Ad1025.pdf
PDF 2 MB Posted
- Attached to
- WRC Oxford Woods WTP Restoration
- Solicitation number
- Oak-0000001025
- Issued by
- Oakland County, Michigan
About this file
This is an advertisement and bidding document for the Oxford Woods Water Treatment Plant (WTP) Restoration Project issued by the Oakland County Water Resources Commissioner in Michigan. The project involves restoration and welding work for three water storage tanks: two 17,039-gallon pressure filter vessels and one 8,600-gallon hydropneumatic tank. Specific work includes second manway installation, weld repairs, patch plate installations, pit welding, exterior and piping surface preparation and coating, wet interior surface preparation and coating, concrete saddle surface preparation, manway gasket replacement, and piping nuts and bolt replacements. Electronic sealed bids will be received via BidNet Direct, with a bid opening scheduled for Tuesday, October 28, 2025 at 1:30 PM via Microsoft Teams. The project is expected to commence on or after November 3, 2025, with substantial completion targeted by May 1, 2026.
The contract will be awarded to the lowest responsive and responsible bidder, with a total contract price to be determined through unit pricing for specific line items. A 5% bid bond is required with the proposal, and the successful bidder will need to provide performance, payment, and maintenance bonds. The project will be funded through the Oakland County Water Resources Commissioner's budget, with bidders required to submit comprehensive documentation including experience and qualification statements, safety compliance certifications, and detailed technical specifications. Contractors must self-perform at least 25% of construction trade work and have an R-Stamp certification for welding on pressure vessels. The project involves complex restoration work with specific surface preparation, coating, and welding requirements for potable water storage infrastructure.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Form DC-116 ADVERTISEMENT
JIM NASH
OAKLAND COUNTY WATER RESOURCES COMMISSIONER
Page ADV-1 of ADV-2 4-23-2024
OXFORD WOODS WTP RESTORATION PROJECT - WELDING
OAKLAND COUNTY, MICHIGAN
Electronic sealed Bids will be received by the Owner for the following project:
One 8,600 gallon Hydropneumatic Tank:
• Second manway installation.
• Coordination with work completed by others: Exterior and piping surface preparation and coating. Wet interior surface preparation and coating. Concrete saddles surface preparation and coating. Manway gasket replacement. Piping nuts and bolts replacement.
Two 17,039 gallon Pressure Filter Vessels:
• As-directed weld repairs, patch plates, and pit welding.
• Coordination with work completed by others: Exterior and piping surface preparation and coating. Wet interior surface preparation and coating. Filter Media Replacement. Manway gasket replacement. Piping nuts and bolts replacement.
THE BIDS WILL BE OPENED AND PRESENTED PUBLICLY VIA MICROSOFT TEAMS AND READ
AT THE FOLLOWING DATE AND TIME: Tuesday, October 28, 2025 at 1:30 PM
Please see the link below to the Microsoft Teams Bid Opening:
https://teams.microsoft.com/l/meetup-join/19%3ameeting_NTQ2MGZlOGMtNWNiNi00OGIwLWIwZGYtOTc0MDllOWRkMzNk%40thread.v2/ 0?context=%7b%22Tid%22%3a%226dd9592c-fa62-4c52-920e-c6981494a443%22%2c%22Oid%22%3a%22a40a441f-c712-4a30-82e9-4c6288e50f0d%22%7d
Meeting ID: 228 936 735 024 6 Passcode: aR9f6bo3 Dial in by phone +1 248-333-6396,,208172165# United States, Pontiac Phone conference ID: 208 172 165#
BIDS MUST BE POSTED TO THE BidNet Direct Website no later than the following date and time: Thursday, October 28, 2025 at 1:30 PM
Bidders shall review and comply with the Information for Bidders, which is incorporated by reference, and carefully review all Bidding Documents. Bids submitted after the exact time specified for receipt will not be considered.
Bidding Documents will be available on the BidNet Direct website. The proposed Contract Documents under which the work will be performed are included in the Bidding Documents. For questions about BidNet Direct, refer to https://www.oakgov.com/government/purchasing/bidder-registration/bid-solicitation-public-search.
https://teams.microsoft.com/l/meetup-join/19%3ameeting_NTQ2MGZlOGMtNWNiNi00OGIwLWIwZGYtOTc0MDllOWRkMzNk%40thread.v2/0?context=%7b%22Tid%22%3a%226dd9592c-fa62-4c52-920e-c6981494a443%22%2c%22Oid%22%3a%22a40a441f-c712-4a30-82e9-4c6288e50f0d%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_NTQ2MGZlOGMtNWNiNi00OGIwLWIwZGYtOTc0MDllOWRkMzNk%40thread.v2/0?context=%7b%22Tid%22%3a%226dd9592c-fa62-4c52-920e-c6981494a443%22%2c%22Oid%22%3a%22a40a441f-c712-4a30-82e9-4c6288e50f0d%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_NTQ2MGZlOGMtNWNiNi00OGIwLWIwZGYtOTc0MDllOWRkMzNk%40thread.v2/0?context=%7b%22Tid%22%3a%226dd9592c-fa62-4c52-920e-c6981494a443%22%2c%22Oid%22%3a%22a40a441f-c712-4a30-82e9-4c6288e50f0d%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_NTQ2MGZlOGMtNWNiNi00OGIwLWIwZGYtOTc0MDllOWRkMzNk%40thread.v2/0?context=%7b%22Tid%22%3a%226dd9592c-fa62-4c52-920e-c6981494a443%22%2c%22Oid%22%3a%22a40a441f-c712-4a30-82e9-4c6288e50f0d%22%7d https://www.oakgov.com/government/purchasing/bidder-registration/bid-solicitation-public-search https://www.oakgov.com/government/purchasing/bidder-registration/bid-solicitation-public-search
Form DC-116 ADVERTISEMENT
JIM NASH
Page ADV-2 of ADV-2 4-23-2024
QUESTIONS, COMMENTS, or CONCERNS of any Bidder regarding the Bidding Documents or the project, must be submitted in writing via the BidNet Direct website by the following date and time:
Thursday, October 16, 2025 at 3:00PM. No questions received after this time will be given consideration. Questions will be reviewed, and formal responses will be disseminated via addenda on BidNet Direct.
