Ad for Bid _ Independence Parkway Scoping RFP.pdf

PDF 790 KB Posted

Attached to
PROFESSIONAL CONSULTING SERVICES LIBERTY INDEPENDENCE PARKWAY PHASE 2 SCOPING RFP
Solicitation number
PE-68990-NONST-2027-000000049
Issued by
Lanier County, Georgia

About this file

Summary

This Request for Proposals (RFP) is issued by the Liberty County Board of Commissioners for professional consulting services to provide scoping services for the Liberty Independence Parkway Phase 2 project (PI# 0021719), also known as the Hinesville By-Pass/U.S. Highway 84 Connector. The County seeks a Georgia Department of Transportation (GDOT) prequalified engineering consultant to evaluate a new highway south of Hinesville and prepare a scoping study through the GDOT review and approval process. The proposed highway would connect the new Highway 84 Connector near the intersection of State Route 119 and Tibet Road in Walthourville to State Route 196 west of U.S. Highway 84. RFP responses are due by 4:00 PM on December 3, 2026, and must be submitted to Joseph Mosley, County Administrator, at 112 North Main Street, Hinesville, Georgia 31313. Proposals shall remain firm for 60 days following the submission deadline. The scope of work includes project justification, traffic analysis, alternatives evaluation, environmental screening, public and stakeholder involvement, cost estimates, implementation planning, and GDOT review and approval coordination. The contract will include specific GDOT and Federal Highway Administration requirements, and formal concept development and concept approval are excluded from this phase.

Evaluation of proposals will be based on technical merit and price, with scoring weights of 25% for Company/Personnel Experience, 25% for Past Performance, 40% for Project Understanding/Approach, and 10% for Costs. The selected consultant must demonstrate experience providing scoping services through the GDOT process and maintain required GDOT prequalifications in Transportation Planning, Environmental Screening, and Highway Design and Roadway disciplines. The study is partially funded by GDOT, with contingency on receipt of ongoing funds. Disadvantaged Business Enterprise (DBE) participation is mandatory at approximately 10% of the total contract amount. The consultant must provide proof of insurance including workers' compensation, commercial general liability of at least $1,000,000, automobile liability of at least $1,000,000, and professional liability of at least $1,000,000. Proposals must include a sealed cost proposal on the provided Exhibit J fee schedule. The Liberty County Board of Commissioners reserves the right to reject any and all proposals, waive irregularities, and modify or terminate the contract if funding is eliminated or decreased.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

File: 2026-167 RFQ Scoping 0021719.docx Page 1 of 45

REQUEST FOR PROPOSALS

PROFESSIONAL CONSULTING

SERVICES

LIBERTY INDEPENDENCE PARKWAY

PHASE 2 SCOPING

(A.K.A. HINESVILLE BY-PASS/

U.S. HIGHWAY 84 CONNECTOR)

PI# 0021719

Dated: October 26, 2026

RFP’s due by 4:00 PM on December 3, 2026

File: 2026-167 RFQ Scoping 0021719.docx Page 2 of 45

LIBERTY COUNTY BOARD OF COMMISSIONERS

PROFESSIONAL CONSULTING SERVICES

LIBERTY INDEPENDENCE PARKWAY PHASE 2 SCOPING

The Liberty County Board of Commissioners is interested in contracting with a qualified consultant to provide scoping services for Liberty Independence Parkway Phase 2 pursuant to the Scope of Work in Exhibit I herein.

The preferred qualifications of the consultant include previous experience providing scoping services and preparing scoping reports through the Georgia Department of Transportation process.

The Request for Proposal is available on the Liberty County Board of Commissioners website:

https://www.libertycountyga.gov/bids.aspx or the Liberty County Board of Commissioners office, 112 N. Main Street, Hinesville, GA 31313, or email joseph.mosley@libertycountyga.gov or call Joseph Mosley, County Administrator, (912) 876-2164.

Request for Proposal response is due December 3, 2026, by 4:00 PM at the Liberty County Board of Commissioner’s Offices at 112 North Main Street, Hinesville, Georgia 31313.

Date of publication: October 26, 2026 https://www.libertycountyga.gov/bids.aspx mailto:joseph.mosley@libertycountyga.gov

File: 2026-167 RFQ Scoping 0021719.docx Page 3 of 45

This publication was prepared in cooperation with the Department of Transportation, and State of Georgia. The opinions, findings, and conclusions in these publications are those of the author(s) and not necessarily those of the Department of Transportation or State of Georgia.

Liberty County Board of Commissioners

112 Main Street Hinesville, Georgia 31313 Phone: 1-912-876-2164 joseph.mosley@libertycountyga.gov

Visit our website for the most up-to-date information and downloadable documents at www.libertycountyga.gov

The Liberty County Board of Commissioners is committed to assuring full compliance with all civil rights provisions of federal statutes and related authorities that prohibit discrimination in programs and activities receiving federal financial assistance.

These laws include but are not limited to Title VI of the Civil Rights Act of 1964 ("Title VI"), the Civil Rights Restoration Act of 1987 (P.L. 100.259), Section 162 (a) of the Federal-Aid Highway Act of 1973 (23 USC 324) (sex), Americans with Disabilities Act of 1990, Section 504 of the Rehabilitation Act of 1973, and the Age Discrimination Act of 1975, as amended.

The Liberty County Board of Commissioners does not discriminate against persons in the provision of its programs, services or activities.

The Liberty County Board of Commissioners is a direct recipient of federal grants from the US

Department of Transportation and therefore the following statement shall be included in all solicitations:

"The Georgia Department of Transportation in accordance with Title VI of the Civil Rights Act of 1964 and 78 Stat. 252, 42 USC 2000d- 42 and Title 49, Code of Federal Regulations, Department of Transportation, Subtitle A, Office of the Secretary, part 21, Nondiscrimination in federally assisted programs of the Department of Transportation issued pursuant to such Act, hereby notifies all bidders that it will affirmatively ensure that any contract entered into pursuant to this advertisement, minority business enterprises will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, sex, or national origin in consideration for an award."

http://www.libertycountyga.gov/

File: 2026-167 RFQ Scoping 0021719.docx Page 4 of 45

Table of Contents In General

Objective

Executive Summary

Experience and Ability and Additional Proposal Requirements ............ Error! Bookmark not defined.

Past Performance

Understanding of the Project Requirements

Cost Proposal

Additional Requirements

The following additional requirements shall be included:

Submission

Evaluation and Selection

Evaluation Criteria

Selection Committee

Requirements and Selection Process

Proof of Insurance

Disqualification

Protests

Contract Requirements

Amendments to the Contract

Liberty County Board of Commissioners’ Reservation of Rights and Disclaimers

EXHIBIT A: ACKNOWLEDGEMENT OF RECEIPT OF RFP*

EXHIBIT B: GENERAL INFORMATION FORM

EXHIBIT D: CERTIFICATION OF ELIGIBILITY TO PROPOSE

EXHIBIT E: CERTIFICATION OF NON-COLLUSION

EXHIBIT F: FEDERALLY REQUIRED CONTRACT CLAUSES

EXHIBIT G: LIBERTY COUNTY BOARD OF COMMISSIONERS REQUIRED CONTRACT

CLAUSES

EXHIBIT H: PROTEST POLICY AND PROCEDURES

EXHIBIT I: SCOPE OF WORK FOR LIBERTY INDEPENDENCE PARKWAY PHASE 2 SCOPING

Project purpose and limits

Required outcome and governing requirements

Project management and initiation

File: 2026-167 RFQ Scoping 0021719.docx Page 5 of 45

Traffic analysis and alternatives - Traffic and safety studies

Development and screening of alternatives

Public and stakeholder involvement

Cost estimates and implementation plan

GDOT review and approval

Required deliverables and acceptance

Schedule and responsibilities

Quality control and boundaries of services

EXHIBIT J: FEE SCHEDULE

EXHIBIT K: PROJECT LOCATION GRAPHIC

File: 2026-167 RFQ Scoping 0021719.docx Page 6 of 45

INTRODUCTION

RFP proposal is due December 3, 2026, by 4:00 PM

For the purposes of this contract and project, the Liberty County Board of Commissioners must comply with funding rules and regulations of the Federal Highway Administration (FHWA), Federal Transit Administration (FTA) and the Georgia Department of Transportation (GDOT) as well as other federal, state and local funding sources. The Liberty County Board of Commissioners is an Equal Opportunity Employer. Disadvantaged Business Enterprises are encouraged to submit proposals and no proposer will be subject to discrimination based on race, color, religion, ancestry, national origin, age, gender, handicap, sexual orientation, veteran’s status, or other protected class, as identified by law, in consideration of an award of contract.

The proposed work is for the services of a professional consulting firm to provide scoping services for Liberty Independence Parkway Phase 2.

If you desire to propose, please complete, and return the “Acknowledgement of Receipt of RFP” as shown in the exhibits. Please see the section on submissions for contact information as this is critical for sharing questions and addenda.

The Liberty County Board of Commissioners reserves the right to waive any minor informality, or to issue addenda to this Request for Proposal. Any addenda issued will be mailed or emailed to all consultants of record that have completed and returned the RFP Acknowledgement of Receipt Form.

Questions Questions concerning this Request for Proposal must be submitted in writing, may be hand delivered, mailed, or emailed to Joseph Mosley at joseph.mosley@libertycountyga.gov.

All responses to questions will be mailed or emailed to all consultants on record that have completed and returned the RFP Acknowledgement of Receipt Form.

Questions concerning the Request for Proposal will be accepted through November 20, 2026 at 4:00 PM, and written responses will be provided no later than November 23, 2026. Q&A will be posted to the Liberty County Board of Commissioners web page and email notice of same sent to registered proposers.

In General The Liberty County Board of Commissioners is interested in contracting with a qualified consultant to perform scoping services. The preferred qualifications of the consultant are previous experience and performance providing scoping services and preparing scoping reports through the Georgia Department of Transportation process.

Regional Context and Existing Conditions Liberty County has desired the development of a bypass around the metropolitan area of Hinesville for more than 25 years. In the early 2000’s the Liberty County Board of Commissioners Morland Altobelli, Inc (Now Atlas Technical Consultants) to develop plans for a by-pass around Hinesville beginning near the western county line at U.S. Highway 84 and ending near the intersection of State Route 196 and U.S. Highway 84 east of Hinesville. The desire was to also intersect State Route 119 east of Walthourville. The bypass would bring welcome relief to the congestion experienced along U. S. Highway 84 through Hinesville.

File: 2026-167 RFQ Scoping 0021719.docx Page 7 of 45

The first section of this bypass is now under construction and is scheduled to open in 2027. The first segment of the bypass begins at U. S. Highway 84 west of Walthourville at the county line and will connect to State Route 119 east of Walthourville. This project is funded by the Georgia Department of Transportation. The Georgia Department of Transportation project number is PI#522570, US 84 Connector NH000-0026-03(056).

Objective The Liberty County Board of Commissioners is interested in contracting with a qualified consultant to provide scoping services and scoping reports pursuant to the Scope of Work in Exhibit I herein.

Scope of Work Liberty County seeks a Georgia Department of Transportation (GDOT) prequalified engineering consultant to evaluate a new highway south of the City of Hinesville and prepare a Scoping Study through the applicable GDOT review and approval process. The study is partially funded by GDOT. The Consultant shall provide the technical studies, coordination, documentation, and revisions needed for the County to make an informed decision and for GDOT to approve the study. Formal concept development and concept approval are not included in this phase. Detailed information regarding the scope is shown in Exhibit I: Scope of Work for Liberty Independence Parkway Phase 2 Scoping.

Content of Proposals The consultant must provide a proposal that meets or exceeds all requirements listed in this Request for Proposal. The following specific elements should be included.

Executive Summary Present a brief summary describing the proposal and your company and its capabilities. Give the names of the person(s), address(es), telephone and e-mail address. The summary must be limited to a maximum of two pages, and the signer of the proposal must declare that the proposal is in all respects fair and in food faith without collusion or fraud and that the signer of the proposal has the authority to bind the principal proponent.

Company/Personnel Experience This Request for Proposal is for providing scoping services for Liberty Independence Parkway Phase 2. The Liberty County Board of Commissioners has the right to increase or decrease the Contractor’s assignment and/or areas of operation within the scope of this contract.

The proposal should provide a detailed outline of how work will be accomplished. At a minimum the proposal should include the following information:

• Organizational Chart

• Information describing company’s technical and analytical capabilities

• Training and experience (list all certifications)

• Resumes of personnel who will work on project

• Other unique services your company can provide

Include any pertinent information needed to determine the proposer’s experience and ability to perform the anticipated work.

File: 2026-167 RFQ Scoping 0021719.docx Page 8 of 45

Past Performance The proposers shall include a list of consulting services similar to the Statement of Work specified in the Request for Proposal currently in place or completed within the past five years. Include any pertinent information needed to determine the proposer’s past performance.

The proposal will address how the proposers have previously managed tracking the information required in the scope of work. For each of the above items the proposers shall include details of the project such as the public agency, their contact, all pertinent phone numbers and dollar amounts. The proposers shall provide information necessary to investigate the work with the public or private agency.

The proposers shall provide at least three (3) references for contracts of a similar size and scope, (if available) including at least two references for current contracts or those awarded during the past five years. Include the name of the organization, the length of the contract, a brief summary of the work, and the name and telephone number of a responsible contact person. Also provide a description of any conflicts occurring over the last five (5) years with these or any other contract for similar work.

Understanding of the Project Requirements The proposers shall provide their interpretation of what is required to meet the needs of The Liberty County Board of Commissioners. The proposer will use this document, their knowledge and experience to develop their understanding of this project. The proposers are urged to develop scenarios or examples to fully explain their position.

Please see Exhibit I: Scope of Work for Liberty Independence Parkway Phase 2 Scoping for the Georgia Department of Transportation Pre-Qualification requirements for this project.

Cost Proposal The proposal shall include a cost proposal (See Exhibit J herein) in a separately sealed envelope.

The cost proposal will be evaluated and scored in accordance with scoring criteria. By submitting a response, the proposer agrees that it has read, understood, and will submit a proposal by the follow instructions/rules:

1. Cost proposals containing a minimum order/ship quantity or dollar value, unless otherwise noted in the Request for Proposal, will be treated as non-responsive and may not be considered for award; and

2. In the event there is discrepancy between the proposer’s unit price and extended price, the unit price shall govern; and

3. In the event there is a discrepancy between (1) the proposer’s pricing as quoted on the Request for Proposal’s provided cost worksheet and (2) the proposer’s pricing as quoted by the proposer in one or more additional documents, the former shall govern; and

4. The prices quoted and listed in the cost proposal shall be firm throughout the term of the resulting contract, unless otherwise noted in the Request for Proposal or contract.

Invoicing and Status Reports shall be submitted quarterly and within 30 days after end of the respective quarter.

File: 2026-167 RFQ Scoping 0021719.docx Page 9 of 45

Additional Requirements The following additional requirements shall be included:

1. Each Proposal shall be typed and should be concise but comprehensive.

2. Required certifications must be completed, signed, and submitted with each proposal.

(Exhibits B, C, D, & E.)

3. Proposals shall start with a transmittal letter signed by the principal followed by a Table of

Contents.

4. Proposals submitted in response to this Request for Proposal must remain firm for a period of sixty (60) days following the deadline for submission for this Request for Proposal.

5. The bidder will describe how they plan to incorporate the DBE and/or small business participation.

6. Proposals may also include any miscellaneous information.

Submission One (1) original, six (6) hard copies, and one (1) digital copy on a USB drive. Request for Proposals shall be submitted in a sealed envelope marked “Request of Proposals, Professional Consulting Services, Liberty Independence Parkway Phase 2 Scoping” no later than 4:00 PM on December 3, 2026, to:

Joseph Mosley, County Administrator Liberty County Board of Commissioners 112 N. Main Street, Suite 2200 Hinesville, GA 31313 912-876-2164 joseph.mosley@libertycountyga.gov

Evaluation and Selection It is the Liberty County Board of Commissioners’ intent to evaluate the proposals based on technical merit and price. It is the intent of the Liberty County Board of Commissioners to choose the proposer whose proposal provides the highest value to the Liberty County Board of Commissioners. The Liberty County Board reserves the right to waive any irregularities, reject any and/or all proposals, in whole or in part, when, in the Liberty County Board of Commissioners’ opinion, such rejection is in the best interests of the Liberty County Board of Commissioners.

Evaluation Criteria Each proposal will be reviewed by a selection committee of qualified individuals. Their proposal review and evaluation will be subjective; however, the weighing values are established to minimize that subjectivity. The following delineates the value attributed to each section.

