ADDENDUM _1 _ 2024 LMIG Resurfacing McDuffie .pdf
PDF 365 KB Posted
- Solicitation number
- PE-69700-NONST-2024-000000001
- Issued by
- Lowndes County, Georgia
About this file
This document is an Addendum to the 2024 LMIG Resurfacing project for McDuffie County and the City of Thomson in Georgia. The Addendum extends the Completion Date for the contract from October 31, 2024 to April 30, 2025, and adjusts the associated liquidated damages clause accordingly. It also clarifies the scope of work for shoulder building, manhole/valve adjustments, and striping requirements. The Revised Bid Schedule provides updated unit quantities and line items. Bids are due by 2:00 PM on Thursday, June 13, 2024, and the lowest responsive and responsible bidder will be awarded separate contracts with McDuffie County and the City of Thomson.
The contract pricing is to remain firm for the duration of the contract, which is to begin upon issuance of the Notice to Proceed and continue through April 30, 2025. The contractor will be responsible for all traffic control requirements, with associated costs to be included in the overall bid. Payment for shoulder building and grassing will be under the Grading per Mile item for McDuffie County roads only, as the City of Thomson will not require those activities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| INVITATION TO BID _ Bid No_ 2024_001 2024 LMI.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT NOS: MCDUF2024-01 & THOM2024-01
BID NO.: 2024-001
June 6, 2024
Addendum No. 1
2024 LMIG Resurfacing McDuffie County & City of Thomson
General Information:
I. General Conditions: (page 3 in document.)
• CHANGE:
H. TERM
1. Contract Time charges shall begin on the day after issuance of the Notice to Proceed by the individual counties and continue until October 31, 2024, for each contract. The Contractor will be required to perform such resurfacing within a time agreed to by both parties and at the Contract unit prices. Failure to perform such work in the time agreed will result in Liquidated Damages of $750.00 per day until such work is completed.
• TO:
H. TERM
1. Contract Time charges shall begin on the day after issuance of the Notice to Proceed by the individual counties and continue until April 30, 2025, for each contract. The Contractor will be required to perform such resurfacing within a time agreed to by both parties and at the Contract unit prices. Failure to perform such work in the time agreed will result in Liquidated Damages of $750.00 per day until such work is completed.
I. PRODUCTION REQUIREMENTS
2. Failure to meet the Completion Date of October 31, 2024, will result in the assessment of liquidated damages in the amount of $750 per calendar day for failure to complete work by October 31, 2024, and will continue until work is completed and accepted by the County.
I. PRODUCTION REQUIREMENTS
2. Failure to meet the Completion Date of April 30, 2025, will result in the assessment of liquidated damages in the amount of $750 per calendar day for failure to complete work by April 30, 2025, and will continue until work is completed and accepted by the County.
General Information: (continue)
CONTRACT SECTION: (page I-1 in document)
ARTICLE 1 - SERVICES TO BE PERFORMED BY CONTRACTOR
Contractor agrees to perform the services specified in the “Description of Services” attached to this Agreement and incorporated in this Agreement by reference. The Contractor awarded work under this contract shall commence work within ten (10) days after the issuance of the Notice to Proceed and shall fully complete all work hereunder by the Completion Date of October 31, 2024.
If said work is not completed within the time stated, the Contractor shall be liable and hereby agrees to pay McDuffie County as liquidated damages and not as a penalty, (1) $750 per calendar day for failure to complete the work by the Completion Date of October 31, 2024, all as liquidation of the extra expense incurred by the County and liquidated damages to the County. Liquidated damages will continue until the contract is complete.
ARTICLE 1 - SERVICES TO BE PERFORMED BY CONTRACTOR
Contractor agrees to perform the services specified in the “Description of Services” attached to this Agreement and incorporated in this Agreement by reference. The Contractor awarded work under this contract shall commence work within ten (10) days after the issuance of the Notice to Proceed and shall fully complete all work hereunder by the Completion Date of April 30, 2025.
If said work is not completed within the time stated, the Contractor shall be liable and hereby agrees to pay McDuffie County as liquidated damages and not as a penalty, (1) $750 per calendar day for failure to complete the work by the Completion Date of April 30, 2025, all as liquidation of the extra expense incurred by the County and liquidated damages to the County. Liquidated damages will continue until the contract is complete.
The following changes were made to the bid schedule:
1. Page 1 of 2, Item 040, 432-5010 MILL ASPH CONC PVMT, VARIABLE DEPTH EA
1235.00 was CHANGED to Item 040, 432-5010 MILL ASPH CONC PVMT, VARIABLE
DEPTH SY 1460.00
For Contractors Information:
1. Would McDuffie County be willing to extend the completion date until April 30, 2025? The current workloads of contractors and completion dates of other projects are making it difficult to guarantee any more completion windows in 2024.
RESPONSE: Completion Date changed to April 30, 2025.
2. Pay item # 040, “Milling Asph Conc Pvmt…” shows a unit of “EA”. Should this be
“SY”?
RESPONSE: Unit has been corrected, see revised Bid Schedule
3. Will McDuffie County consider implementing the GDOT asphalt index on this project?
RESPONSE: No
4. With the bridge exception noted on Quail Farm Road, in order to get an adequate tie into both ends of the bridge it will require some variable depth milling. Has this been accounted for in the milling pay item?
RESPONSE: Additional milling quantity has been added to account for the milling at both ends of the bridge.
5. How are tie-ins to side roads and driveways to be accomplished? Run the gate out?
RESPONSE: Yes, See Bid Document: II. Special Provisions - F.6.
6. Page 17, in the proposal, has a paving exception for the Bridge on Quail Farm Road.
It states that it will still be striped, using thermoplastic, however there are no pay items for thermoplastic. How will this be paid?
RESPONSE: Bridge to be striped with current striping items listed in the proposal.
Attachment:
• Revised Special Notice
• Revised Bid Schedule – Pages 1-2
You should acknowledge receipt on Bid Schedule of the bidding documents.
FAILURE TO ACKNOWLEDGE THE ADDENDUM MAY RESULT IN REJECTION OF YOUR
BID.
RECEIPT OF BIDS CORRECTED: 2:00 PM LOCAL TIME, THURSDAY, JUNE 13, 2024
ADDENDUM NO. 1
SPECIAL NOTICE 1
A COMPLETION DATE OF APRIL 30, 2025, HAS BEEN
ESTABLISHED FOR CONSTRUCTION ON THE 2024 LMIG
RESURFACING PROJECTS IN MCDUFFIE COUNTY AND
THE CITY OF THOMSON. CONTRACTOR WILL BE
ASSESSED LIQUIDATED DAMAGES IN THE AMOUNT OF
$750.00 PER CALENDAR DAY FOR FAILURE TO
COMPLETE THE PROJECT BY APRIL 30, 2025.
THE CONTRACTOR WILL BE RESPONSIBLE FOR ALL
REQUIREMENTS COVERED UNDER SPECIAL PROVISION
150 – TRAFFIC CONTROL. ALL COST ASSOCIATED WITH
TRAFFIC CONTROL SHALL BE INCLUDED IN THE
OVERALL BID.
THE CONTRACTOR WILL BE RESPONSIBLE FOR
CLIPPING SHOULDERS PRIOR TO THE PAVING
OPERATION.
SPECIAL NOTICE 2
(MCDUFFIE COUNTY)
THE CONTRACTOR WILL BE RESPONSIBLE FOR
SHOULDER BUILDING FOR ALL ROADS IN MCDUFFIE
COUNTY ONLY, PAYMENT FOR THE WORK WILL BE PAID
FOR UNDER GRADING PER MILE ITEM.
FINAL GRASSING IN MCDUFFIE COUNTY TO BE
COMPLETED BY THE CONTRACTOR ONCE THE
SHOULDER BUILDING HAS BEEN COMPLETED. COST
FOR GRASSING TO BE INCLUDED IN THE COST OF
GRADING PER MILE.
NO SHOULDER BUILDING OR GRASSING TO BE DONE IN
THE CITY OF THOMSON.
SPECIAL NOTICE 3
(CITY OF THOMSON)
THE CONTRACTOR WILL BE RESPONSIBLE FOR THE
ADJUSTMENTS OF MANHOLES AND/OR VALVES TO
GRADE FOR THE ROADS IN THE CITY OF THOMSON. THE
CONTRACTOR WILL BE RESPONSIBLE FOR THE
INSTALLATION ONLY, THE CITY OF THOMSON WILL
SUPPLY ALL REQUIRED MATERIALS. THE CONTRACTOR
IS TO COORDINATE WITH THE CITY OF THOMSON PRIOR
TO BEGINNING PAVING WORK TO VERIFY REQUIRED
MATERIALS AND WHEN AVAILABLE. MATERIALS WILL BE
DELIVERED TO WORK SITE BY THE CITY UNLESS OTHER
ARRANGEMENTS HAVE BEEN MADE BETWEEN THE
CONTRACTOR AND THE CITY OF THOMSON.
PAYMENT FOR THE INSTALLATION WORK TO BE PAID
FOR UNDER ADJUSTMENT OF MANHOLE AND VALVES
(INTALLATION ONLY) ITEMS.
2024MCDUF & 2024THOM
2024 LMIG RESURFACING IN MCDUFFIE COUNTY AND
THE CITY OF THOMSON
2024-001
BID SCHEDULE
Item # GDOT # Description Units
Est. Bid
Quantity Unit Price Bid Total Price Bid
005 210-0200 GRADING PER MILE (SHOULDERS) LM 7.18
010 402-3100
RECYCLED ASPH CONC 9.5 MM SUPERPAVE, TP 1, GP 1
OR BLEND 1, INCL BITUM MATL & H LIME TN 1,275.00
015 402-3113
RECYCLED ASPH CONC 12.5 MM SUPERPAVE, GP 1 OR
2, INCL BITUM MATL & H LIME TN 7,570.00
020 402-3121
RECYCLED ASPH CONC 25 MM SUPERPAVE, GP 1 OR 2,
INCL BITUM MATL & H LIME TN 200.00
025 413-0750 TACK COAT GL 11,055.00
030 415-5000
ASPHALTIC CONCRETE OPEN GRADED CRACK RELIEF
INTERLAYER, GP 2 ONLY, INCL BITUM MATL & H LIME TN 4,430.00
035 429-1000 RUMBLE STRIPS (THERMOPLASTIC) EA 3.00
040 432-5010 MILL ASPH CONC PVMT, VARIABLE DEPTH SY 1,460.00
045 652-2501 SOLID TRAFFIC STRIPE, 5 IN, WHITE LM 16.52
050 652-2502 SOLID TRAFFIC STRIPE, 5 IN, YELLOW LM 13.06
055 652-3502 SKIP TRAFFIC STRIPE, 5 IN, YELLOW GLM 4.32
060 653-1704 THERMOPLASTIC SOLID TRAF STRIPE, 24 IN, WHITE LF 191.00
065 611-8052 ADJUST MANHOLE TO GRADE (INSTALLATION ONLY) EA 19.00
070 611-8142
ADJUST VALVE BOX TO GRADE (INSTALLATION
ONLY) EA 4.00
TOTAL
100.00%
MCDUFFIE COUNTY, GEORGIA
PROJECT #:
PROJECT:
BID NUMBER: (REVISED BID SCHEDULE)
ADDENDUM NO. 1
COMPANY NAME: ______________________________________________________________
Failure to return this page my result in rejection of bid. Page 1 of 2
2024MCDUF & 2024THOM
2024 LMIG RESURFACING IN MCDUFFIE COUNTY AND
THE CITY OF THOMSON
2024-001
MCDUFFIE COUNTY, GEORGIA
PROJECT #:
PROJECT:
BID NUMBER: (REVISED BID SCHEDULE)
ADDENDUM NO. 1
ADDENDUM NO.
CERTIFICATION OF NONCOLLUSION IN BID PREPARATION ____________________________________________________________
(Signature) (Date) fewer than 100 employees
100 or more employees
(If your company is an LLC, you must identify all principals to include address and phone numbers in your submittal)
FED TAX ID______________________________________________________
ADDRESS: ____________________________________________________________________________________________________
DOES YOUR COMPANY CURRENTLY HAVE A LOCATION WITHIN MCDUFFIE COUNTY? YES □ NO □
REPRESENTATIVE SIGNATURE: _________________________________________________________________________________
PRINT AUTHORIZED REPRESENTATIVE'S NAME: ___________________________________________________________________
TELEPHONE NUMBER: _______________________________________________ FAX: _____________________________________
E-MAIL ADDRESS_______________________________________________________________________________________________
The County requires that all who enter into a contract for the physical performance of services with the County must satisfy O.C.G.A.
§ 13-10-91 and Rule 300-10-1-.02, in a manner, and such are conditions of the contract. Further, all bidders should identify which of the statutory employee-number categories they represent:
In compliance with the attached specifications, the undersigned offers and agrees, if this bid is accepted by the Board of
Commissioners within ninety (90) days of the date of bid opening, to furnish any or all of the items upon which prices are quoted within the time specified in the bid schedule.
LEGAL BUSINESS NAME: ______________________________________________________________________________________
BID SCHEDULE
Note: The County requires pricing and terms to remain firm for the duration of this contract. Contract to begin upon date of issuance of the “Notice to Proceed” independently for each county and work continuously through April 30, 2025. Failure to hold pricing firm for the duration of this contract will be sufficient cause for the County to declare bid non-responsive.
The undersigned acknowledges receipt of the following addenda, listed by number and date appearing on each:
DATE
COMPANY NAME: ______________________________________________________________
Failure to return this page my result in rejection of bid. Page 2 of 2