Addenda issued to Bidders prior to the date of receipt of Bids shall become a part of the Contract Documents and all Bids shall include the work described in each and every addendum issued.
A certified check, cashier's check, or Bid Bond for a sum not less than five percent (5%) of the amount of the proposal will be required for each proposal.
Owner reserves the right to accept any proposal, to reject any proposal and to waive irregularities in the proposals.
Form DC–119 INFORMATION FOR BIDDERS
Page IB-1 of IB-9 4-23-2024
1. SCOPE OF WORK
The work under this Contract shall consist of the items listed in the Bidding Documents, including all incidentals necessary to fully complete the project in accordance with the proposed Contract Documents.
2. RECEIPT AND OPENING OF BIDS
A. The Bid shall be submitted as one combined electronic pdf file to the BidNet Direct website as indicated in the Advertisement.
B. The Bids must be submitted only on the forms provided by Owner. All blank spaces for bid prices must be filled in, in ink and scanned as a pdf or typewritten, and the Bid Form must be fully executed when submitted and not modified in any way.
C. The Bids shall be made in full conformity with all the instructions, requirements and conditions set forth in the Bidding Documents. Bids are firm, and no bid may be withdrawn for a period of 10 days after opening of bids. Withdrawal of the Bid will result in the forfeiture of the Bidder’s Bid Bond.
D. Any Bids received after the exact time specified in the Advertisement will not be considered. This material requirement is not subject to waiver by Owner.
3. ESCROW BID DOCUMENTS
The three (3) lowest Bidders will be required to place their Bid Documents in escrow within three
(3) business day of the Bid opening in accordance with the attached Escrow Bid Documents Provision Specification. In addition, Owner reserves the right to require additional Bidders to place their Bid documents in escrow also, as provided in the attached Escrow Bid Documents Specification. Such additional Bidders will be notified within 24 hours of the Bid. Contractors bidding on this project are required to maintain all bid notes, take offs, and other Bidding Documents required for inclusion in the Escrow Bid Documents. Failure to submit the Escrow Bid Documents as required may result in a rejection of the Bid.
4. DEFINITIONS
Certain terms used in the Contract Documents shall have the meanings indicated in the General Conditions and Supplementary Conditions which are part of the Contract Documents.
5. INSPECTION OF SITE, INSPECTION OF CONTRACT DOCUMENTS, PLANNING, AND
ANALYSIS
A. Before submitting a Bid, each Bidder is responsible for inspecting the site of the proposed work, and the surrounding premises, to arrive at a clear understanding of the conditions under which the work is to be performed.
B. Before delivery of its Bid, each Bidder is held to have compared the conditions of the site where work is to be performed with the Contract Documents and to have satisfied itself as to the conditions of the site and surrounding premises, including any obstructions, all
Page IB-2 of IB-9 4-23-2024 excavating, filling in, and quantities, and any other conditions affecting the work, including the weather conditions of the project area. Each Bidder must obtain first-hand information concerning the available facilities for receiving, transporting, handling, and storing construction equipment and materials and concerning other local conditions that may affect its work. Each Bidder must acquaint itself with the character and extent of the operations of Owner and any other contractors in the area of the work, so that the Bidder can plan its work accordingly.
C. Bidders must estimate the quantity of materials, labor and equipment required for the work by examination of the site and a review of the Contract Documents including Addenda, and by carefully considering all other relevant factors. Bidder warrants that by submitting its Bid, it had no misunderstanding concerning the quantities or nature of the work to be performed, and the Bidder will assert no such claim asserting such a misunderstanding.
D. No allowances or extra payment will be made to Contractor because of costs or expenses occasioned by Contractor’s failure to comply with the provisions of this Article, or by reason of error or oversight on the part of the Bidder, or on account of interference by the activities of Owner or any other contractor where those activities are apparent or are made known to the Bidders during the bidding process.
E. For bidding purposes, the Bidder is responsible for evaluating the compatibility of proposed construction methods with the Contract Documents, and soil and site information. Bidders must carefully study and compare all portions of the Contract Documents and must notify the Engineer, in writing, prior to the deadline for pre-bid questions, of any concerns, questions, apparent ambiguities, conflicts, incompatibilities, apparent errors, or other discrepancies evident in the Contract Documents.
F. The successful Bidder must complete the work under whatever conditions it may create by its own actions or inactions, sequence of construction, construction means and methods, or other conditions it may create or cause to be created at no additional cost to Owner.
6. AWARD OF CONTRACT
A. The Contract, if awarded, will be awarded to the lowest, responsive, and responsible bidder, subject to the final approval by the Owner. The Contract will be awarded subject to receipt of funds to finance the project and acquisition of easements, during which time the Bids of the lowest three responsive, responsible Bidders will be held.
B. The party to whom the Contract is awarded will be required to execute the Agreement and obtain the Performance Bond, Labor and Material Bond and Maintenance and Guarantee Bond and shall provide proofs of insurance coverage in accordance with the Contract Documents within ten (10) calendar days of the delivery date of the Notice of Award to the successful Bidder. The necessary Agreement and Bond forms shall accompany the Notice of Award. If the Contractor awarded the project fails to execute the Agreement, submit the Performance Bond, Labor and Material Bond and Maintenance and Guarantee Bond and provide proof of insurance coverage in accordance with the Contract Documents within ten (10) calendar days of the delivery date of the Notice of Award, Owner may declare the Contractor in default, in which case the Bid Bond accompanying the Bid will be forfeited to Owner.
Page IB-3 of IB-9 4-23-2024
7. INTERPRETATION OF CONTRACT DOCUMENTS
A. Neither Owner nor the Engineer will give verbal instructions prior to the award of the Contract. Any verbal statements regarding the Contract by any person are not authorized and do not constitute representations, warranties, modifications, agreements, or promises, express or implied, and may not be relied upon by Bidders.
B. Bidders seeking explanations regarding the project, or the Contract Documents must submit written requests to the Engineer, and if explanations are necessary, a reply will be made in the form of an Addendum, a copy of which will be forwarded to all parties that have taken out Contract Documents. The determination of the necessity of explanations will be in the sole discretion of the Engineer and Owner and no obligation to provide a reply or addendum will be implied.
C. Questions, comments, or concerns of any Bidder regarding bidding or the Contract
Documents or the project, must be submitted in writing on the Bidnet Direct website and in advance of the opening of bids per the time specified in the Advertisement
D. Addenda issued to Bidders prior to the date of receipt of Bids shall become a part of the
Contract Documents and all Bids shall include the work described in each and every Addendum issued.
8. NAME AND STATUS OF BIDDER
A. The name and legal status of the Bidder, that is, as a corporation, limited liability company, partnership, limited partnership or individual, must be stated in the Bid form.
B. The place of residence of Bidder, or the office address in the case of a firm or company must be stated in the Bid Form.
C. Unless the legal status of the Bidder is an Individual, the signature(s) of the signing official(s) must be accompanied by the appropriate Resolution or Certificate Form found at the end of the Bid Form, properly executed, authorizing the official(s) to sign both the Bid Form and the Contract. Failure to submit this form is basis for rejecting the Bid.
9. QUALIFICATION OF BIDDERS AND SUBCONTRACTORS
A. Except as otherwise reserved herein, Owner will only award the Contract to a responsible Bidder. A finding that the Contractor is not responsible in connection with the project shall not necessarily preclude the Bidder from bidding and performing work on other projects for Owner.
B. Factors to be considered in determining whether Owner’s standard of responsibility has been met shall include, but not be limited to, whether the Contractor has:
a. The appropriate financial, material, equipment, facilities, and personnel resources and expertise available, or the ability to obtain them, necessary to indicate it can meet all contractual requirements;
b. A satisfactory record of performance;
Page IB-4 of IB-9 4-23-2024
c. A satisfactory record of integrity;
d. Qualified legally to contract with Owner and has supplied all necessary information in connection with the inquiry concerning responsibility.
e. If Contractor has been deemed non-responsible in the past, provided a detailed explanation of its remedial actions after the determination to address any concerns expressed by the authority making the declaration such that the authority would consider awarding a contract to the Contractor, notwithstanding past concerns about Contractor’s performance.
C. The Contractor must supply information requested by Owner concerning the responsibility of the Bidder. If the Bidder fails to supply the requested information, Owner must base the determination of responsibility upon any available information or may find the Bidder non-responsible if such failure is unreasonable. A finding that the Bidder has failed to make a required disclosure or submitted false information may result in immediate disqualification of the Bidder.
D. Within 10 days after bids are received by Owner, the Contractor who has submitted the low bid must, upon request of Owner, complete and submit to Owner the following:
1) MIOSHA Form 300 – “Log of Work-Related Injuries” for the last three (3) years.
2) MIOSHA Form 300A - “Summary of Work-Related Injuries & Illnesses” for the last three (3) years.
E. In addition to meeting the criteria set forth in this Article, and the submission of the required information requested herein, the ability of the Contractor and its identified Subcontractors to proficiently handle technical issues, safety, scheduling, and administrative issues as demonstrated by its past performance on projects for Owner, as well as projects for other public agencies, will be considered in determining whether a Contractor is a responsible contractor for this project. Past performance issues to be considered include, but are not limited to, the following:
a. Failure to adhere to and/or comply with Contractor’s obligations in the Contract
Documents;
b. Failure to follow administrative procedures and provisions in the Contact Documents;
c. Submission of false claims or falsely inflated claims;
d. Failure to prosecute the work in accordance with the Plans and Specifications included in the Contract Documents; and
e. Failure to follow bidding instructions.
F. The Bidder shall promptly submit upon request by Owner any additional information necessary to satisfy Owner that the Bidder is adequately prepared to fulfill the Contract.
Page IB-5 of IB-9 4-23-2024
G. The existence of any judgment, citation, default, finding of non-responsibility or other negative information disclosed by Contactor in its Experience and Qualification Statement or independently discovered by Owner, or Contractor’s failure to provide the certifications required by this Article, will be considered, among all other factors, in determining whether a Contractor is a responsible Bidder for this project. As part of its response, Contractor may submit an explanation of the facts giving rise to the judgment, citation, default, or negative finding, or reasons why the required certifications cannot be provided, and ask Owner to deem the Contractor both responsive and responsible notwithstanding such facts or omissions.
H. The requirements identified above are not an exhaustive or exclusive list of all qualifications required of the Contractor, its Subcontractors, or personnel. The minimum requirements indicated above are in addition to any other requirements contained elsewhere in the Contract Documents and/or typically considered under state or federal procurement law.
I. Owner may, when circumstances warrant, accept any Bidder as a responsible Bidder despite its failure to meet all the minimum standards set out herein. To the extent that special circumstances exist which a Bidder believes render the Bidder a qualified and responsible Bidder for this project, despite the failure to meet one or more of the standards for qualification set out herein, the Bidder may submit a notarized sworn statement explaining the special circumstances and requesting consideration of its Bid.
Notwithstanding the foregoing, Owner has no obligation to consider such special circumstances, or to disregard the requirements set forth in this Article and elsewhere in the Contract Documents and deem the Bidder responsible.
J. Bidder must attend a pre-award conference to satisfy Owner that the Bidder is adequately prepared to fulfill the Contract.
K. If a Bidder who otherwise would have been awarded a contract is found non-responsible, a written determination of non-responsibility setting forth the basis of the finding will be prepared by Owner upon request. A copy of the determination will be sent promptly to the non-responsible Bidder. The final determination will be made part of the bid file.
L. The Contractor must self-perform at least 25% of the construction trade work as determined by dollar value. This does not include General Conditions.
10. CONTRACTOR AND SUBCONTRACTOR INFORMATION AND LISTING
A. Bidder must provide a completed Experience and Qualification Statement (DC-118) with its bid. Additional qualification information as requested by Owner shall be submitted within ten (10) calendar days after bids are received by Owner including but not limited to a completed Experience and Qualification Statement (DC-118) for each Subcontractor who will work on the project.
B. Bidders shall submit with their bid a list by name, trade, and scope of work each Subcontractor who will perform Work with a value more than ten percent (10%) of Bid Total.
Page IB-6 of IB-9 4-23-2024
11. PRELIMINARY SCHEDULE
A. Each Bidder shall submit with its bid a Preliminary Schedule demonstrating the Bidder’s plan to complete the construction work within the time allowed in the Agreement and to achieve the completion of any milestones identified in the Contract Documents. The requirements of the Preliminary Schedule are described in the General Specifications.
B. Failure to provide the requested schedule may result in the Contractor being declared non-responsive.
C. The Bidder’s Preliminary Schedule shall be based on the dates identified in the Bidding
Documents by Owner.
12. ADDITIONAL BIDDING INFORMATION
The Advertisement, which precedes the "Information for Bidders" and the Contract Documents as defined in the General Conditions may contain additional bidding information and is considered a part of these instructions.
13. EQUALS AND SUBSTITUTIONS
Anticipated proposed Equals and Substitutions shall not be the basis for any bid pricing. For bidding, Bidders shall base their bid on the design and any specified products. Equals or Substitutions may be submitted for consideration after the award of the Contract. Approval of proposed Equals or Substitutions are discretionary, and Contractor waives the right to make a claim on that basis. Bidders shall not assume that any contemplated Equal or Substitutions will be approved. The Contractor will be responsible for Engineer Fees for review, analysis, tests and/or all other costs necessary to review, analyze and/or implement a proposed Substitution regardless of whether the Bid is approved.
14. BID BOND
A. Each shall be accompanied by a Bid deposit in the form of a certified check, a cashier's check or Bid Bond executed by the Bidder and a qualified, acceptable Surety Company, payable to the Owner, in the amount of five percent (5%) of the accompanying Bid, as guarantee on the part of the Bidder that it will, if called upon to do so, enter into a Contract in the form of the Contract Documents, perform the work required by the Contract Documents, at the prices stated, and furnish acceptable surety for its faithful and entire fulfillment. All cashier’s and certified checks will need to be mailed or hand delivered to the Oakland County Water Resource Commissioner’s office located at One Public Works Drive, Building 95 West, Waterford, MI 48328.
B. The Bid deposits of all, except the three (3) lowest Bidders, will be returned within forty-eight (48) hours after the Bids are opened. The Bid deposits of the apparent second and third lowest Bidders that Owner has retained will be returned after the signed Contract has been delivered and the required bonds and insurance of the Contractor have been finally approved by Owner, or after rejection of all Bids.
Page IB-7 of IB-9 4-23-2024
15. GUARANTEE BONDS
A. In addition to the Bid Bond, the Contractor shall furnish Owner the following bonds prior to the Contract being executed:
a. A Performance Bond in an amount at least equal to one hundred percent (100%) of the Contract Price as security for faithful performance on the Contract.
b. A separate Labor and Material Payment Bond in an amount at least equal to one hundred percent (100%) of the Contract Price as security for payment of all persons performing labor and furnishing materials in connection with the Contract.
16. BOND REQUIREMENTS
A. All bonds required of Bidder or Contractor shall meet the following requirements:
a. The Bidder or Contractor shall pay the premiums.
b. The form of the bonds shall be as appended herewith (NOTE: the form of Bid
Bond is NOT incorporated in the Contract Documents).
c. The surety on the bonds shall be a corporate bonding company named on the current list of Surety Companies acceptable on Federal Bonds as published in the U.S. Treasury Department Circular Number 570. If the surety is ever delisted on the cited Circular, Owner may, in Owner’s sole discretion, demand and Contractor shall provide replacement Bonds from a then-listed surety at no additional cost to Owner
d. The surety shall be a corporate bonding company authorized and admitted to transact business in Michigan and subject to service of process and personal jurisdiction in Michigan. A copy of the certificate issued by the State of Michigan evidencing such authorization shall be furnished to Owner.
e. The surety shall be a corporate bonding company, which is otherwise satisfactory to Owner. Without limiting the other factors upon which Owner may determine the acceptability of a surety, Owner specifically reserves the right to reject any surety which has denied, delayed, or obstructed payment or discharge of the sureties’ obligations under a prior bond in favor of Owner.
f. Attorneys-in-Fact who sign bonds must file with each bond a certified copy of a currently effective and dated Power of Attorney.
g. Owner may, but is not obligated to, require the substitution of any of the bonds by
Bidder or Contractor upon the occurrence of any of the events referred to herein and in the General Conditions or Supplementary Conditions.
h. Providing the bonds required hereunder shall not establish that a Bidder is qualified, responsive, or responsible, and shall not limit Owner’s right to review Bidder's qualifications and reject any Bid.
