This Addendum 1 is issued by Gwinnett County Airport (Briscoe Field) in Georgia for the Taxiway Z Lighting and Airport Sign Retrofit Project (BL090-23). The project involves the supply, removal of old fixtures and signs, and installation of new lighting fixtures and airport signs at the airport taxiway. Key clarifications include requirements for either a general contractor's license or electrical contractor's license, and the critical directive that all old light fixtures removed during the project must be reused and carefully disconnected without damage or cutting of wires. Bid packages should be submitted to Gwinnett County Financial Services - Purchasing Division at 75 Langley Drive, Lawrenceville, Georgia 30046, with delivery accepted via UPS, FedEx, or truck with lift-gate. The pre-bid conference was scheduled for June 21, 2023, at 10:00 a.m. at the Airport Administration Building, 600 Briscoe Boulevard, Lawrenceville, Georgia 30046. The deadline for questions was June 22, 2023, at 3:00 p.m. Bids must remain open for 120 days after opening, and the Owner reserves the right to award to the lowest responsible, responsive bidder whose bid meets requirements and complies with Georgia law and FAA guidelines.

Bid security must be submitted in the form of a bid bond equal to five percent of the maximum bid price. The bidder qualification questionnaire requires documentation of relevant experience, bonding capacity, and organizational capabilities. Contractors must perform at least 40 percent of the work with their own forces and must be prequalified with the State Highway Division. All bids must include acknowledgment of all addenda and submission of affidavits regarding non-collusion. Pricing shall include all applicable sales taxes and fees. The successful bidder must execute the agreement and provide required contract security and insurance certificates within ten days of notice of award. Project completion timelines and any contract extensions will be determined during the preconstruction conference, which will address labor standards, equal employment opportunity obligations, and other contract-related matters.

Text of this file

BL090-23 Page 1

June 28, 2023

Addendum 1

BL090-23, Gwinnett County Taxiway Z Lighting and Airport Sign Retrofit Project

Clarification:

C1. The supplemental conditions have been revised to include a licensed electrician as indicated by the highlighted verbiage. Please replace the original supplemental conditions with the attached.

C2. The bidder qualification questionnaire has been revised to include a licensed electrician as indicated by the highlighted verbiage. Please replace the original bidder qualification questionnaire with the attached.

C2. Please note that it is the intention of the airport to re-use ALL old light fixtures removed during the project. Lights will need to be disconnected from their transformers and/or other connections – without cutting wires or otherwise damaged during removal.

Questions:

Q1. What are the licensing requirements for this project?

A1. Per the bid document, a vendor should provide either their general contractors license number OR their electrical license number, per clarification 1 and 2 above.

Q2. What address will the packages for this project be sent to?

A2. Packages for this project can be sent to:

Airport Administration

ATTN: TAXIWAY Z LIGHTING PROJECT

600 Briscoe Boulevard

Lawrenceville, GA 30046

Q3. Does the delivery address accept UPS and/or Fedex?

A3. The address does accept both UPS and Fedex deliveries. We do NOT have a loading dock and do NOT have a forklift. Any freight deliveries will require a truck with a lift-gate.

Q4. Is this project for supply only or installation and supply?

BL090-23 Page 2

A4. Supply, removal of old fixtures/signs, and installation of new fixtures/signs.

This addendum should be acknowledged in the space provided in the original bid document.

Failure to do so may result in your bid being deemed non-responsive.

Thank you.

Olivia Graves

Purchasing Associate II

Bid # BL090-23

Addendum No. 1 - IB-11

Gwinnett County Airport – Briscoe Field BL090-23

Taxiway Z Lighting and Airport Sign Retrofit June, 2023

SUPPLEMENTAL INSTRUCTIONS TO BIDDERS

1. DEFINED TERMS

1.1 Terms used in these INSTRUCTIONS TO BIDDERS are defined in the Bid Forms and

Construction Contract and shall have the intent and meaning assigned them therein.

1.2 The term “Successful Bidder” means the lowest, qualified, responsible, responsive BIDDER to whom OWNER (on the basis of OWNER'S evaluation as hereinafter provided) makes an award.

1.3 The term “Contractor” means the individual, partnership, firm, or corporation primarily liable for the acceptable performance of the work contracted and for the payment of all legal debts pertaining to the work who acts directly or through lawful agents or employees to complete the contract work.

1.4 The term “Bidding Documents” means the Bidding Requirements, Contract Forms, Bid

Forms, Conditions of the Contract, Specifications, Drawings, and Addenda issued by the

OWNER for the purpose of obtaining a bid on the Work.

2. BIDDING DOCUMENTS

2.1 Complete sets of Bidding Documents in digital form or for a non-refundable fee as stated in the Notice to Bidders may be obtained from ENGINEER.

2.2 Complete sets of bidding documents shall be used in preparing bids; neither OWNER nor

ENGINEER assume any responsibility for errors or misinterpretations resulting from use of incomplete sets of Bidding documents.

2.3 OWNER and ENGINEER in making copies of the bidding Documents available on the above terms do so only for the purpose of obtaining bids on the Work and do not confer a license or grant for any other use.

3. QUALIFICATIONS OF BIDDERS

3.1 By submission of a BID the BIDDER agrees, that if awarded a contract to perform on the

Site and with his own organization, work equivalent to at least FORTY PERCENT (40%) of the total amount of the Work to be performed under the contract. If during the progress of the Work hereunder, the CONTRACTOR requests an adjustment of such percentage and the

ENGINEER determines that it would be to the OWNER'S advantage, the percentage of the work required to be performed by the CONTRACTOR'S organization may be adjusted;

PROVIDED prior written approval of such adjustment is obtained from the ENGINEER.

3.1.1 Each BIDDER must furnish with his BID a list of items that he will perform with his own forces and the estimated total cost of these items.

3.1.2 The “Work” in Paragraph 3 of Qualifications of Bidders shall be defined as

Addendum No. 1 - IB-12

Gwinnett County Airport – Briscoe Field BL090-23

Taxiway Z Lighting and Airport Sign Retrofit June, 2023 work performed on the actual project site by the contractor's own personnel and equipment.

The prime contractor may supply materials to the job site, but such materials cannot be used toward requirement as physical work on the project unless the contractor uses the materials to complete their own scope of work. The Contractor is also responsible for the coordination and active supervision of the whole work of the project; however, Construction Management

Services cannot be considered physical work on the project for the purpose of the 40% requirement.

3.2 Unless otherwise specified, a bidder must submit evidence that they are prequalified with the

State Highway Division and are on the current “bidder’s list” of the state in which the proposed work is located. Bidders must provide evidence with their bid. Additional requirements for bid submission are specified in Item 12 of these Supplemental Instructions to Bidders.

4. EXAMINATION OF CONTRACT DOCUMENTS AND SITE

4.1 It is the responsibility of each Bidder before submitting a Bid, to (a) examine the Bidding

Documents thoroughly; (b) visit the site(s) to familiarize himself with local conditions that may in any manner affect costs, progress or performance of the work; (c) familiarize himself of federal, state and local laws, ordinances, rules and regulations that may in any manner affect cost, progress or performance of the Work; (d) study and carefully correlate BIDDER's observations with the Drawings and Specifications; and (e) notify ENGINEER of all conflicts, errors or discrepancies.

4.2 Before submitting a Bid, each BIDDER will, at BIDDER's own expense and assuming all risks, make or obtain any additional examinations, investigations, explorations, tests and studies and obtain any additional information and data which pertain to the physical conditions (surface, subsurface and Underground Facilities) at or contiguous to the site or otherwise which may affect cost, progress performance or furnishing of the Work and which bidder deems necessary to determine its Bid for performing and furnishing the Work in accordance with the time, price and other terms and conditions of the Contract Documents.

4.3 On request in advance, OWNER will provide each BIDDER access to the site to conduct such explorations and tests as each BIDDER deems necessary for submission of a Bid.

BIDDER shall fill all holes, clean up and restore the site to its former condition upon completion of such explorations.

4.4 The lands upon which the Work is to be performed, rights-of-way and easements for access thereto and other lands designated for use by Contractor in performing the work are owned by the OWNER. All additional lands and access thereto required for temporary construction facilities or storage of materials and equipment other than at locations indicated on the

Drawings are to be provided by Contractor.

4.5 The submission of a Bid will constitute an incontrovertible representation by BIDDER that

BIDDER has complied with every requirement of this Article 4, that without exception the

Bid is premised upon performing and furnishing the Work required by the Contract

Documents and such means, methods, techniques, sequences or procedures of construction

Addendum No. 1 - IB-13 as may be indicated in or required by the Contract Documents, and that the Contract

Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

5. ADDENDA AND INTERPRETATIONS

5.1 All questions about the meaning or intent of the Contract Documents are to be directed to

BUYER. Interpretations or clarifications considered necessary by ENGINEER in response to such questions will be issued by Addenda electronically mailed or delivered to all parties recorded by ENGINEER as having received the Bidding Documents.

The deadline for receipt of questions is June 22, 2023 at 3:00 p.m. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

5.2 Addenda may also be issued to modify the Bidding Documents as deemed advisable by

OWNER or ENGINEER.

5.3 Failure of any BIDDER to receive any such Addendum or interpretation shall not relieve

BIDDER from any obligation under this BID as submitted.

6. BID SECURITY

6.1 Each BID must be accompanied by Bid Security made payable to OWNER, in an amount of five (5) percent of the BIDDER's maximum BID PRICE in the form of a Bid Bond prepared on the form of Bid Bond included in the BID, duly executed by the BIDDER as principal and issued by a surety.

6.2 Attorneys-in-fact who sign the bid Bonds or Contract Bonds must file with each bond a certified and effectively dated copy of their power-of-attorney.

6.3 The Bid Security of the successful BIDDER will be retained until such BIDDER has executed the Agreement and furnished the required Contract Security and Insurance

Certificates, whereupon it will be returned; if the Successful BIDDER fails to execute and deliver the Agreement and furnish the required Contract Security and Insurance Certificates within ten (10) days of NOTICE OF AWARD, OWNER may annul the NOTICE OF

AWARD and the Bid Security of the BIDDER will be forfeited to OWNER as liquidated damages for such withdrawal, failure or refusal. The Bid Security of any BIDDER whom the OWNER believes to have a reasonable chance of receiving the award may be retained by

OWNER until the earlier of the seventh day after the “effective day of the agreement” by

OWNER to CONTRACTOR and the required Contract Security and Insurance Certificates are furnished, or One Hundred Twenty (120) days after the Bid Opening or such extension of time mutually agreeable to Owner and successful Bidder. Bid Security of other BIDDERS may be returned within seven (7) days of the Bid Opening.

Addendum No. 1 - IB-14

7. CONTRACT TIME.

7.1 The numbers of days within which, or the dates by which, the Work is to be substantially completed and also completed and ready for final payment (the Contract Time) are set forth in the Bid Form and the Agreement.

7.2 EXTENSION OF CONTRACT TIME

If satisfactory fulfillment of the Contract requires performance of work in greater quantities than those set forth in the Bid, the Contract time allowed for performance shall be extended on a basis commensurate with the amount and difficulty of the added work as determined by the Engineer, whose decision shall be final and conclusive.

If the normal progress of the work is delayed for reasons beyond his control, the Contractor shall, within 15 days after the start of such delay, file a written request to the Engineer for an extension of time setting forth therein the reasons and providing complete documentation for the delay which he believes will justify the granting of his request. The Contractor’s plea that insufficient time was specified is not a valid reason for extension of time. If the Engineer finds that the work was delayed because of conditions beyond the control and without the fault of the Contractor, he may extend the time for completion in such amount as the conditions justify.

Any authorized extension of the Contract Time will be in full force and effect the same as though it was the original Contract time.

7.3 AVAILABLE DAY

Any calendar day inclusive of Saturdays, Sundays, and Legal Holidays on which the

Engineer determines that the Contractor is not prevented from accomplishing at least five hours of productive work on the controlling item or items of work which would normally be in progress at that time by causes beyond his control, and not due to his fault or negligence, including but not restricted to unsuitable weather and its aftermath, suspension order of the

Engineer, acts of God, acts of public enemy, fire, flood, epidemic, quarantine, strikes, or freight embargo.

8. LIQUIDATED DAMAGES

8.1 Provisions for Liquidated Damages are set forth in the Agreement and Bid Form documents.

9. SUBSTITUTE OR “OR-EQUAL” ITEMS

9.1 The Contract, if awarded, will be on the basis of materials and equipment described in the

Drawings or specified in the Specifications without consideration of possible substitute or

“or-equal” Items. Whenever it is indicated on the Drawings or specified in the Specifications that a substitute or “or-equal” item of material or equipment may be furnished or used if acceptable to ENGINEER, application for such acceptance will not be considered by

Addendum No. 1 - IB-15

ENGINEER until after the Effective Date of the Agreement.

