A5 - CVN 68 2 HPAC SOW Air End Overhaul Redacted.pdf
PDF 764 KB Posted
- Attached to
- Intent to Sole Source No. 2 HPAC Repairs Federal contract opportunity
- Solicitation number
- N4523A25R6018
About this file
This Statement of Work (SOW) details a Class B overhaul for High Pressure Air Compressor (HPAC) No. 2 for the Puget Sound Naval Shipyard and Intermediate Maintenance Facility. The work will be performed onboard a CVN 68 class Aircraft Carrier from March 24, 2025, through April 22, 2025, with the Original Equipment Manufacturer (OEM) tasked with restoring the compressor to normal operating condition. Key requirements include performing an air end overhaul, accomplishing Level II cleanliness requirements, submitting a Condition Found Report within three business days, and conducting a four-hour operational test.
The contractor must comply with specific security and radiological requirements, including obtaining Defense Biometric Identification System (DBIDS) credentials, passing background checks, and potentially working in areas requiring personal radiation monitoring. The government will provide support services such as rigging/crane support and oil/coolant replenishment. Deliverables include a Condition Found Report and a Completion Report, both to be submitted to the Contracting Officer's Representative. The SOW indicates this is a sole-source contract with Curtiss-Wright Fleet Solutions, who are the NAVSEA authorized service provider with proprietary design specifications for the HPAC.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B2 - Sole Source Justification CVN 68 2 HPAC Redacted.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
FOR
High Pressure Air Compressor’s (HPAC) No. 2; Class B Overhaul
1.0 BACKGROUND:
The Puget Sound Naval Shipyard and Intermediate Maintenance Facility (PSNS&IMF) in support of a CVN 68 class Aircraft Carrier requires the Original Equipment Manufacturer (OEM) to provide services to restore High Pressure Air Compressor (HPAC) No. 2 to normal operating condition
1.1 SCOPE:
1.1.1 Air End Overhaul High Pressure Air Compressor’s (HPAC) No. 2
2.0 REFERENCES:
2.1 NAVSEA 389-0288; Radiological Controls.
2.2 Northwest Regional Maintenance Center Local Standard Item
2.3 S6220-DD-MMA-010; HIGH-PRESSURE AIR COMPRESSOR OIL FREE MODELS N30NL-4,
4A, AND 3E
2.4 NAVSEA S9AA0-AB-GOS-010; General Specifications for Overhaul of Surface Ships
2.5 Cleanliness Verification Sign-Off Sheet (Attachment A)
2.6 Operating Log-5000 PSIG Service (Attachment B)
2.7 Material History Record (Attachment C)
3.0 REQUIREMENTS:
3.1 Period of Performance: March 24, 2025, through April 22, 2025.
3.2 Planning, supervising, or performing nuclear work is NOT authorized without the express approval of .
3.3 LOCATION OF WORK:
3.3.1 This work will be performed Onboard the Naval Vessel while vessel is deployed.
3.3.1.1 Contractor employees require access to the following compartment(s) to conduct repairs to No. 2 HPAC, Main Machinery Room
3.4 RESTRICTED DATA:
3.4.1 Contractor employees require access to and control of RESTRICTED DATA (RD), regarding Naval Nuclear Propulsion Information (NNPI and U-NNPI), to accomplish the requirements of this contract.
3.5 WORK CONTROLS:
3.5.1.1 Coordinate with Ship’s Force (SF) to verify boundaries and ensuring entire site is isolated and ready for work.
3.5.1.2 Ensure all work on ship’s systems and components properly authorized and controlled to ensure personnel and ship safety standards are met. Ships Force
(SF) will act as the Repair Activity designated representative (s) for the tag out of isolation.
3.5.1.3 Review Work Authorization Form (WAF) with ship's force to ensure understanding authorized work areas prior to starting work and maintain a copy of the WAF onsite during production work.