Page IB-8 of IB-9 4-23-2024
17. REJECTION OF BIDS
Owner reserves the right to reject any or all Bids. Owner further reserves the right to waive any non-material irregularity or informality in the Bids. Owner reserves the right to reject any Bid submitted by any Bidder that Owner determines is not a responsive or responsible Bidder based on information supplied by the Bidder or on any other information that Owner receives or acquires on its own, including the experience of Owner and/or any other public agency owner with the Bidder. Owner’s rights in this regard may be exercised in Owner’s sole discretion and Owner shall not have any obligation to exercise or refrain from exercising these rights.
18. OVERTIME COMPENSATION
Refer to the Labor Standards Provisions, EPA Form 5720-4 and the U.S. Department of Labor Memorandum No. 143 for further information. Labor compensation, including Overtime shall be governed by applicable local, federal, and state law and regulations.
19. CONTRACT DOCUMENTS
Each Bidder is obligated to carefully review all materials included or referenced in the Contract Documents including, without limitation, the General and Supplementary Conditions. The Contract Documents are defined in the General and Supplementary Conditions and the Bidder must familiarize itself with all provisions, terms, and conditions of all Contract Documents.
20. OWNER’S RESERVATION OF RIGHTS
A. In addition to Owner’s rights in Article 23 [Rejection of Bids], Owner reserves the following rights in connection with this Advertisement:
a. Withdraw the Advertisement at any time, in Owner’s sole discretion.
b. Make an award under the Advertisement in whole or in part.
c. Disqualify any Bidder whose conduct and/or Bid fails to conform to the requirements of the Advertisement.
d. Seek clarifications and revisions of Bids.
e. Use Bid information obtained through site visits, management interviews and
Owner’s investigation of a Bidder’s qualifications, experience, ability or financial standing, and any material or information submitted by the Bidder in response to the Owner’s request for clarifying information during evaluation and/or selection under the Advertisement.
f. Prior to the bid opening, direct Bidders to modify their Bid addressing all addenda including addenda that may modify the Bidding Documents.
g. Change any of the scheduled dates.
h. Eliminate any mandatory, non-material specifications that cannot be complied with by all the prospective Bidders.
Page IB-9 of IB-9 4-23-2024
i. Waive any requirements that are not material.
j. Negotiate with the successful Bidder within the scope of the Bidding Documents in the best interests of the Owner.
k. Conduct contract negotiations with the next responsible Bidder, should the
Owner be unsuccessful in negotiating with the lowest, responsive, responsible Bidder.
l. Utilize all ideas submitted in the Bids received.
Require clarification at any time during the procurement process and/or require correction of arithmetic or other apparent errors for the purpose of assuring a full and complete understanding of a Bidder’s Bid and/or to determine a Bidder’s compliance with the requirements of the solicitation.
OAKLAND COUNTY - PROJECT SUMMARY - 1
SECTION 00 00 40
PROJECT SUMMARY
PART 1 – GENERAL
This Project Summary is an overview of the entire Project and is intended, but is not guaranteed, to place all project specifics in one location to aid Bidders.
1.01 SCHEDULE
The Contractor is to abide by the following schedule:
Commence work on or after November 3, 2025.
Substantial Completion by May 1, 2026, including cure and disinfection times.
Note that only one tank can be out-of-service at a time. The Owner reserves the right to delay the project as needed.
Work sequencing will be determined (to some extent) by the Owner. One filter tank will be drained and work completed along with its associated piping. The second filter tank, its associated piping and the raw water and finished water completed. The hydropneumatic tank and its piping would be completed last. The Owner reserves the right to alter this schedule as needed. Intention is to perform the work in three phases but work in each phase may change.
1.02 SCOPE of WORK
Tank Information:
Filter Tanks:
The structures are both 17,039 gallon pressure filter water storage tanks located at 1295 Queens
Drive in Oxford, Michigan. Each tank has a diameter of 10 feet and length of 34 feet and are located inside of a building.
Hydropneumatic Tank:
The structure is a 8,600 gallon hydropneumatic water storage tank located at 1295 Queens Drive in Oxford, Michigan. The tank has a diameter of 8 feet and length of 23 feet and is located inside of a building.
OAKLAND COUNTY - PROJECT SUMMARY - 2
Filter Tanks:
Repair:
1) Weld repairs – contingency
2) Patch plates – contingency
3) Pit welding – contingency
Work completed by others:
• Exterior and Piping: Abrasive blast clean to a SSPC-SP6 commercial standard within containment to protect all controls. Apply a three (3) coat epoxy system.
• Wet Interior: Abrasive blast clean to a SSPC-SP10 near-white metal standard. Apply a three (3) coat zinc epoxy system.
• Filter Media Replacement: Remove the filter media and install new media after the topcoat is dry.
• Repairs: Install manway gaskets. Replace nuts and bolts
Hydropneumatic Tank:
Repairs:
1) Install second manway.
Work completed by others:
• Exterior and Piping: Abrasive blast clean to a SSPC-SP6 commercial standard within containment to protect all controls. Apply a three (3) coat epoxy system.
• Wet Interior: Abrasive blast clean to a SSPC-SP10 near-white metal standard. Apply a three (3) coat zinc epoxy system.
• Concrete Saddles: Clean and apply a two (2) coat epoxy system.
• Repairs by others: Install manway gaskets. Replace piping bolts and nuts. Remove pipe
(small pipe) fittings, re-tap as needed, and reinstall.
