Districts 2 and 3 = $5,000,000.00 Contract 3 - Districts 4 and 5 = $5,000,000.00
3. VI D 3 and 4; p. 8 Refers to C.2 and C.3. Presume this should be D.2 and D.3?
Yes; see revision below.
Addendum No. 1 RFQ-484-041222, Pavement Evaluations for Interstate Maintenance
4. Section II; p. 3 Is there a breakdown of weightage of points that will be carried over from Phase I to Phase II?
RFQ, Page 4, Section IV. Selection Criteria for Phase I;
and Page 5, Section V. Selection Criteria for Phase II identifies each Criteria for Evaluation and the breakdown of percentage weights for each Phase.
RFQ, Page 3, Section II.Item E. Final Selection:
Final selection will be determined by carrying the scores from Phase I forward for each Finalist and by evaluating the Technical Approach and Past Performance criteria for Phase II. The Selection Committee will discuss the Finalist’s Phase II Responses and the final rankings will be determined.
5. Section VI C 5. p. 7 Some firms providing specialty testing, as a key team member, (such as TSD) as a subconsultant to the prime may not be prequalified with GDOT, as GDOT does not have specific area class for this kind of specialty testing.
Can these specialized subconsultants work directly under the Prime’s umbrella (Prime that is prequalified in the listed area classes)?
If yes, will listing the subconsultant with NO prequals on the team, result in disqualification?
GDOT does not have an area class for this specific work, therefore no Area class is required.
Yes.
No.
6. There are 6 area classes identified where the prime and/or team must be prequalified. None of these area classes identify TSD testing; therefore, it is our understanding that ARRB Systems doesn’t need to be prequalified. Can you please confirm if that is correct?
To be clear, ARRB is not prequalified in any of the 6 area classes identified in the RFQ and ARRB’s role will be limited to providing TSD data collection services only.
7. On page 13, section D (Audit and Accounting System Requirements), item 3 refers to yearly CPA overhead audit for contract amount exceeding $250K; does this refer to GDOT contracts?
II. RFQ, Section VI, Item D is DELETED in its entirety and REPLACED WITH:
D. Additional Resources and Challenges
1. Organizational chart which identifies the project manager, prime, Key Team Leaders, Key Team Member, support personnel, and reporting structure. The chart may be submitted on a 11” x 17” page. (Excluded from the page count)
2. Primary Office - Identify and discuss the primary office which will be responsible for handling the specific project and the number and types of staff within the office and how this office could benefit the project and
Addendum No. 1 RFQ-484-041222, Pavement Evaluations for Interstate Maintenance promote efficiency. This information to be included on the one (1) page with the Narrative on Additional Resource Areas.
3. Narrative on Additional Resource Areas – Respondents are to provide information regarding additional resource areas identified as important to the project, to discuss how the key areas will integrate and work together on the project, to discuss any information which is pertinent to these areas, to provide a narrative regarding how the organization of the team, including the PM, Key Team Leaders, and Key Team Member can deliver the project. Respondents may discuss the advantages of the team and the abilities of the team members which will enable the project to move as expeditiously as possible. Respondents submitting more than the one (1) page allowed (combined for D.2 and D.3), will be subject to disqualification.
4. Identify Additional Resources – Respondents are allowed one (1) page to provide information on additional resources, outside of the Project Manager, Key Team Leaders and Key Team Member, providing a brief description of the resource and describe how the additional resources identified will help address Pavement Evaluations for Interstate Maintenance of challenges. Respondents submitting more than the one (1) page allowed will be subject to disqualification.
The information is limited to the organization chart (excluded from page count), [one (1) page of text to include both D.2. Primary Office and D.3. Narrative on Additional Resource Areas], and one (1) page of text for Identify Additional Resources.
Other files
| File | Type | Posted |
|---|---|---|
| Selection of Firms | — | |
| Shortlist Notification | — | |
| Award Information | — | |
| RFQ-484-041222 | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .