This is Addendum No. 1 to the contract documents for the MDOT Houghton & L'Anse Garage Roof Repairs project issued by the State of Michigan Department of Technology, Management & Budget (DTMB) on November 24, 2021. The addendum clarifies project requirements and specifications for roof repair work at two locations: Houghton and L'Anse garages. The bid date remains Wednesday, December 8, 2021, and a mandatory pre-bid meeting was held with an attendee list attached to the addendum. The addendum modifies special working conditions to specify that work inside the buildings is limited to four ten-hour workdays during summer months when State employees work, while work outside the buildings may be performed anytime Monday through Friday.
The addendum provides technical clarifications on the project drawings and specifications. For the L'Anse site protective entrance canopy, the addendum clarifies that welding shown in details 8 and 2 may be performed either in the field or at the shop, at the contractor's preference, with field welds requiring proper painting upon accepted visual inspection. For the Houghton site roof repair plan, the addendum revises the 4-inch PVC roof drain location and requires relocation of the storm structure 10 to 15 feet away from the building to the north beyond the storage shed, with the storm structure cover specified as an MDOT Type D cover.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 211105 Specifications 19322.pdf | ||
| 211105 Advertisment 19322.pdf | ||
| 211105 Plans 19322.pdf | ||
| Addendum 2 19322.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum #1 Page 1 of 1
ADDENDUM NO. 1
DATE: November 24, 2021
PROJECT: MDOT Houghton & L’Anse Garage Roof Repairs
OWNER: State of Michigan
DTMB FILE #: 591/19322.JBB
BID DATE: Wednesday, December 8, 2021 ** THIS ADDENDUM DOES NOT CHANGE THE
BID DATE**
The following shall be incorporated into the Contract Documents dated 5 NOV 2021.
GENERAL
The Mandatory Pre-Bid Meeting Attendee List is attached.
PROJECT MANUAL
Revise Section 00750 SPECIAL WORKING CONDITIONS item 3 to state:
3. The State employees will work 4 ten-hour days during summer months, so work inside of the building is limited to be performed during this time. Work outside the building can be performed anytime Monday – Friday.
DRAWINGS
A-101 PROTECTIVE ENTRANCE CANOPY (L’Anse Site) – Clarification: the welding shown in detail 8 and 2 are shown as a mixture of field and shop welds. The welds can be field, or shop welded at the contractor’s preference. Any field welds shall be properly painted upon an accepted visual inspection.
A-101 ROOF REPAIR PLAN (Houghton Site) – Revise the drawing to extend the 4” PVC Roof Drain and shift the storm structure another 10’-15’ away from the building, beyond the “storage shed” to the north. Also, revise the storm structure cover to be an MDOT Type D cover.
End of Addendum No. 1