10. SUBCONTRACTORS, SUPPLIERS AND OTHERS

10.1 All BIDDERS shall submit as part of their BID on the prescribed schedules a list of all subcontractors and other persons and organizations (including those who are to furnish principal items of material and equipment) proposed for those portions of the Work as to which such identification is required. If requested by OWNER, the low BIDDER shall submit an experience statement with pertinent information as to similar projects and other evidence of qualification for each subcontractor, other person or organization. If OWNER after due investigation has reasonable objection to any proposed subcontractor, other person or organization, the OWNER may, before giving the NOTICE OF AWARD, require the apparent Successful bidder to submit an acceptable substitute without an increase in Bid

Price. If the apparent Successful Bidder declines to make any such substitution, the

Contract shall not be awarded to such BIDDER, but his declining to make any such substitution will not constitute grounds for sacrificing his Bid Security. Any subcontractor, other person, or organization so listed and to whom the OWNER does not make written objection prior to giving the NOTICE OF AWARD will be deemed acceptable to OWNER.

10.2 NO CONTRACTOR shall be required to employ any subcontractor, other person, or organization against whom he has reasonable objection.

11. BID FORM AND SCHEDULES

11.1 Bid Forms and schedules must be typed or completed in ink. Each Bid must be submitted on the prescribed form. All blank spaces and Bid Prices must be filled in.

11.2 The firm, corporation or individual name of the BIDDER must be signed in ink in the space provided for signatures on the Bid form. BIDS by corporations must be executed in the corporate name by the president or a vice-president (or other corporate officer accompanied by evidence of authority to sign), and the corporate seal must be affixed and attested by the secretary or assistant secretary of the corporation. The corporate address and state of incorporation shall be shown in the space provided.

11.3 BIDS by partnerships must be executed in the partnerships name and signed by a partner, whose title must appear under the signature and the official address of the partnership must be shown below the signature.

11.4 BIDS by individuals must be signed by the individual owner and the terms “doing business” or “Sole Owner” must appear under the signature.

11.5 The Bid shall contain an acknowledgment of receipt of all Addenda (the numbers of all addenda and the date each was received shall be filled in on the BID form).

11.6 The address and telephone number (Main, Mobile, Fax, etc.) to which communications

Addendum No. 1 - IB-16 regarding the BID are to be directed must be shown on the Bid Form.

11.7 Affidavits: Each BIDDER is required to duly execute the BIDDER's and Non-Collusion

Affidavits at the end of the BID.

11.8 All names must be typed or printed below the signature.

12. SUBMISSION OF BIDS

12.1 BIDS shall be submitted at the time and place indicated in the Advertisement. Each BID shall be enclosed in a sealed envelope and marked and addressed as required in the

Advertisement and shall be accompanied by the Bid Security and other required documents.

If the BID is sent through the mail or other delivery system, the sealed envelope shall be enclosed in a separate envelope with the notation “BID ENCLOSED: Taxiway Z Lighting and Airport Sign Retrofit Project, Gwinnett County Bid No. BL090-23” on the face thereof. Submit original and one copy of the Bid Form, Schedules, and other required documents as listed on page B-6. DO NOT SUBMIT THE PROJECT MANUAL OR

DRAWINGS WITH BID.

12.1.1 Indicate the following information on the outside of the sealed envelope containing the bid:

a. Project Name as stated on page 1 of the Bid Forms

b. Bidder’s Name and Address

12.1.2 Submit Bids to:

Gwinnett County Financial Services - Purchasing Division

2nd Floor

75 Langley Drive

Lawrenceville, Georgia 30046

13. MODIFICATIONS AND WITHDRAWAL OF BIDS

13.1 BIDS may be modified or withdrawn by an appropriate document duly executed (in the manner that a BID must be executed) and delivered to the place where BIDS are to be submitted at any time prior to the opening of BIDS. Requests for withdrawal or modified must be in writing.