Section Weight Company/Personnel Experience 25% Past Performance 25% Project Understanding/Approach 40%

Costs 10% Total 100%

Note: While the evaluation team will review the proposal in its entirety and may consider anything, they find relevant, particular emphasis is placed on the following:

File: 2026-167 RFQ Scoping 0021719.docx Page 10 of 45

Current Project Knowledge – knowledge of current location/site analysis technology, practices and procedures.

Company Experience – detailed information relative to the proposer’s general qualifications as well as specific to this project; past performance record on similar work, corporate history and team organization.

Project Understanding – provision of adequate, specific, information regarding the proposer’s technical approach to this project. Such information shall include, but not be limited to:

Selection Committee The Selection Committee will consist of a five-person panel, including the LCPC/HAMPO Executive Director, the Liberty County Administrator, the Liberty County Engineer, the Hinesville City Engineer, and the Hinesville City Manager. The LCPC/HAMPO Executive Director will moderate the selection process.

Requirements and Selection Process

1. Proposals will be ranked using the published evaluation criteria, including technical qualifications and fee.

2. The County will negotiate scope, contract terms, and compensation with the highest-ranked offeror. If an acceptable agreement cannot be reached, the County will formally terminate those negotiations before proceeding to the next highest-ranked offeror.

3. Confidentiality will be maintained during the selection process.

4. The offeror with whom negotiations are conducted will be given reasonable opportunity to support and clarify its proposal.

5. Unsuccessful offerors will be notified at the earliest practicable time that their proposals are no longer considered.

6. Award will be made to the offeror whose proposal will be the most advantageous to the

Liberty County Board of Commissioners. The Liberty County Board of Commissioners reserves the right not to make an award.

7. Any respondent who communicates with any Liberty County Board of Commissioners elected members, the press or engages in the services of any individual or firm for the purposes of influencing the outcome of the proposal process will be disqualified from further consideration.

Proof of Insurance

1. The primary firm must include evidence in the proposal that he or she maintains the following minimum insurance:

• Workers' compensation and employer's liability in amounts required by law;

• Commercial general liability with limits of liability not less than $1,000,000;

• Automobile liability insurance with limits of liability not less than $1,000,000; and,

• Professional Liability with limits of liability not less than $1,000,000.

Disqualification The Liberty County Board of Commissioners will disqualify any proposal it determines to be unresponsive, including, but not limited to the following:

1. Proposals that fail to meet the minimum requirements listed within this RFP.

2. Proposals that are received after the submission deadline.

3. Proposals in which consultants misrepresent goods or services or provide demonstrably

File: 2026-167 RFQ Scoping 0021719.docx Page 11 of 45 false information.

4. Proposals that identify individuals which are currently subject to State or Federal debarment order or determination.

Protests The Liberty County Board of Commissioners’ policy and procedure for the administrative resolution of protests is set forth in the appendix as “Exhibit H: Protest Policy and Procedures”.

Contract Requirements The selected Firm agrees to comply with all applicable state, and local laws, rules and regulations, all as amended, in the performance of its contract with the Liberty County Board of Commissioners. The selected Consultant acknowledges and agrees that the contract by and between the Liberty County Board of Commissioners and the selected Consultant shall include certain contract provisions required by the Liberty County Board of Commissioners, Georgia Department of Transportation and Federal Highway Administration, Federal Transit Administration, Code of Federal Regulations, all as amended. Such contract shall be construed under, governed by, and enforced in accordance with law without regard to conflict of law or choice of law principles.

Form of Contract Preparation of contract shall be the responsibility of the selected Firm. The Liberty County Board of Commissioners, GDOT, FHWA and FTA require that specific clauses accompany federally funded projects executed by the MPO. There are no funds from the FHWA or the FTA at this time, Consultants should be prepared to abide by the necessary clauses and include each verbatim and unaltered in a potential contract.

Amendments to the Contract The Liberty County Board of Commissioners reserves the right to negotiate mutually acceptable amendments to the Contract arising from the Request for Proposal and with respect to the addition of services that are consistent with the services solicited by the Request for Proposal. The right to negotiate mutually acceptable amendments applies for the term of this Contract and any extensions.

Terms and Conditions

1. The Liberty County Board of Commissioners reserves the right to reject any and all proposals for failure to meet the requirements contained herein, to waive any technicalities, and to select the proposal which, in the Liberty County Board of Commissioners’ sole judgment, best meets the requirements of the project.

2. T h e Liberty County Board of Commissioners creates no obligation on the part of the Liberty County Board of Commissioners to award a contract or to compensate the proposer for any costs incurred during the proposal presentation, response, submission, or oral interviews (if held). The Liberty County Board of Commissioners reserves the right to award a contract based upon proposals received without further discussion or negotiation.

Proposers should not rely upon the opportunity to alter their Proposal during discussions.

3. Inspection – Proposer’s shall permit, if requested, authorized representatives of the Liberty

County Board of Commissioners to inspect a Proposer’s data, facilities, equipment and records relating to this Request for Proposal. Unsubstantiated statements or the refusal to permit audit or inspection may cause the Proposer to be deemed non-responsive.

File: 2026-167 RFQ Scoping 0021719.docx Page 12 of 45

4. Proprietary Information – All Proposals shall become the property of the Liberty County

Board of Commissioners. If any proprietary information is contained in or attached to a proposal, it must be clearly identified as such.

5. Limitation on Funding – The Contract for services resulting from this Request for Proposal will be subject to the contract between the Liberty County Board of Commissioners and the availability of on-going funds from the Liberty County Board of Commissioners’ funding sources. The Contract for this service is contingent upon receipt of these funds by the Liberty County Board of Commissioners. If funding from these sources is eliminated or decreased, the Liberty County Board of Commissioners reserves the right to terminate the Contract or modify it accordingly.