1.03 MISCELLANEOUS
A. Small pipe connections into the tanks will be removed by the owner prior to the start of the project.
B. The welder will require an R-Stamp certification to perform work on the structures.
OAKLAND COUNTY - SCHEDULE of VALUES - 3
SECTION 00 54 00
SCHEDULE OF VALUES
PART 1
1.01 LINE ITEMS
A. Bidder agrees to perform all work as described in the Contract Documents, including all labor and material for the following items – Section 05 00 00:
1. WELD REPAIR – CONTINGENCY - 20 LINEAL FT. – FILTER 1
2. WELD REPAIR – CONTINGENCY - 20 LINEAL FT. – FILTER 2
3. PATCH PLATES – CONTINGENCY - 20 LINEAL FT. – FILTER 1
4. PATCH PLATES – CONTINGENCY - 20 LINEAL FT. – FILTER 2
5. PIT WELDING – CONTINGENCY - 20 LINEAL FT. – FILTER 1
6. PIT WELDING – CONTINGENCY - 20 LINEAL FT. – FILTER 2
7. MANWAY – HYDROPNEUMATIC TANK
B. Coordination with other contractors will be required:
8. PIPING NUT AND BOLT REPLACEMENT – HYDROPNEUMATIC TANK – BY OTHERS
9. EXTERIOR REPAINT WITH CONTAINMENT – FILTER 1 – BY OTHERS
10. PIPING REPAINT – FILTER 1 – BY OTHERS
11. WET INTERIOR REPAINT – FILTER 1 – BY OTHERS
12. EXTERIOR REPAINT WITH CONTAINMENT – FILTER 2 – BY OTHERS
13. PIPING REPAINT – FILTER 2 – BY OTHERS
14. WET INTERIOR REPAINT – FILTER 2 – BY OTHERS
15. FILTER MEDIA REPLACEMENT – FILTER 1 – BY OTHERS
16. FILTER MEDIA REPLACEMENT – FILTER 2 – BY OTHERS
17. EXTERIOR REPAINT WITH CONTAINMENT – HYDROPNEUMATIC TANK – BY OTHERS
18. PIPING REPAINT – HYDROPNEUMATIC TANK – BY OTHERS
19. WET INTERIOR REPAINT – HYDROPNEUMATIC TANK – BY OTHERS
OAKLAND COUNTY - ADDITIONS to GENERAL CONDITIONS - 1
SECTION 00 91 17
ADDITIONS TO GENERAL CONDITIONS
PART 1 – GENERAL
GENERAL PURPOSE OF THESE ADDITIONS TO GENERAL CONDITIONS
A. These Additions to the General Conditions were prepared by Dixon Engineering, Inc.
using paragraphs from Engineering Joint Contract Documents Committee (EJCDC) General Conditions GC-700 -18 which were modified by DIXON as they pertain to the coating industry. The General Conditions of this Contract were prepared by the Owner. These Additions to General Conditions are intended to supplement the Owner’s General Conditions as they relate to this specific Project. For example:
1. The Owner’s General Conditions detail the payment process, how to submit a
Request for Payment application, what form to use and when and where to submit the application. These Additions to General Conditions detail how DIXON calculates approval of a pay request, no payment for stored materials, percentage complete calculation methodology, etc.
2. Liquidated Damages (if applicable) are defined in the General Conditions including when, where, and amount. In the Additions to General Conditions the method of calculating claimed wind and weather days is detailed.
B. This Additions to General Conditions follow the EJCDC format and the Article numbers reflect the Article number in the 2018 edition of the EJCDC General Conditions. Note that not all Articles or subsections are referenced.
DISCREPANCIES BETWEEN THE OWNER’S GENERAL CONDITIONS AND THESE
ADDITIONS TO GENERAL CONDITIONS.
A. If the conflict is administrative in nature, then the Owner’s General or Supplemental Conditions govern. Examples are Pay Request procedures, filing a Claim, etc.
B. If the conflict is of a technical nature, then the Additions to General Conditions govern.
C. An issue determined to be in conflict in a specific item does not void other non-conflicting paragraphs in the same Article number.
D. Bidders are required to familiarize themselves with all the General and Supplemental Conditions of the Contract, as well as these Additions to General Conditions.
E. In all cases of discrepancies between the General Conditions, the Supplemental Conditions, the Additions to General Conditions, the Technical Specifications and/or the Drawings, the Engineer is to be notified. The Specifications are to govern over the Drawings.
F. If Work proceeds without the Contractor obtaining proper interpretations of the conflicting issues from the Engineer, any installed Work that is not in accordance with the Specification, and best practices are to be replaced at no additional cost and
OAKLAND COUNTY - ADDITIONS to GENERAL CONDITIONS - 2 other costs that may occur are also the responsibility of the Contractor if they were aware of the conflict.
ARTICLE 1 DEFINITIONS AND TERMINOLOGY
1.01 DEFINED TERMS
A. Construction Industry Definitions: These definitions are taken from the EJCDC General Conditions C-700-18, the 2018 edition and some were modified by DIXON to be specific to the coating industry.
1. Bulletin—If time permits, a Bulletin is issued prior to a Change Order. A Bulletin is an inquiry of the Contractor of the cost to complete the Work described in the Bulletin. It is intended as the basis of a Change Order if all parties reach agreement.
A Bulletin may be considered as the same as a Change Proposal except that a Bulletin is generated by the Engineer because it generally requires Specifications to be addressed.
2. Change Order (CO) —is a written order to the Contractor signed by the Owner, issued after execution of the Contract, authorizing a change in the Work or an adjustment in the Contract sum or the Contract time. A document which is signed by the Contractor and the Owner and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Times, or other revision to the Contract, issued on or after the Effective Date of the Contract.
3. Change Proposal—A written request by Contractor, duly submitted in compliance with the procedural requirements set forth herein, seeking an adjustment in Contract Price or Contract Times, or both; contesting an initial decision by Engineer concerning the requirements of the Contract Documents or the acceptability of Work under the Contract Documents; challenging a Set-off against payments due;
or seeking other relief with respect to the terms of the Contract.
4. Constituent of Concern (CC)—Asbestos, petroleum, radioactive materials, polychlorinated biphenyls (PCBs), lead based paint (as defined by the HUD/EPA standard) hazardous waste, and any substance, product, waste, or other material.
Lead, chrome, and other by-products of paint removal, as well as strippers, new coatings, and thinners, are to be included in this definition. Coating industry related CC, from new or from previous projects cannot be the basis of Contract Termination or Change Proposal by the Contractor.
5. Drawings—The part of the Contract that graphically shows the scope, extent, and character of the Work to be performed by Contractor. A Shop Drawing is not a Drawing and is not part of the Contract Documents.
6. Electronic Document—Any Project-related correspondence, attachments to correspondence, data, documents, Drawings, information, or graphics, including but not limited to Shop Drawings and other Submittals, that are in an electronic or digital format.
7. Electronic Means—Electronic mail (email), upload/download from a secure Project website, or other communications methods that allow: (a) the transmission or communication of Electronic Documents; (b) the documentation of transmissions, including sending and receipt; (c) printing of the transmitted Electronic Document by the recipient; (d) the storage and archiving of the Electronic Document by sender and recipient; and (e) the use by recipient of the
OAKLAND COUNTY - ADDITIONS to GENERAL CONDITIONS - 3
Electronic Document for purposes permitted by this Contract. Electronic Means does not include the use of text messaging, or of Facebook, Twitter, Instagram, or similar social media services for transmission of Electronic Documents.
8. Field Order—A written order issued by the Engineer which requires minor changes in the Work but does not change the Contract Price or the Contract Times.
9. Hold Point—A point in the construction sequence when the Contractor is required to stop Work on that portion of the Project until Work has been Site reviewed by RPR or Project Manager.
10. Non-Conformance Report—A report written by the Engineer or Resident Project Representative, to document the Contractor’s Work that does not meet requirements of the Specifications or Contract.
11. Performance Specifications—Specifications that require the manufacturer or supplier of equipment, materials, or systems to design, manufacture, deliver, and install products to achieve specific results under stipulated conditions of operation and in environments described in applicable Specification Sections.
12. Ready for Final Payment – This term is used to define a time when Liquidated Damages begin, separate from Liquidated Damages for failure to meet Substantial Completion Date. Ready for Final Payment Date is generally listed 30 days after Substantial Completion Date. All punch list items are to be completed, Site cleaned and restored, and equipment removed. At the option of the Owner this Liquidated Damage may be in addition (cumulative) with a Liquidated Damage for failure to meet Substantial Completion Date.
13. Resident Project Representative—The authorized representative of Engineer assigned to assist Engineer at the Site. As used herein, the term Resident Project Representative or “RPR” includes any assistants or field staff of Resident Project Representative.
14. Schedule of Values—A schedule, prepared and maintained by Contractor, allocating portions of the Contract Price to various portions of the Work and used as the basis for reviewing Contractor’s Applications for Payment. The Schedule of Value Form is supplied in these Bidding Documents as Section 00 54 00. This Schedule is to be submitted with the Bid. Adjustment of Schedule of Values by Engineer will not change the total Bid as calculated by the Contractor completing the Schedule of Values.
15. Set-off—Owner may withhold from payment including Final Payment an amount equal to additional expenses incurred by Owner which were the responsibility of the Contractor. Such expenses may include additional engineering expenses related to excess review of incomplete submittals of Shop Drawings, pay requests, or bonds and insurance, excess Requests for Information, excess tests and inspections and return visits to the site to complete a reinspection of a previously failed inspection, increase inflation in engineering fees that result from Contractor delaying Project into the next season; additional expenses incurred by Owner resulting from Contractor failure to clean site, site rehabilitation, and other construction related expenses resulting from Contractor not completing their Contractual obligations.
16. Site—Lands or areas indicated in the Contract Documents as being furnished by Owner upon which the Work is to be performed, including rights-of-way and easements, and such other lands furnished by Owner which are designated for the use of Contractor.
OAKLAND COUNTY - ADDITIONS to GENERAL CONDITIONS - 4
17. Specifications—The part of the Contract that consists of written requirements for materials, equipment, systems, standards, and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable to the Work.
18. Submittal—A written or graphic document, prepared by or for Contractor, which the Contract Documents require Contractor to submit to Engineer, or that is indicated as a Submittal in the Schedule of Submittals accepted by Engineer.
Submittals may include Shop Drawings and Samples; schedules; product data;
Owner-delegated designs; sustainable design information; information on special procedures; testing plans; results of tests and evaluations, source quality-control testing and inspections, and field or Site quality-control testing and inspections;
warranties and certifications; Suppliers’ instructions and reports; records of delivery of spare parts and tools; operations and maintenance data; Project photographic documentation; record documents; and other such documents required by the Contract Documents. Submittals, whether or not approved or accepted by the Engineer, are not Contract Documents. Change Proposals, Change Orders, Claims, notices, Applications for Payment, and requests for interpretation or clarification are not Submittals.
19. Substantial Completion—The time at which the Work (or a specified part thereof) has progressed to the point where, in the opinion of Engineer, the Work (or a specified part thereof) is sufficiently complete, in accordance with the Contract Documents, so that the Work (or a specified part thereof) can be utilized for the purposes for which it is intended. The terms “substantially complete” and “substantially completed” as applied to all or part of the Work refer to Substantial Completion thereof. On tank projects, date of Substantial Completion is the date the tank is, or would have been returned to service, except for voluntary delay by Owner. Date of Substantial Completion is after complete cure, disinfection, and testing.
20. Work Change Directive—A written directive to the Contractor issued on or after the Effective Date of the Contract, signed by the Owner and recommended by the Engineer, ordering an addition, deletion, or revision in the Work.
