A5 43249900 Quality Assurance Surveillance Plan.pdf
PDF 53 KB Posted
- Attached to
- Lease of 100kW Diesel Generator
- Solicitation number
- N4523A25Q4022
About this file
This is a Quality Assurance Surveillance Plan (QASP) for an Emergency Diesel Generator (EDG) project at Puget Sound Naval Shipyard and Intermediate Maintenance Facility, covering the period from February 28, 2025 to February 27, 2026. The plan outlines specific performance requirements, standards, and surveillance methods for the contractor's maintenance and service of the EDG system.
The QASP establishes key performance metrics including: a 4-hour response time for certified mechanics to make repair/replace determinations after problem notification, a 48-hour timeline for EDG/ATS replacement after determination, and a 48-hour timeline for repairs. The contractor must provide all required pre-delivery maintenance and follow delivery instructions with proper documentation. Any deviations from performance standards must be communicated to the Contracting Officer Representative (COR), who tracks compliance through service request forms and monthly reports. Non-conforming services may result in price reductions or required re-performance at no cost to the government.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Surveillance Plan (QASP) Project: Emergency Diesel Generator (EDG).
Place of Performance: Puget Sound Naval Shipyard and Intermediate Maintenance Facility.
Period of Performance: 28 February 2025 - 27 February 2026
Requirement PWS Performance Standards Allowable Deviation Surveillance Method Correction Procedure Certified Mechanic shall make a repair or replace determination within four hours of notification of a problem.
Para
5.20, 5.20.1
Contractor begins evaluation of system and provides the government a determination within 4 hours of service call.
The contractor shall not deviate from the
4 hour determination schedule. In the event of government caused delays please communicate issues to the
Contracting Officer Representative
(COR).
COR tracks response time and determination notification on service request forms and monthly reports.
Government will seek an equitable price reduction or other adequate consideration for acceptance of nonconforming services.
Replacement of Emergency Diesel
Generator (EDG) will be within 48 hours of replace or repair determination being communicated to the government.
Para 5.20.2 The Contractor will remove the EDG/ATS that needs to be replaced and have a fully operational
EDG/ATS in place within 48 hours of the repair/replace determination. The Contractor provided Process Control Procedure will outline the processes to be followed.
The contractor shall not deviate from the
48 hour replacement schedule. In the event of government caused delays please communicate issues to the
COR.
Contracting Officer Representative tracks response time and determination notification on service request forms and monthly reports.
Government will seek an equitable price reduction or other adequate consideration for acceptance of nonconforming services.
Repair of Emergency Diesel
Generator (EDG) will be within 48 hours of repair or replace determination.
Para 5.20.2 The Contractor will repair the EDG/ATS that within 48 hours of making a repair or replace determination. The Contractor provided Process
Control Procedure will outline the processes to be followed.
The contractor shall not deviate from the
48 hour repair schedule. In the event of government caused delays please communicate issues to the COR.
Contracting Officer Representative tracks response time and determination notification on service request forms and monthly reports.
Government will seek an equitable price reduction or other adequate consideration for acceptance of nonconforming services.
Equipment, Maintenance, and
Delivery Section 1
Section 5
The Contractor will provide all required pre-delivery maintenance, follow the delivery instructions, and include all required submittals with each delivery.
The contractor shall comply with all PWS requirements and communicate to the government if any of the requested performance characteristics cannot be met by system prior to delivery. The government will determine on a case by case basis as to the acceptability of non-conforming supplies.
Contracting Officer Representative and Customer will coordinate deliveries and provide for inspection and acceptance at point of delivery. Any part of the pre-delivery maintenance that reveals non-conformance with the PWS must be communicated prior to removal from Contractors point of origin. Contractor must receive notification from the COR of acceptability of non-conforming supplies prior to removal from point of origin.
Immediate no cost re performance for any EDG/ATS found to be incapable of meeting basic PWS requirements at point of origin.
Government will seek an equitable price reduction, other adequate consideration for acceptance of non-conforming supplies if the contractor communicates variances from the PWS and the
CONTRACTING OFFICER allows for delivery despite non conformance with PWS. The
Government and Contractor will mutually agree to the price reduction or consideration prior to delivery.