6. Protest and Appeal Procedures – The procurement procedures and appeal processes are contained in Exhibits attached hereto and made a part thereof.

7. Insurance: The firm selected to perform the work described in this Request for Proposal will be required to provide and maintain evidence of public liability, worker’s compensation and property damage insurance with limits of not less than $1,000,000.

Liberty County Board of Commissioners’ Reservation of Rights and Disclaimers

1. The Liberty County Board of Commissioners is requesting responses to this Request for

Proposal pursuant to its determination that such a process best serves the interests of the Liberty County Board of Commissioners and the public, and not because of any legal requirement to do so.

2. The Liberty County Board of Commissioners shall not be responsible in any manner for any costs associated with responses to this Request for Proposal.

3. The Liberty County Board of Commissioners reserves the unqualified right, in its sole and absolute discretion, to undertake discussions with one or more respondents or any third party, to waive any irregularities, to waive defects or noncompliance in the filing or contents of any Proposal, and to proceed with that Proposal, or elements of one or more Proposals, if any, which in its sole judgment will, under the circumstances, best serve the Liberty County Board of Commissioners’ interest.

4. The Liberty County Board of Commissioners reserves the unqualified right to amend the terms of this Request for Proposal at any time, and to solicit and accept modifications to any Proposal at any time when it is in the best interest of the Liberty County Board of Commissioners to do so.

5. The Liberty County Board of Commissioners reserves the unqualified right, in its sole and absolute discretion, to choose or reject any Proposal received in response to this Request for Proposal, either based on an evaluation of the factors listed in this Request for Proposal or for other reasons, whether any Proposal offers the highest monetary compensation to the Liberty County Board of Commissioners or any other public entity.

6. The Liberty County Board of Commissioners reserves the unqualified right, in its sole and absolute discretion, to reject any and all Proposals or to suspend or abandon this Request for Proposal process at any time, with no recourse for any Respondent.

File: 2026-167 RFQ Scoping 0021719.docx Page 13 of 45

7. The information contained in this Request for Proposal and in any subsequent addenda or related documents is provided as general information only. The Liberty County Board of Commissioners makes no representations, warranties, or guarantees that the information contained herein is accurate or complete. The furnishing of such information by the Liberty County Board of Commissioners shall not create or be deemed to create any obligation or liability upon it for any reasons whatsoever, and each recipient of the Request for Proposal, by submitting a Proposal to the Liberty County Board of Commissioners, expressly agrees that it has not relied upon the foregoing information, and that it shall not hold the Liberty County Board of Commissioners, or any third party who advised or prepared a report for the Liberty County Board of Commissioners, liable or responsible therefore in any manner whatsoever.

8. The Liberty County Board of Commissioners may, at any time, request further information from any Respondent, interview any respondents to more fully understand their responses to this Request for Proposal, and require any respondent to arrange a site visit for its Selection Advisory Committee.

9. The Liberty County Board of Commissioners reserves the right, in its sole discretion, to develop the project on any schedule and use any chosen approach.

10. Neither the expression of any respondent’s interest, nor the submission of any respondent’s qualifications and any documents or other information, nor the acceptance thereof by the Liberty County Board of Commissioners, nor any correspondence, discussions, meetings or other communications between a respondent and the Liberty County Board of Commissioners, nor a determination by the Liberty County Board of Commissioners that the respondent is qualified hereunder, shall:

(i) Impose any obligation on the Liberty County Board of Commissioners to include the respondent in any such further procedures which the Liberty County Board of Commissioners may utilize prior to the final selection of a respondent,

(ii) Be deemed to impose any obligation whatsoever on the Liberty County Board of Commissioners to select the respondent, or to enter negotiations with the respondent, or

(iii) Entitle the respondents to any compensation or reimbursement for any costs or expenses incurred by the respondent in connection with the respondent’s submission hereunder. No costs of responding to the Request for Proposal or any addenda thereto, nor of the attending any subsequent interviews or meetings in connection with this development opportunity, shall be reimbursed by the Liberty County Board of Commissioners.

11. The Liberty County Board of Commissioners may consult individuals familiar with each respondent regarding the respondent’s prior operations and development or management projects, financial plan, past performance, experience and qualifications, or other matters, whether or not the specific individuals are identified in the Request for Proposal response.

Submission of a proposal in response to this Request for Proposal shall constitute permission for the Liberty County Board of Commissioners to make such inquiries, and authorization to third parties to respond thereto.

12. The individual responses to this Request for Proposal, including all drawings, plans, photos and narrative material shall become the property of the Liberty County Board of

File: 2026-167 RFQ Scoping 0021719.docx Page 14 of 45

Commissioners upon their receipt thereof. The Liberty County Board of Commissioners will maintain the confidentiality of any material that is provided in response to this Request for Proposal and clearly marked “Confidential”, to the maximum extent possible, in a manner consistent with applicable law. Given the nature of the public records law, respondents should nevertheless be aware that any information given to the Liberty County Board of Commissioners in response to this Request for Proposal or any correspondence, discussion, meeting, or other communication between the respondent and the Liberty County Board of Commissioners before, with, or after the submission of the response, either orally or in writing, may not be, or may not be deemed to have been, proprietary or confidential.

13. Neither the members of the Liberty County Board of Commissioners nor any individual member, nor any officer, agent, or employee thereof shall be charged personally by a respondent or any third party with any liability or held liable to it under any term or provision of this Request for Proposal nor any statement made herein.

14. The Liberty County Board of Commissioners reserves the unqualified right, in its sole and absolute discretion, to disqualify any team, firm, or individual from any phase or component of the selection processor this development opportunity, due to:

(i) Felonious or other criminal record in any jurisdiction (domestic or foreign);

(ii) A determination by the Liberty County Board of Commissioners that the respondent has failed to disclose:

(a) Any matter that materially relates to the fitness or ability of the respondent to perform the work and services associated with this development opportunity, or

(b) A conflict of interest; or

(c) A determination that such disqualification would serve the public interest.

15. The Liberty County Board of Commissioners reserves the unqualified right to:

(i) Disqualify any prospective respondent or reject any response at any time solely on the grounds that a real or perceived legal or policy conflict of interest is presented;

(ii) Require any prospective respondent to take any action or supply any information necessary to remove the conflict, including without limitation, obtaining an opinion from the State Ethics Commission; or

(iii) Terminate any contract arising out of this Request for Proposal if, in the opinion of the Liberty County Board of Commissioners, any such relationship would constitute or have the potential to create a real or perceived conflict of interest.

File: 2026-167 RFQ Scoping 0021719.docx Page 15 of 45

APPENDIX

EXHIBIT A: ACKNOWLEDGEMENT OF RECEIPT OF RFP* .......................... Error! Bookmark not defined.

EXHIBIT B: GENERAL INFORMATION FORM ............................................... Error! Bookmark not defined.

EXHIBIT C: DBE UTILIZATION FORM ............................................................ Error! Bookmark not defined.

EXHIBIT D: CERTIFICATION OF ELIGIBILITY TO PROPOSE ...................... Error! Bookmark not defined.

EXHIBIT E: CERTIFICATION OF NON-COLLUSION ...................................... Error! Bookmark not defined.

EXHIBIT F: FEDERALLY REQUIRED CONTRACT CLAUSES ....................... Error! Bookmark not defined.

EXHIBIT G: HAMPO REQUIRED CONTRACT CLAUSES .............................. Error! Bookmark not defined.

EXHIBIT H: PROTEST POLICY AND PROCEDURES .................................... Error! Bookmark not defined.

EXHIBIT I: SCOPE OF WORK FOR LIBERTY INDEPENDENCE PARKWAY PHASE 2 SCOPING

EXHIBIT J: FEE SCHEDULE

EXHIBIT K: PROJECT LOCATION GRAPHIC

File: 2026-167 RFQ Scoping 0021719.docx Page 16 of 45

EXHIBIT A: ACKNOWLEDGEMENT OF RECEIPT OF RFP*

CONSULTING SERVICES FOR LIBERTY INDEPENDENCE PARKWAY PHASE 2

SCOPING PI# 0021719

Name of Firm:

Contact Person:

Address:

Telephone Number:

Fax Number:

Email:

Please return to Joseph Mosley at joseph.mosley@libertycountyga.gov.

*Addenda and Q&A will only be forwarded to those firms that complete and submit the RECEIPT OF RFP form. In addition, the County reserves the right not to accept proposals from firms that have not submitted the receipt of the Request for Proposals.

File: 2026-167 RFQ Scoping 0021719.docx Page 17 of 45

EXHIBIT B: GENERAL INFORMATION FORM

(Must be completed and submitted with Proposal)

Name of Organization:

Address:

Telephone Number:

Years in Business:

Organization is (check one):

Corporation; __ Partnership; Association; Joint Venture; Sole Proprietorship;

Public Agency; _ Quasi-Public Agency

Other: (Explain):

Name, Title, Telephone Number and email of the Organization’s Authorized Representative:

Acknowledgment of received Addenda No(s):

The undersigned, being cognizant of the pages, documents and Exhibits concerned herewith agrees to provide the Liberty County Board of Commissioners, with the services described in the Request for Proposals for Professional Consulting Services Liberty Independence Parkway Phase 2 Scoping.

The stated Proposal shall be firm for 60 days from December 3, 2026, deadline for this Proposal.

I hereby affirm that this Proposal is genuine, not a sham or collusive, and is not made in the interest of any person not therein named.

Authorized Signature Date

File: 2026-167 RFQ Scoping 0021719.docx Page 18 of 45

EXHIBIT C: DBE UTILIZATION FORM

SCOPING PI# 0021719

The undersigned Bidder/Offeror has satisfied the requirements of the solicitation in the following manner (please check the appropriate space):

The Bidder/Offeror anticipates using one or more DBE and/or small business on the project to include approximately 10% of the total contract amount. In accordance with Liberty County Policy the DBE goal is mandatory.

DBE PARTICIPATION SCHEDULE

The Bidder/Offeror shall complete the following information for all DBE’s participating in the contract that comprises the DBE Utilization percent stated in the DBE Utilization Form. The Bidder/Offeror shall also furnish the name and telephone number of the appropriate contact person should the Liberty County Board of Commissioners have any questions in relation to the information furnished herein.

DBE IDENTIFICATION AND INFORMATION FORM

Name and Address Contact Name and Telephone Number

Participation Percent of Total Contract Value

Description of Work to be Performed

Certified DBE by GDOT?

( ) yes ( )no

File: 2026-167 RFQ Scoping 0021719.docx Page 19 of 45

EXHIBIT D: CERTIFICATION OF ELIGIBILITY TO PROPOSE

(Name of Proposer): hereby certifies that it is not included on the U.S. Comptroller General’s Debarred Bidders List.

Signature of Authorized official:

Firm:

The Proposer further certifies to the best of its knowledge and belief that it and its principals

A) Are not presently debarred, suspended, proposed for debarment, declared ineligible or voluntarily excluded from covered transactions by any federal department or agency. Have not within a three (3) year period preceding this Proposal, been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, state or local) transaction or contract under a public transaction, violation of Federal or state antitrust statutes, or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making a false statement, or receiving stolen property.

B) Are not presently indicted for, or otherwise criminally or civilly charged by a governmental entity

(Federal, state or local) with commission of, any of the offenses enumerated in Paragraph B of this certification.

C) Have not within a three (3) year period preceding this Proposal had any public transactions

(federal, state or local) terminated for cause or default.

Where the Proposer is unable to certify to any of the statements in this Certification, such Proposer shall attach an explanation to this Proposal.

Check One:

I DO CERTIFY I DO NOT CERTIFY

DATE:

SIGNATURE:

NAME & TITLE:

File: 2026-167 RFQ Scoping 0021719.docx Page 20 of 45

EXHIBIT E: CERTIFICATION OF NON-COLLUSION

The undersigned certifies under penalties of perjury that this Proposal has been made and submitted in good faith and without collusion or fraud with any other person. As used in this Certification, the word “person” shall mean any natural person, business, partnership, corporation, Union committee, club, or other organization, entity or group of individuals.

SIGNATURE:

NAME:

FIRM:

DATE:

File: 2026-167 RFQ Scoping 0021719.docx Page 21 of 45

EXHIBIT F: FEDERALLY REQUIRED CONTRACT CLAUSES

NO GOVERNMENT OBLIGATION TO THIRD PARTIES

(1) The Purchaser and Contractor acknowledge and agree that, notwithstanding any concurrence by the Federal Government in or approval of the solicitation or award of the underlying contract, absent the express written consent by the Federal Government, the Federal Government is not a party to this contract and shall not be subject to any obligations or liabilities to the Purchaser, Contractor, or any other party (whether or not a party to that contract) pertaining to any matter resulting from the underlying contract.

(2) The Contractor agrees to include the above clause in each subcontract financed in whole or in part with Federal assistance provided by FTA. It is further agreed that the clause shall not be modified, except to identify the subcontractor who will be subject to its provisions.

ASSIGNABILITY CLAUSE

Neither the Liberty County Board of Commissioners nor the contractor shall assign or transfer any of its rights or obligations hereunder without the prior written consent of the other

PROGRAM FRAUD AND FALSE OR FRAUDULENT STATEMENTS& RELATED ACTS

(1) The Contractor acknowledges that the provisions of the Program Fraud Civil Remedies Act of 1986, as amended, 31. U.S.C. § § 3801 et seq. and U.S. DOT regulations, "Program Fraud Civil Remedies," 49 C.F.R. Part 31, apply to its actions pertaining to this Project. Upon execution of the underlying contract, the Contractor certifies or affirms the truthfulness and accuracy of any statement it has made, it makes, it may make, or causes to be made, pertaining to the underlying contract or the FTA assisted project for which this contract work is being performed. In addition to other penalties that may be applicable, the Contractor further acknowledges that if it makes, or causes to be made, a false, fictitious, or fraudulent claim, statement, submission, or certification, the Federal Government reserves the right to impose the penalties of the Program Fraud Civil Remedies Act of 1986 on the Contractor to the extent the Federal Government deems appropriate.

(2) The Contractor also acknowledges that if it makes, or causes to be made, a false, fictitious, or fraudulent claim, statement, submission, or certification to the Federal Government under a contract connected with a project that is financed in whole or in part with Federal assistance originally awarded by FTA under the authority of 49 U.S.C. § 5307, the Government reserves the right to impose the penalties of 18 U.S.C. § 1001 and 49 U.S.C. § 5307(n)(1) on the Contractor, to the extent the Federal Government deems appropriate.

(3) The Contractor agrees to include the above two clauses in each subcontract financed in whole or in part with Federal assistance provided by FTA. It is further agreed that the clauses shall not be modified, except to identify the subcontractor who will be subject to the provisions.

File: 2026-167 RFQ Scoping 0021719.docx Page 22 of 45

FEDERAL CHANGES - 49 CFR Part 18

Federal Changes - Contractor shall at all times comply with all applicable FTA regulations, policies, procedures and directives, including without limitation those listed directly or by reference in the Master Agreement between the Liberty County Board of Commissioners and FTA, as they may be amended or promulgated from time to time during the term of this contract. Contractor's failure to so comply shall constitute a material breach of this contract.

INCORPORATION OF FEDERAL TRANSIT ADMINISTRATION (FTA) TERMS

FTA Circular 4220.1F

Incorporation of Federal Transit Administration (FTA) Terms - The preceding provisions include, in part, certain Standard Terms and Conditions required by DOT, whether or not expressly set forth in the preceding contract provisions. All contractual provisions required by USDOT, as set forth in FTA Circular 4220.1F are hereby incorporated by reference. Anything to the contrary herein notwithstanding, all FTA mandated terms shall be deemed to control in the event of a conflict with other provisions contained in this Agreement. The Contractor shall not perform any act, fail to perform any act, or refuse to comply with any the Liberty County Board of Commissioners requests which would cause the Liberty County Board of Commissioners to be in violation of the FTA terms and conditions.

AMERICANS WITH DISABILITIES ACT (ADA)

ADA Access - This requirement applies to contracts for Architectural and CONSULTING Services.

The contractor agrees to comply with the requirements of 49 U.S.C. § 5301 (d), which states the Federal policy that the elderly and persons with disabilities have the same right as other persons to use mass transportation service and facilities, and that special efforts shall be made in planning and designing those services and facilities to implement that policy. The contractor also agrees to comply with all applicable requirements of section 504 of the Rehabilitation Act of 1973, as amended, 29 U.S.C. § 794, which prohibits discrimination on the basis of handicaps, with the Americans with Disabilities Act of 1990 (ADA), as amended, 42 U.S.C. §§ 12101 et seq., which requires that accessible facilities and services be made available to persons with disabilities, including any subsequent amendments to that Act, and with the Architectural Barriers act of 1968, as amended, 42 U.S.C. §§ 4151 et seq., which requires that buildings and public accommodations be accessible to persons with disabilities, including any subsequent amendments to that Act. In addition, the contractor agrees to comply with any and all applicable requirements issued by the FTA, DOT, DOJ, U.S. GSA, U.S. EEOC, U.S. FCC, any subsequent amendments thereto and any other nondiscrimination statute(s) that may apply to the Project.

http://www.fta.dot.gov/16874_16882_ENG_HTML.htm

File: 2026-167 RFQ Scoping 0021719.docx Page 23 of 45

GOVERNMENT-WIDE DEBARMENT AND SUSPENSION (NONPROCUREMENT)

49 CFR Part 29, Executive Order 12549

This contract is a covered transaction for purposes of 49 CFR Part 29. As such, the contractor is required to verify that none of the contractor, its principals, as defined at 49 CFR 29.995, or affiliates, as defined at 49 CFR 29.905, are excluded or disqualified as defined at 49 CFR 29.940 and 29.945. The contractor is required to comply with 49 CFR 29, Subpart C and must include the requirement to comply with 49 CFR 29, Subpart C in any lower tier covered transaction it enters into. By signing and submitting its bid or proposal, the bidder or proposer certifies as follows:

The certification in this clause is a material representation of fact relied upon by the Liberty County Board of Commissioners. If it is later determined that the bidder or proposer knowingly rendered an erroneous certification, in addition to remedies available to the Liberty County Board of Commissioners, the Federal Government may pursue available remedies, including but not limited to suspension and/or debarment. The bidder or proposer agrees to comply with the requirements of 49 CFR 29, Subpart C while this offer is valid and throughout the period of any contract that may arise from this offer. The bidder or proposer further agrees to include a provision requiring such compliance in its lower tier covered transactions.

ENERGY CONSERVATION REQUIREMENTS - 42 U.S.C. 6321 et seq. , 49 CFR Part 18

Energy Conservation - The contractor agrees to comply with mandatory standards and policies relating to energy efficiency which are contained in the state energy conservation plan issued in compliance with the Energy Policy and Conservation Act.

SEISMIC SAFETY REQUIREMENTS - 42 U.S.C. 7701 et seq. 49 , CFR Part 41

Seismic Safety - The contractor agrees that any new building or addition to an existing building will be designed and constructed in accordance with the standards for Seismic Safety required in Department of Transportation Seismic Safety Regulations 49 CFR Part 41 and will certify to compliance to the extent required by the regulation. The contractor also agrees to ensure that all work performed under this contract including work performed by a subcontractor is in compliance with the standards required by the Seismic Safety Regulations and the certification of compliance issued on the project.

FLY AMERICA REQUIREMENTS – 49 U.S.C. §40118, 41 CFR Part 301-10

The Fly America requirements apply to the transportation of persons or property, by air, between a place in the U.S. and a place outside the U.S., or between places outside the U.S., when the FTA will participate in the costs of such air transportation. Transportation on a foreign air carrier is permissible when provided by a foreign air carrier under a code share agreement when the ticket identifies the U.S. air carrier's designator code and flight number. Transportation by a foreign air carrier is also permissible if there is a bilateral or multilateral air transportation agreement to which the U.S. Government and a foreign government are parties and which the Federal DOT has determined meets the requirements of the Fly America Act. Micro-purchases are defined as those purchases under $2,500. These requirements do not apply to micro-purchases. The Fly America requirements flow down from FTA recipients and sub-recipients to first tier contractors, who are responsible for ensuring that lower tier contractors and subcontractors are in compliance. The relevant statutes and regulations do not mandate any specified clause or language. FTA proposes the following language.- The Contractor agrees to comply with 49 U.S.C. 40118 (the "Fly America" Act) in accordance with the General Services Administration's regulations at 41 CFR Part 301-10, File: 2026-167 RFQ Scoping 0021719.docx Page 24 of 45 which provide that recipients and sub-recipients of Federal funds and their contractors are required to use U.S. Flag air carriers for U.S Government-financed international air travel and transportation of their personal effects or property, to the extent such service is available, unless travel by foreign air carrier is a matter of necessity, as defined by the Fly America Act. The Contractor shall submit, if a foreign air carrier was used, an appropriate certification or memorandum adequately explaining why service by a U.S. flag air carrier was not available or why it was necessary to use a foreign air carrier and shall, in any event, provide a certificate of compliance with the Fly America requirements. The Contractor agrees to include the requirements of this section in all subcontracts that may involve international air transportation.

TERMINATION - 49 U.S.C. Part 18, FTA Circular 4220.1F

a. Termination for Convenience (General Provision) The Liberty County Board of Commissioners may terminate this contract, in whole or in part, at any time by written notice to the Contractor when it is in the Government's best interest. The Contractor shall be paid its costs, including contract close-out costs, and profit on work performed up to the time of termination. The Contractor shall promptly submit its termination claim to the Liberty County Board of Commissioners to be paid the Contractor. If the Contractor has any property in its possession belonging to the Liberty County Board of Commissioners, the Contractor will account for the same, and dispose of it in the manner the Liberty County Board of Commissioners directs.

b. Termination for Default [Breach or Cause] (General Provision) If the Contractor does not deliver supplies in accordance with the contract delivery schedule, or, if the contract is for services, the Contractor fails to perform in the manner called for in the contract, or if the Contractor fails to comply with any other provisions of the contract, the Liberty County Board of Commissioners may terminate this contract for default.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .