This is a Quality Assurance Surveillance Plan (QASP) document for a 750 kW Rental Emergency Diesel Generator contract.
The QASP establishes performance standards and surveillance methods for monitoring the contractor's delivery and maintenance of one 750 kW Emergency Diesel Generator and one 1600 Amp Automatic Transfer Switch (ATS) during the performance period of August 17, 2026 through November 17, 2026. The plan defines key performance metrics including equipment delivery timeliness, operational readiness, fuel delivery and management, maintenance responsiveness, and documentation compliance. Surveillance activities include receipt inspections, weekly operational checks, fuel quality verification, preventive maintenance monitoring, and contractor report reviews. The QASP specifies acceptance criteria such as generator arrival within required timeframes, ATS functionality verification, fuel delivery within specified intervals, maintenance response times not exceeding 24 hours for critical issues, and complete maintenance records. Performance monitoring is the responsibility of the contracting officer's technical representative (COTR) with documented observations recorded and corrective action procedures established for non-compliance. The document provides the framework for ensuring the contractor delivers reliable emergency power generation capabilities meeting the Navy's operational requirements at Naval Base Kitsap Bangor in Silverdale, Washington.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 2: Quality Assurance Surveillance Plan Quality Assurance Surveillance Plan (QASP) Project: Emergency Diesel Generator (EDG) and Automatic Transfer Switch (ATS) Place of Performance: Trident Refit Facility, Silverdale WA @ Various piers in WRA.
Period of Performance: 15-AUGUST-2026 thru 15-OCTOBER-2026
| Requirement |
| PWS |
| Performance Standards |
| Allowable Deviation |
| Surveillance Method |
| Correction Procedures |
| Certified manufacturers technical representative shall make repairs or replacement determination within 4-hours of notification of a problem. |
| Para 4.6 |
| Contractor begins evaluation of system and provides the Government a determination within 4 hours of service call. |
| The contractor shall not deviate from the 4-hour determination schedule. In the event of any Government caused delays please communicate issues to the Contracting Officer Representative (COR). |
| COR will track response time and determination notification on service request forms and monthly reports. |
| Government will seek an equitable price reduction or other adequate consideration for acceptance of nonconforming services. |
| Replacement of Emergency Diesel Generator (EDG) and/or Automatic Transfer Switch (ATS) will be within 48-hours of replace or repair determination being communicated to the Government. |
| Para 4.6 |
| The contractor will remove the EDG/ATS that needs to be replaced and have a 100%fully operational EDG/ATS in place within 48-hours of the repair/replace determination. The contractor provided process- control-procedures that will -outline the processes to be followed. |
| The contractor shall not deviate from the 48-hour replacement schedule. In the event of Government caused delays please communicate issues to the COR. |
| COR will track response time and determination notification on service request forms and COR surveillance reports. |
| Government will seek an equitable price reduction or other adequate consideration for acceptance of nonconforming services. |
| Repair or replacement determination of Emergency Diesel Generator (EDG) will be within 4-hours of manufacturer’s technical representative being onsite troubleshooting of discrepancy. |
| Para 4.6 |
| The contractor will repair the EDG/ATS within 4-hours of making a repair or replace determination. The contractor provided process-control- procedure that will outline the processes to be followed. |
| The contractor shall not deviate from the 4-hour repair schedule. In the event of Government caused delays please communicate issues to the COR. |
| COR will track response time and determination notification on service request forms and |
COR surveillance reports.
Government will seek an equitable price reduction or other adequate consideration for acceptance of nonconforming services.
| Equipment Maintenance and Delivery |
| Para 4.1, 4.2, 4.4, 4.6 and 4.7. |
| The contractor will provide all required pre-delivery maintenance, follow the delivery instructions, and include all required submittals with each delivery. |
| The contractor shall comply with all PWS requirements and communicate with the COR for delivery and if any of the requested performance characteristics cannot be met by system prior to delivery. The Government will determine on a case- -by-case basis as to the acceptability of non-conforming supplies. |
| COR and Customer will coordinate deliveries and provide for inspection and acceptance at point of delivery once system is in place. |
Any part of the pre-delivery maintenance that reveals non-conformance with the PWS must be communicated prior to Government acceptance. Contractor will receive notification from the COR of any acceptability of non-conforming supplies prior to removal from point of origin.
Immediate no cost re-performance for any EDG/ATS found to be incapable of meeting basic PWS requirements at point of origin.
Government will seek an equitable price reduction, other adequate consideration for acceptance of non-conforming supplies if the contractor communicates variances from the PWS and the CONTRACTING OFFICER allows for delivery despite non-conformance with PWS. The Government and Contractor will mutually agree to the price reduction or consideration prior to delivery.