B. Defective:
1. The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it:
a. Does not conform to the Contract Documents; or
b. Does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or
c. Has been damaged prior to Engineer’s recommendation of final payment
(unless responsibility for the protection thereof has been assumed by Owner at the Substantial Completion).
d. All Work completed that is rejected by an unresolved non-conformance report.
OAKLAND COUNTY - ADDITIONS to GENERAL CONDITIONS - 5
ARTICLE 2 PRELIMINARY MATTERS
2.03 BEFORE STARTING CONSTRUCTION
A. Preliminary Schedules: Within 10 days after the Effective Date of the Agreement (or as otherwise specifically required by the Contract Documents), Contractor is to submit to Engineer for timely review:
1. A preliminary Progress Schedule indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract.
2.04 PRECONSTRUCTION CONFERENCE
A. Preconstruction Conference is herein called Preconstruction Meeting:
1. The Engineer will schedule a Preconstruction Meeting to be attended by the
Owner, Engineer, and Contractor. Prior to beginning any Work, Contractor is to submit to the Engineer, a Project Schedule and all other required Submittals for the Project. If the schedule is aggressive, working overtime, weekends, and/or holidays, that time is to be reflected in the Project Schedule. Once the Project has begun, the Contractor is to carry the Project Schedule to completion without delay.
2. Attend a Preconstruction Meeting that may be scheduled by the Owner at a mutually agreeable time after Contract preconditions, bonds, certificates of insurance, and other requirements have been met.
3. A Corporate Officer, or someone with legal authority to obligate the company/corporation, Project Manager (if different from officer), and the intended superintendent are to attend. If the Project Superintendent does not attend the meeting, it is to be the Contractor’s responsibility to supply the information discussed at the meeting to the Field Superintendent.
4. The Owner will be represented by the Project contact person, and the Engineer by the Project Manager, or a Contract Administrator.
5. All containment, personal hygiene, and lead control issues required in this Contract will be reviewed. Be prepared to commit designated “Competent Person(s)” to responsibilities of confined space, scaffold rigging, lead, etc.
B. Progress Meetings:
1. The Project Manager or Owner will schedule Progress Meetings to be held on the job Site whenever needed to supply information necessary to prevent job interruptions, to observe the Work, or to inspect completed Work. The Contractor is to be represented at each Progress Meeting by persons with full authority to act for the Contractor regarding all portions of the Work.
OAKLAND COUNTY - ADDITIONS to GENERAL CONDITIONS - 6
ARTICLE 3 CONTRACT DOCUMENTS INTENT REQUIREMENTS, REUSE
3.01 INTENT
A. The Drawings and Specifications are intended to include all Work and materials necessary for completion of the Work. Any incidental item of material, labor, or detail required for the proper execution and completion of the Work and omitted from either the Drawings or Specifications or both, but obviously required by governing codes, local regulations, trade practices, operational functions, and good workmanship, is to be provided as a part of the Contract Work without extra cost, even though not specifically detailed or mentioned.
ARTICLE 4 COMMENCEMENT AND PROGRESS OF THE WORK
4.01 COMMENCEMENT OF CONTRACT TIMES
A. Contractor is to start to perform the Work on the date when the Contract Times commence to run. No Work is to be done at the Site prior to such date except as recommended immediately following or by written authorization of the Owner AND the Engineer (Engineer must be able to schedule appropriate RPR for Project.)
Contract time is governed by out-of-service time. The Contractor is encouraged to deliver equipment to the Site prior to Contract start. The Site will be available up to two (2) weeks prior to the agreed drainage date. Contractor is also encouraged to rig the structure, complete containment installation, and complete weld repairs that do not affect the wet interior prior to draining of the tank. The amount of Work completed is to have been approved at the Preconstruction Meeting. Since the tank is not out of service these dates do not apply against Out of Service time but may require scheduling RPR services (see Section 00 91 19.01 Scheduling for RPR Services).
B. Delaying Work start for the convenience of the Contractor may require Owner to Set-off inflation increased Engineering or RPR expenses against Contractor’s Request for Payment.
4.05 DELAYS IN CONTRACTOR’S PROGRESS
A. Liquidated Damages
1. Contract time is governed by out-of-service time.
2. On tank projects, the date of Substantial Completion is the date the tank is or would have been returned to service, except for voluntary delay by Owner. Date of Substantial Completion is after complete cure, disinfection, and testing. A voluntary delay in filling by Owner, or delay that is no fault of the Contractor, may extend Substantial Completion date.
3. Abnormal weather conditions are defined as weather conditions that are at variance with the routine. Below is an example of the determination procedure and of the required claim format, and is not intended to match the specified project:
Project length: 45 days
OAKLAND COUNTY - ADDITIONS to GENERAL CONDITIONS - 7
Substantial Completion date: June 30th.
Start date: May 16th.
3 years of data* 2021, 2022, 2023 Average number of rain/wind days: 9 Actual number of rain/wind days**: 12 Claim for time extension: 3 days.
4. *Submit weather history from nearest weather reporting station for three (3) previous years from the same time period. Submit formal, by simple claim (use format above).
5. **Rain/wind day is a rain or wind day where either rain and/or wind conditions exceeded safe Work conditions or were outside the parameters of good paint practices. Wind days are winds in excess of 20 mph for over four (4) hours during normal Work hours, and rain days having measurable precipitation.
6. Weather Claim Evaluation: Engineer will evaluate claim and make sole determination as to whether days meet criteria. Engineer will disallow dates where Work could have been completed on the interior; dates that result from the Contractor’s Work practices (i.e., complete wet interior first and then move to the exterior). Good weather days not used will count against the claim.
7. Claimed rain/wind days that occur after the scheduled Substantial Completion Date, or an extended Substantial Completion Date will not be awarded.