3.5.1.4 Make request at least five (5) days prior to needing changes to isolation or work boundary to Ship’s Force (SF).
3.5.1.5 Ensure the isolation, de-energizing, drainage of the isolated and depressurization of mechanical, electrical, electronics and pressure system is accomplished.
3.5.1.6 Submit changes to isolation or work boundaries to Ship’s Force (SF) upon completion of production work, sign Block 16 of WAF.
3.6 SECURITY REQUIREMENTS:
3.6.1 Defense Biometric Identification System (DBIDS) Program: Commander, Navy
Installations Command (CNIC) has established the Defense Biometric Identification System (DBIDS) for access control to CNIC Installations via Entry Control Points (ECP). DBIDS is an enterprise identity management and perimeter installation access control solution in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to three years, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. There are no fees associated with obtaining a DBIDS credential.
3.6.2 The Government performs background screening and credentialing. Throughout the year, the Contractor employee must continue to meet background-screening standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
3.6.3 Access to Installation. All Contractor personnel shall obtain access to the installation through enrollment and registration into the Defense Biometric Identification System (DBIDS). The Contractor shall provide the Contracting Officer with the name of their designated Service Contractor Administrator (SCA) for enrollment in DBIDS.
Contact the Contracting Officer’s Representative (COR) or Contracting Officer’s Security Officer for assistance as needed. Once enrolled, the Contractor must provide the DBIDS Registrar with an approved employee list and then direct their employees to register into DBIDS.
3.6.4 DBIDS Credentials. Contractor employees shall furnish a completed copy of the SECNAV 5512/1 form to obtain the required background check and visit the local Navy Installation Visitor Control Center to obtain a DBIDS credential once approved.
The SECNAV 5512/1 form and additional information about DBIDS can be found at https://www.cnic.navy.mil/om/dbids.html.
3.6.5 Unescorted access requires authenticating an individual’s identity and determining their fitness using the following guidelines:
3.6.5.1 Identity Proofing. The process of providing sufficient information (e.g., identity history, credentials, and documents) when attempting to establish an identity. The following credentials are identity proofed at the card issue site from federally authorized identity documents and will be considered identity proofed. CAC, Uniformed Services Identification (ID) Card issued to military retirees and military family members, Non-DoD Federal Personal Identification Verification, United States (U.S.) Passport or Passport Card, Foreign passport that contains a temporary I-551 stamp or temporary I-551 printed notation on a machine-readable immigrant visa, or others listed in reference (a) and chapter 16. (Note: While certain identification is approved for identity proofing, in order to register a visitor into DBIDS, the visitor must have an ID with an ID number associated. U.S.
Citizens are required to provide their Social Security Number (SSN), Certificate of Naturalization or Taxpayer ID Number to receive a DBIDS pass to access the installation).
3.6.5.2 Vetting. An evaluation of an applicant or card holder’s character and conduct for approval, or denial of the issuance of an access control credential for physical access. The SECNAV 5512/1 is the sole means to initiate background checks on all visitors and/or contractors/vendors. Every background check for the purpose of access control requires completion of SECNAV 5512/1 for accountability purposes.
3.6.6 Personnel requiring access for 31 days or more will be issued a DBIDS card once all required documentation is provided to the VCC and registration is completed. Visits for 30 days or less will receive a paper DBIDS pass.
3.6.7 DBIDS passes require a picture and fingerprints for all visitor registrations. Failure to provide either can result in denial of base access for escorted or unescorted access.
3.6.8 Pre-enrollment. DBIDS pre-enrollment is available at https://dbids-usfj.dmdc.mil/portal/.
3.6.9 Contractors shall be accessing Machinery Spaces that contain UNNPI, NOFORN information, NNPI National Security Information (NSI), and Restricted Data.
Workers assigned to work in these spaces REQUIRES A FINAL SECURITY CLEARANCE: Minimum of Confidential.
3.6.10 Coordinate all contractor employee badging and security issues via the Government representative:
3.7 RADIOLOGICAL REQUIREMENTS:
3.7.1 Contractor may be required to accomplish work onboard ship in areas that require personal monitoring of radiation (i.e. wearing a TLD). Contractor employees shall be trained in accordance with Reference 2.1 and be able to check out a TLD. Contracted workers will not handle radioactive materials or perform work on radiological controlled systems. Contractor shall obtain TLD’s from Ship’s Force (SF) as required.
3.8 GOVERNMENT REPRESENTATIVES:
3.8.1 Contracting Officer Representative (COR): Located within the contract
3.9 TECHNICAL WORK REQUIREMENTS:
3.9.1 Comply with the requirements of Northwest Regional maintenance Center Local
Standard Item 099-12NW of Reference 2.2.
3.9.2 No. 2 HPAC:
3.9.2.1 Perform air end overhaul of No. 2 HPAC to restore unit to normal working condition in accordance with OEM specification and ref. 2.3 as guidance.
3.9.3 Accomplish the level II cleanliness requirements of Reference 2.4 section 505j and verify on attachment A, Reference 2.5.
3.9.4 Submit a Condition Found Report (CFR) for the compressor to the Contracting Officer’s Representative (COR) within three business days. The report should contain the following information: (CDRL A001, DI-MGMT-81648)
3.9.5 Observe Operational testing. Testing will be a four-hour run at normal conditions.
3.9.5.1 Complete and submit log sheet attachment B, ref 2.6 or vendor equivalent to the Contracting Officer’s Representative (COR).
3.9.5.2 Accomplish additional minor repairs of No. 2 HPAC to correct air, oil, water leaks, and electrical discrepancies.
3.9.6 Submit a signed copy of attachment C MATERIAL HISTORY DATA SHEET, ref 2.7 to the Contracting Officer’s Representative (COR) upon completion of work on compressor and components.
3.9.7 Submit one legible copy, in electronic media, of the Completion Report to the COR within three (3) business days of completion of HPAC repairs containing the following information (CDRL A002, DI-MGMT-82050).
4.0 Contractor Furnished Material
4.1 OEM will provide all material necessary to return unit to operational condition.
5.0 GOVERNMENT WILL PROVIDE:
5.1 Services provided as listed below:
5.1.1 Provide rigging/crane support from equipment spaces to Hanger Bay, and from Hanger Bay to Pier and return.
5.1.2 Provide drain/disposal/replenishment of 2190 oil.
5.1.3 Provide drain/disposal/replenishment of Jacket Water 50/50 Coolant Mix.
6.0 QUALITY:
6.1 Quality Assurance Surveillance Plan (QASP): The Quality Assurance Surveillance Plan (QASP) is a tool the Government utilizes to verify the contractor is performing all services and delivery/installation of replacement parts required by the above requirements in a timely, accurate and complete fashion.
7.0 DELIVERABLE ITEMS:
Number Name Frequency Quantity
A001 Condition Found Report (CFR) As needed 1 Each
A002 Completion Report Within 3 business days 1 Each
Attachment A:
TITLE: Verification of Levels of Cleanliness Sheet
DISTRIBUTION STATEMENT D:
Distribution authorized to DOD components and DOD contractors only; Critical Technology; May 2017. Other requests for this document shall be referred to Puget Sound Naval Shipyard (Code 260).
Destroy by any method that will prevent disclosure of the contents or reconstruction of the document.
Ship System: Compressed Air Systems, SWLIN 551 Equipment: High Pressure Air Compressor, SWLIN 551
References: 1) NAVAL SHIPYARD QUALITY PROGRAM MANUAL (NAVSEA TL855- AA-STD-010 Rev 4)
2) INSPECTIONS AND VERIFICATIONS IN NONNUCLEAR SHIPS
SYSTEMS (PSNS&IMFINST 4730.62 31 Aug 2018)
3) ENGINEERING AND PLANNING PROCEDURES MANUAL (EPPM)
ENGRDEPT P5200(2) (Rev LATEST)
4) GENERAL SPECIFICATIONS FOR OVERHAUL OF SURFACE SHIPS
(S9AA0-AB-GOS -010 Rev 10), PARAGRAPH 505J.
5) UNIVERSAL PROCESS INSTRUCTION (UIPI) 0505-908 (Rev LATEST)
LEVEL II AND III CLEANLINESS FOR PIPING SYSTEMS/EQUIPMENT
Definitions:
System Entry: Contractor technicians have entered/opened up the respective fluid portion of the specific system.
Level II Cleanliness: Surface shall be visually free of grease, oil, flux, scale, dirt, loose particles, and any other contamination foreign to the base metal. Tap water residues on all metals and light superficial rust on carbon steel surfaces, caused by short time exposure to the atmosphere, are permitted. Light dust on cleaned surfaces is not objectionable, if the quantity and size of the particles does not adversely affect the system operation.
Background:
Reference (1) Chapter 7 tasks the shipyard to “develop and maintain procedures to ensure work performed associated with repair or conversion of Naval ship systems and/or components meet specified requirements in order to preclude downstream failures.” Reference (1) Section 7.2 establishes Inspection and Verification (I&V) Attributes that the shipyard is responsible for in ensuring that the NAVSEA I&V attributes are invoked in locally developed Technical Work Instructions. Further local guidance is provided in Reference (2) for PSNS & IMF and associated entities. Reference (3), Appendix C-54, establishes <V> attribute 551-001 for system cleanliness on compressed air systems.
Reference (1 & 2) establish that verification attributes <V> may be performed by either PSNS & IMF production (shop supervisor or mechanic), Quality Assurance Officials (QAO), or other personnel that have been appropriately trained to perform this function.
As required by Reference (2), the person designated to sign for an action verifies, based on personnel observation or Objective Quality Evidence, and certifies by his/her signature that the action has been performed in accordance with the specified requirements. Any work performed by the Task Group Instruction (TGI) involving an I/V which is subsequently voided by additional work or requires performing an I/V attribute that already has been signed off will require that affected I/V attribute to be reinvoked.
NOTES:
1) This document here by serves as a briefing to allow contractors to complete <V> attributes as follows in this document.
2) Attributes have been modified to be worded for Contractor mechanics or Contractor supervisor to be able to complete.
3) Additional guidance for Level II Cleanliness is provided in Reference (5). Contractor can reach out to Contracting Official Representative (COR) or Project Engineer (PE) for further guidance and clarification on technical requirements for Level II Cleanliness.
Procedure & Signatures:
1) Prior to certification of work, contractor shall complete the following signatures for <V> Attribute 551-001 as implemented by References (1 – 5).
1.1) Instructions for completing signatures (NOTE: Print in “Name” block):
1.1.1) If entry into the air system, as previously defined, was not performed, then contractor technician shall mark “No” and complete “Level II Cleanliness Maintained” marked as “N/A”.
Contractor shall then complete “Name”, “Signature”, and “Date”.
1.1.2) If entry into the air system, as previously defined, was performed, then the contractor technician shall mark “Yes” and complete “Level II Cleanliness Maintained” marked as “Yes” (upon verifying that system meets Level II requirements, as previously defined, upon closure of the system,). Contractor shall then complete “Name”, “Signature”, and “Date”.
2.) After completion of signatures, submit either original or copy of signed sheet (in forms of electronic media as specified in the PWS) to the COR.
See following sheets for signatures to complete.
High Pressure Air Compressor No. 2:
System Entry – Yes: No:
<V> Attribute 551-001: Accomplish signoff for cleanliness per PSNS&IMFINST 4730.62. Acceptance criteria: After completion of work FME & Level II Cleanliness was maintained on High Pressure Air Compressor No. 2 was maintained per UIPI 0505-908.
Comments:
Level II Cleanliness Maintained – Yes: ___ N/A: ____
Name:
Signature:
Date:
Attachment B:
Sheet 1 of
5000 PSIG SERVICE
HIGH PRESSURE AIR COMPRESSOR
(4-HOUR) OPERATING LOG
COMPRESSOR SERIAL NUMBER _______________________________________ DATE ___________________
COMPRESSOR
OPERATING MODE:
MAN _____ AUTO ________
CONDS. DRAIN MODE:
MAN________ AUTO ______
UNMON______ MON______
SHUTDOWN NORM
TIME
PR
ES
SU
RE
(P
SI
G
1ST STAGE DISCH 60a 33-38
2ND STAGE DISCH 175a 90-100
3RD STAGE DISCH 550a 310-350
4TH STAGE DISCH 1300a 775-855
5TH STAGE DISCH 3000a 1900-2100
6TH STAGE DISCH 5500a 5000
FRAME OIL BEFORE FILTER Noted
FRAME OIL AFTER FILTER BELOW 12 ± 2b 25-50
FRESH WATER 8-10
PILOT AIR 145-150
TE
M
PE
RA
TU
RE
F)
1ST STAGE DISCH 360b 260-300g
2ND STAGE DISCH 345b 270-300g 3RD STAGE DISCH 345 315-335g 4TH STAGE DISCH 345 270-300g 5TH STAGE DISCH 345 255-280g 6TH STAGE DISCH 345 250-270g FRESH WATER OUTLET 200 120-130g CRANKCASE OIL 180 120-150g SEA WATER OUTLET 390+ f 95g FINAL AIR DISCH 125 b 70-95g
1ST STAGE SUCT AMB + 20
2ND STAGE SUCT 70-120
3RD STAGE SUCT 70-110
4TH STAGE SUCT 70-110
5TH STAGE SUCT 70-110
6TH STAGE SUCT 70-110
a. Relief valve lifts
b. Automatic shutdown
c. In AUTOMATIC, compressor should normally start when pressure is less than/drops to 4700 PSIG.
d. When Oil Pressure Differential, at normal operating temperature, reaches 10 PSIG, the filter must be changed.
e. Maximum duration at 5500 PSIG: 2 hours in an 4 hour period.
f. Not used: set to maximum possible value, must be at least 390°
g. Variation in seawater inlet temperature may change this value significantly, see table 2.1B.
Figure 2-7 Operating Log - 5000 PSIG Service
Attachment C:
Sheet 1 of
MATERIAL HISTORY DATA SHEET
MH Document #
Ship’s Name:
Hull:
Plant:
Ship's System:
Common Name of Equipment:
Accomplished by:
Location and Compartment:
FOR SHIPYARD USE ONLY: Applicable ICN and KeyOp(s):
Electrical Electronic Hull Machinery
MATERIAL HISTORY DATA SHEET SUMMARY:
Modifications/Alterations (Areas to Consider)
ShipAlt, Field Change, or A&I Number and Revision:
Brief Description of Work Accomplished
Preventative Maintenance (Areas to Consider)
Maintenance Requirement:
Brief Description of Maintenance :
Problems Identified and Resulting Corrective Maintenance :
Corrective Maintenance (Areas to Consider) Replacement Part Information Detailed Description of Problem and Symptoms Details of Actions Taken Including Testing Performed
Supporting Documentation (Areas to Consider)
Description of Enclosures:
Highlight Applicable Information
MATERIAL HISTORY DESCRIPTION OF EVENT:
Date Remarks
ORIGINATOR/POINT OF CONTACT:
NAME (Print) Code Phone Number Date
REVIEWER:
NAME (Print) Code Phone Number Date
Attachment C:
Sheet of
MATERIAL HISTORY CONTINUATION DATA SHEET
MH Document #
Ship’s Name:
Hull:
Plant: Ship's System:
Common Name of Equipment: Location and Compartment:
MATERIAL HISTORY DESCRIPTION OF EVENT (Continued):
Date Remarks
File details come from the government source that posted it. Updated .