13.2 If within twenty-four (24) hours after the time BIDS are opened, any BIDDER files a duly signed written notice with the OWNER and promptly thereafter demonstrates to the reasonable satisfaction of the OWNER that there was a material and substantial mistake in the preparation of his BID, that BIDDER may withdraw his BID and the BID Security will be returned. Thereafter, that BIDDER will be disqualified from further bidding on the Work.

14. OPENING OF BIDS

14.1 BIDS will be opened and (unless obviously non-responsive) read aloud publicly. An abstract

Addendum No. 1 - IB-17 of the amounts of the base BIDS and any major alternates will be made available to

BIDDERS after opening of BIDS. BIDS that have been withdrawn will be returned to the

BIDDER unopened.

15. BIDS TO REMAIN OPEN SUBJECT TO ACCEPTANCE

15.1 ALL BIDS shall remain open for One Hundred Twenty (120) days after the day of the opening, but OWNER may, in his sole discretion, release any BID and return the BID

Security prior to that Date.

16. AWARD OF CONTRACT

16.1 OWNER reserves the right to reject any and all BIDS, to waive any and all informalities not involving price, time or changes in the work, and to negotiate contract terms with the

Successful BIDDER, and the right to disregard all nonconforming, non-responsive, unbalanced or conditional BIDS. Also, OWNER reserves the right to reject the BID of any

BIDDER if OWNER believes that it would not be in the best interest of the Project to make any award to that BIDDER, whether because the BID is not responsive, or the BIDDER is unqualified or of doubtful financial ability or fails to meet any other pertinent standards or criteria established by OWNER. Discrepancies between the indicated sum or any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

16.1.1 Responsiveness shall be defined as:

a. The completeness and regularity of Bid Form;

b. A Bid Form without excisions or special conditions;

c. A Bid Form having no alternative bias for items unless requested in the Specifications

d. A Bid Form without obviously unbalanced unit prices;

e. Submission of a properly executed Bid Bond;

16.2 In evaluation of BIDS, OWNER will consider qualifications of the BIDDERS and whether or not the BIDS comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid form or prior to the Notice of Award.

16.3 OWNER may consider the qualifications and experience of subcontractors, other persons or organizations (including those who are to furnish the principal items of materials and equipment) proposed for those portions of the work as to which the identity of subcontractors and other persons and organizations must be submitted as provided in the Bid Documents.

Operating costs, maintenance considerations, performance data and guarantees of materials may also be considered by OWNER.

16.4 OWNER may conduct such investigations as he deems necessary to assist in the evaluation of any BID and to establish the responsibility, qualifications and other persons and organizations to do the work in accordance with the contract documents to OWNER's satisfaction within the prescribed time.

16.4.1 Responsibility shall be based on whether the BIDDER:

Addendum No. 1 - IB-18

a. Maintains a permanent place of business;

b. Has adequate plant equipment to do the work properly and within the time limit that is established;

c. Has adequate financial status to meet his obligations contingent to doing the Work.

d. Have been the general or electrical contractor engaged in construction of facilities of similar character for at least two cumulative years.

16.4.2 In considering BIDS for this Work, particular attention will be given to the method of construction which the BIDDER plans to follow; the available experienced and skilled men which he plans to use in the prosecution of Work; the types of equipment and materials he plans to install; and, he shall prepare and furnish this information in writing at the OWNER's request.

16.4.3 Furthermore, the successful BIDDER must, prior to the award of the Contract, be prepared to discuss in detail all manners relating to any special features of the Work with the end view of obtaining high-grade workmanship and proper performance of the Contract.

16.5 OWNER reserves the right to reject the BID of any BIDDER who does not pass any evaluation to OWNER's satisfaction.

16.6 If a contract is to be awarded, it will be awarded to the lowest BIDDER whose evaluation by

OWNER indicates to OWNER that the award will be in the best interests of the Project.

If the lowest or the best bid exceeds the funds available for the work, the Owner may reject all bids, or reduce the Scope of Work as necessary to diminish the total cost of the project to a sum compatible with the funds available for the specified work.

Award of the Contract, if awarded, will be made by the Owner, upon the recommendation of the Engineer and approval by the Federal Aviation Administration, to the lowest or best responsible, responsive Bidder, whose bid meets the requirement of the Owner, and complies with the applicable laws of the State of Georgia.

16.7 If a contract is to be awarded, OWNER will give the Successful BIDDER a NOTICE OF

AWARD within One Hundred Twenty (120) days after the day of Bid Opening, or such mutually agreeable extension of time.

16.8 Joint Ventures: Each co-venturer (hereinafter “partner”) in a Joint Venture (JV) must meet the minimum experience requirement as outlined in the Bid. If a Joint Venture is presented, then the JV shall submit a statement specifying the distribution of ownership in the JV (i.e.:

Firm A = 60%, Firm B = 40%).

The JV shall designate a Partner in Charge who shall act as the point of contact for both the present and future should the Commission need to contact them. Also, the JV Partner in

Charge shall complete at least 40% of the work as defined in the Bid.

Both named partners must have been engaged in similar projects of scope and magnitude of ograves Highlight

Addendum No. 1 - IB-19 airfield grading and paving work on airports under FAA guidelines and regulations for at least two cumulative years each. Bidder shall submit evidence of such experience.

The designated Project Manager must have and show evidence of at least two cumulative years of prior airport airfield grading and paving supervisory experience. Each partner within the JV must be properly licensed for the scope of work on the project.

17. BID AND CONTRACT SECURITY AND INSURANCE

17.1 Contract document requirements in this Manual set forth OWNER'S requirements as to

Bonds and Insurance. When the Successful BIDDER delivers the executed Agreement to

OWNER it shall be accompanied by the required Contract Security and Insurance certificates and Policies.

17.2 All Bonds (Bid, Payment and Performance) must be signed or countersigned by the surety company's proper resident agent, authorized to do business in the State of Georgia on whom service can be made in the event of litigation.

18. SIGNING OF AGREEMENT

18.1 When OWNER gives a NOTICE OF AWARD to the successful BIDDER, it will be accompanied by two (2) unsigned counterparts of the Agreement and all other required

Contract Documents. Within ten (10) days following the effective date of “Award”

CONTRACTOR shall sign and deliver all executed counterparts of the Agreement to the

OWNER with all other Contract Documents including insurance certificates and executed bonds attached thereto. ENGINEER will identify those portions of the Contract Documents not fully signed by the OWNER and CONTRACTOR and such identification shall be binding on all parties.

19. ESTIMATED QUANTITIES

19.1 Laws and Regulations: The BIDDER's attention is directed to the fact that applicable

Federal and State laws, municipal ordinances and the rules and regulations of all authorities having jurisdiction over construction of the Project shall apply to the Contract throughout, and they will be deemed to be included in the Contract the same as though therein written out in full.

19.2 Estimated Quantities: Where quantities of work are given in the BID these are approximate and are assumed solely for comparison of the BIDS. They are not guaranteed to be accurate statements or estimates of quantities of work that are to be performed under the contract, it being presumed that the BIDDER has verified the quantities necessary to complete the Work of the contract as intended, and any departure therefrom will not be accepted as valid grounds for any claim for damages, for extension of time or for loss of profits; not with any additional payment be made, regardless of the actual quantities required or ordered to complete the Work.

Addendum No. 1 - IB-20

20. PRE-BID CONFERENCE

20.1 A pre-bid conference will be held at 10:00 a.m. on June 21st, 2023 at the Airport

Administration Building Conference Room, 600 Briscoe Blvd., Lawrenceville, GA 30046.

Representatives of the Owner and Engineer will be present to discuss the project. Bidders are encouraged to attend and participate in this conference. ENGINEER will transmit to all plan holders and prospective bidders of record a summary of the conference and such addenda as ENGINEER considers necessary in response to questions arising at the conference. Potential bidders should attend pre-bid conference to submit an informed bid.

Bidders are encouraged to schedule a site visit after the pre-bid meeting.

21. EQUAL EMPLOYMENT OPPORTUNITY

a. EQUAL EMPLOYMENT OPPORTUNITY: Attention of Bidders is called to the requirement for ensuring that employees and applicants for employment are not discriminated against because of their race, color, religion, sex, or national origin.

b. EMPLOYMENT PRACTICES: (1) Contractor shall, to the greatest extent practicable, follow hiring and employment practices for work on the project which will provide new job opportunities for the unemployed and underemployed, and (2) insert or cause to be inserted the same provision in each construction subcontract.

