This document is an addendum to Quote Request 90369 issued by the St. Johns River Water Management District in Florida for the fabrication of new aluminum walkways. The addendum addresses questions received from potential respondents regarding the Statement of Work and specifications. It clarifies that the cost of H-piles and protective coating for the walkways should be included in the overall cost, and that SS-316 hardware should be used for both aluminum and steel components. The quote request is for the fabrication of two 20-foot aluminum walkways and the delivery of four 30-foot H-piles to the District's Apopka Field Office. Responses are due by 3:00 p.m. on Monday, July 29, 2024.
The contract opportunity is limited to the State of Florida and Putnam County. Respondents are required to acknowledge receipt of this addendum in their submittals. The District's procurement specialist, Breanna Pierce, can be contacted for any questions regarding the addendum.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QR 90369 - Fabrication New Aluminum Walkways.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATE: July 22, 2024
TO: Interested Firms
FROM: Breanna Pierce, Procurement Specialist
SUBJECT: Addendum 1 to Quote Request 90369 – Fabricate New Aluminum Walkways
As a result of questions received from potential respondents, please be advised of the following changes to the subject Request for Proposal:
1. The time and date for the submittal of responses remains the same: 3:00 p.m., Monday, July 29, 2024
2. Question: Statement of Work - IV. Contractor Responsibilities - 4th bullet - H Piles HP 8 x 36 x 4' 6". There is no item on the Quote Code Schedule?
These piles shall be included in the cost of the walkway, no separate cost is required.
3. Question: The S1 sheet Note Specifications #6 is protective coating. There is no item on Quote Code Schedule?
Paint is for the H piles and shall be included in the cost of the H-piles.
4. Question: The S1 sheet Note Specifications Structural Steel # 4 and Structural Aluminum # 6 hard-ware. One states SS304 and the other SS316?
SS-316 shall be used for both aluminum and steel hardware.
NOTE: Please acknowledge receipt of this Addendum in your submittal.
If you have any questions regarding this addendum, contact Breanna Pierce at (386) 643-1168 or via email at bpierce@sjrwmd.com.