AAAP Post Award Schedule (7).pdf

PDF 12 KB Posted

Attached to
Lease of Office Space within Region 10. Request for Lease Proposals (RLP) #24-REG10-Office Space
Solicitation number
24-REG10_2WA0663
Issued by

About this file

This document is the AAAP Post-Award Schedule, which details the generic post-award schedule for AAAP projects based on the size of the requirement. The schedule commences within 5 working days of lease award and outlines the timeframes for the management of the design and construction process, concluding at the date of acceptance for the space. The schedule is referenced when reviewing section 4.01 of the lease, and the Government may modify this schedule for specific projects using an exhibit to the project-specific advertisement posted on the System for Award Management website (SAM.gov).

The related federal contract opportunity is for the Lease of Office Space within Region 10. The U.S. Government seeks to lease 4,250-5,000 ABOA square feet of office space in the Central Business Area of Port Angeles, WA, with a 17-year lease term and 15 firm years. The Government will use the Automated Advanced Acquisition Program (AAAP) to satisfy this space requirement. Offerors must submit rates for all terms available in the AAAP for consideration against future GSA requirements. The Government intends to award a lease to the lowest price, technically acceptable offer, without negotiations.

View the file

Other files

File Type Posted
H DA.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 2 RLP VERSION - REV (10/22)

AAAP Post-Award Schedule

This exhibit details the generic post-award schedule for AAAP projects based on the size of the requirement and should be referenced when reviewing section 4.01 of the lease. The Government may modify this schedule for specific projects using an exhibit to the project specific advertisement posted on the System for Award Management website (SAM.gov).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity

Working Days Based on ANSI/BOMA Occupant Area Square Feet

0K to <20K

ABOA SF

20K to <50K

ABOA SF

50K to <70K +

ABOA SF

Lessor-Provided Design Intent Drawings 30 40 45

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings

45 50 50

Lessor Preparation and Submission of Construction Documents

20 20 35

Government Review of Construction Drawings 20 25 25

Lessor Preparation and Submission of the TI and BSAC Price Proposal

20 30 40

Government Reviews and Approves Pricing 30 30 40

Government Issues Notice to Proceed with Construction

10 10 10

Lessor Completes Construction of TIs and Completion of Other Required Construction Work

60 130 260

AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 RLP VERSION - REV (10/22)

Government Inspects and Accepts Finished Space

10 10 10

Total Work Days from Lease Award to Government Acceptance

245 345 515