21.1 Equal Employment Opportunity Requirements

a. Bidders must comply with the President's Executive Order No. 11246 which prohibits discrimination in employment regarding race, creed, color, sex, or national origin.

b. Each bidder shall complete, sign and include in his bid proposal the Equal

Opportunity Report Statement. When a determination has been made to award a contract to a specific Contractor, such Contractor shall, prior to award, after award of both, furnish such other pertinent information regarding his own employment policies and practices as well as those of his proposed subcontractors, the OWNER, or the Secretary of Labor may require. All such information required of a subcontractor shall be furnished by the Contractor.

22. SALES TAX

22.1 Lump item unit pricing shall include all sales taxes and other applicable taxes and fees.

23. PRECONSTRUCTION CONFERENCE

23.1 Attention of BIDDERS is called to the preconstruction conference to be held with the

Successful BIDDER and all known subcontractors, prior to the issuance of a NOTICE TO

PROCEED. This Conference will be held to acquaint the Successful BIDDER with the

Addendum No. 1 - IB-21 contract provisions concerning the Labor Standards, Equal Employment Opportunity obligations, and other items related to the contract.

END OF INSTRUCTION TO BIDDERS

Addendum No. 1 - B-14

BIDDER QUALIFICATION QUESTIONNAIRE

Submitted by:

Name of Bidder

General /Electrical Contractor's License #

( ) An Individual ( ) A Partnership ( ) A Corporation

Federal Identification #

Principal Office Address:

(1) How many years has your organization been in business as a contractor under your present name?

(2) How many years’ experience in Electrical Installation work has your organization had as a general or electrical contractor?

As a Subcontractor?

(3) List below the requested information concerning projects your organization has completed in the last five (5) years for the type of work required in this project. (Use additional sheets if necessary)

Project Contract Required Actual Name/Address/Tel Title Amount Completion Date Completion Date of Owner

Addendum No. 1 - B-15 Gwinnett County Airport – Briscoe Field BL090-23

Taxiway Z Lighting and Airport Sign Retrofit June, 2023

Project Contract Required Actual Name/Address/Tel

Title Amount Completion Date Completion Date of Owner

(4) Have you ever failed to complete any work awarded to you? If so, where and why?

(5) Has any officer or partner of your organization ever been an officer or partner of some other organization that failed to complete a construction contract? If so, state name of individual, name of other organization, and reason, therefore.

(6) Has any officer or partner of your organization ever failed to complete a construction contract handled in his own name? If so, state name of individual, name of owner and reason, therefore.

(7) Give below any information which would indicate the size and capacity of your organization, including number of employees, equipment owned by your organization, etc., which are available for utilization on this Contract.

Addendum No. 1 - B-16 Gwinnett County Airport – Briscoe Field BL090-23

Taxiway Z Lighting and Airport Sign Retrofit June, 2023

(8) What is your bonding capacity?

(9) What amount of your bonding capacity has been used as of the date of this bid?

(10) How many applications for performance and payment bonds have you made in the last three

(3) years?

(11) How many of these applications were not approved?

(12) Have any claims been filed against your surety bond company in the last five (5) years? If so, describe the nature of the claims and give the names of the surety companies, dates of each claim, identifying numbers of each claim, amounts of each claim, and the status of each claim. (Use additional sheets if necessary.)

(13) Has your company been in disputes or litigation in the last five (5) years over construction projects which are completed or still pending for completion? If so, describe the nature of the disputes or litigation and state the Owner's Name, Address, Telephone, and amount of disputes or litigation. (Use additional sheets if necessary.)

Addendum No. 1 - B-17 Gwinnett County Airport – Briscoe Field BL090-23

Taxiway Z Lighting and Airport Sign Retrofit June, 2023

I, the undersigned, do hereby declare that the foregoing statements are true and correct, all as of the date hereinafter set forth, and that those examining this document have my permission to contact any or all of those parties listed in this questionnaire. Incorrect or misleading statements in this questionnaire shall be grounds for a determination of non-responsibility with respect to such contractor.

(SIGNATURE OF BIDDER)

(TYPE OR PRINT COMPANY NAME)

(TYPE OR PRINT ADDRESS)

BL090-23 ADD1
LZU_addendum No.1 Attachments

Other files

File Type Posted
Award Information —
BL090-23 NOT —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .