Statement of Work Multiple Award Construction Contract (MACC) Indefinite Delivery Indefinite Quantity (IDIQ)

1. INTRODUCTION

The Naval Surface Warfare Center, Corona Division (NSWC Corona) has a requirement for MACC IDIQ to support the construction program at NSWC Corona.

2. BACKGROUND

NSWC Corona’s construction program involves sustainment restoration and modernization, minor construction, new construction and other facility type projects.

3. SCOPE

The Contractor shall provide all labor, materials, equipment, transportation, environmental, architect-engineer (AE) services, and quality controls in order to perform maintenance, sustainment, repair, rehabilitation, energy conservation, environmental, minor construction and lab revitalization program. The Contractor shall perform all facets of the work such as surveying the problem, recommending a solution, and correction of the problem. Work requirements will vary from site to site. This contract is primarily for use at NSWC Corona’s locations (Corona, CA;

Seal Beach, CA; and Fallbrook, CA).

Work performed under this contract will be complex in nature and require multiple disciplines working simultaneously, to include coordination with AE Contractors as necessary.

3.1. Primary Objective

Provide site surveys, work plans, maintenance, repairs, and rehabilitation services on Government installations and facilities.

3.2. Typical Work Requirements

The Contractor shall provide expertise needed to accomplish the required work. Disciplines and related work requirements may include, but are not limited to:

3.2.1. Architectural

Enclosures, shelters, building systems, mobile buildings, chimneys, grout, mortar, concrete, brick, concrete masonry units (CMUs), waterproofing, insulation, caulking and sealants, roofing, gutters, drains, metal decking, joists, siding and exterior surfacing, levelers, docks, ramps, stairs, shelving, windows, doors, painting, finishes, louvers, awnings, shutters, panels, grills, ceilings, acoustical areas, walls, paneling, flooring (conductive and nonconductive), carpeting, tiles, builder’s hardware, signage, metals, woods and plastics, millwork, thermal and moisture protection, playground equipment, fireproofing, equipment systemization layouts, building fixtures and furnishings, and handicap systemization.

3.2.2. AE Design Services

Planning studies, surveying and mapping, soil borings, hydrology reports, geotechnical investigations, project programming documents, requirement development, preparing engineering evaluations, developing project scope, unit guidance or parametric cost estimating, cost evaluation, development of alternatives and economic analysis, analysis of proposed sites for foundations, utilities, access, constraints and identification of environmental issues, concept and site sketches, recommendations on potential utilities impacts, sustainable features, development of design-bid-build drawings and Unified Facilities Guide Specifications, development of design-build drawings and

Unified Facilities Guide Specifications (UFGS), Bid Schedule, Submittal Register, quantity and cost estimates, proposed construction schedule, design analysis and calculations, design documentation report, engineering considerations and instructions report, commissioning, life cycle costing, benefit-cost analyses, economic analysis, and cost estimating services.

3.2.2.1. Drawings

3.2.2.2. Specifications

3.2.2.3. Construction Schedule

3.2.2.4. Design Analysis

3.2.2.5. Independent Technical Reviews

3.2.2.6. Design Documentation Report

3.2.2.7. Engineering Considerations and Instructions Report

3.2.3. Civil

Topographic surveying, grading and earthwork, surface and subsurface storm drainage and drainage control structures, storm water management, erosion and sediment control, clearing and grubbing, paving and surfacing for roads, parking areas and sidewalks, parking layout, pavement markings, traffic control and signage, gates and fencing, curbs and gutters, railroads, dewatering, landscaping, seeding and sodding, riprap, geotechnical investigations, slope stabilization, foundations, borings, trenching, piles and caissons, bridges, spill containment berms, demolition, wetlands delineation, and airfield runways and taxiways.

3.2.4. Electrical

Electrical distribution and network balancing (aerial and underground), transmission lines, poles (telephone and power), towers, ducts, raceways, conduits, tubing, connectors, wires, cable, cable trays, outlet boxes, cabinets and enclosures, supports, fiber optics cable and equipment, manholes, concrete pads, insulators, lightning arrestors, transformers, capacitors, switches, relays, fuses, grounding, lightning protection, cathodic protection, service entrances, panel boards, circuit breakers, motor control centers, special equipment/systems, targeting systems, resistance heating, starters, uninterrupted power supplies, beacons, batteries, generators, solar systems, receptacles, lighting fixtures, lamps, ballasts, equipment connections, special outlets, disconnect switches, splices, terminations, control systems, security systems, intrusion detection systems, utilities monitoring and control systems, and similar micro-processor environmental control systems, audio and visual communication systems, telephone systems, instrumentation systems, and fire detection and alarm systems.

3.2.5. Environmental

Industrial and sanitary sewers, waste treatment facilities, septic tanks with drains, portable toilets wells, water treatment facilities, water distribution systems, potable and fire water supplies, including wells, piping, pumps, valves, sprinklers, water use analyses, leakage analysis, hazardous waste analyses, and disposal of waste products.

3.2.6. Mechanical

Heating, ventilation and air-conditioning systems and components, chillers, refrigerants, cooling towers, air handling equipment, energy conservation, heat transfer surfaces, furnaces, air distribution, valves, pumps and associated piping and ducts; conveying systems, elevators, dumbwaiters, moving walks, box conveyors, hoists and cranes, lifts, escalators with associated electrical and hydraulic controls; incinerators, boilers, material handling systems, dryers, steam lines, transient tubes, shredders, plumbing fixtures, special equipment/systems, sterilization systems, fuel distribution (i.e. propane, natural gas, and slurries), petroleum oil lubricants, storage tanks for fuel, gas, water, and sewage, piping systems, fire suppression (water, chemical, and gas), fuel use and leak analyses, sterilizers, compressed air production and distribution systems, medical and industrial gas distribution systems, exhaust systems, steam systems, pipe insulation, and plumbing systems involving water, solids, and hazardous waste.

3.2.7. Safety

Life safety, fire protection systems, industrial hygiene, inflammatory gases, medical safety and hygiene, asbestos and/or lead based paint evaluation and removal/encapsulation, blast distances, failure mode and effective analyses, Occupational Safety and Hazards Act (OSHA) and American Disability Act evaluations.

3.2.8. Structural

Structural analysis of building systems and ancillary structures (concrete, masonry, steel, etc.), foundations, underwater structures, reinforced concrete, equipment mounting, shock isolation reinforced masonry, wood, steel joists, steel decks, structural steel frame systems, steel bracing, seismic evaluations, steel connections, non-building structures, welding procedures, detailing of structural components and hardened (protective) structures. Non-building structures such as elevated tanks, vertical tanks on ground, horizontal tanks, retaining walls and buried structures. Anchorage and support of mechanical and electrical equipment. Applications of industry building codes and standards.

3.2.9. Other Requirements

Asbestos and/or lead based paint abatement. Demolition and/or temporary removal and reinstallation of supporting elements. Surveys and assessments of systems/equipment.

3.3. All work shall be done in accordance with UFGS.

4. APPLICABLE DOCUMENTS

Work, materials, and equipment shall comply with the most restrictive of local, state, and federal authorities’ codes and ordinances of those plans and specifications. The Contractor is required to adhere to all applicable standards and guidelines specified in the task order. In the absence of named standards, broadly accepted professional standards shall prevail as related to the associated industries within the tasks identified.

Document

Type No./Version Title Date

29 CFR 1910

OSHA Safety and Health Standards for General Industry https://www.osha.gov/laws-regs/regulations/standardnumber/1910

Current

29 CFR 1926

OSHA Safety and Health Regulations for Construction https://www.osha.gov/laws-regs/regulations/standardnumber/1926

Current

EM 385-1-1

US Army Corps of Engineers Safety and Health Requirements

Manual https://www.publications.usace.army.mil/portals/76/publication s/engineermanuals/em_385-1-1.pdf

Current

IBC

International Building Code https://shop.iccsafe.org/codes/2021-international-codes-and-references/2021-international-building-coder.html

Current

FC 1-300-09N

Facility Criteria Navy and Marine Corps Design Procedures https://www.wbdg.org/FFC/DOD/UFC/fc_1_300_09n_2014_c

6.pdf

Current

NFPA 101

Life Safety Code https://www.nfpa.org/codes-and-standards/all-codes-and-standards/list-of-codes-and-standards/detail?code=101

Current

UFC

Department of Defense Unified Facilities Criteria https://wbdg.org/ffc/dod/unified-facilities-criteria-ufc Current

UFGS

Unified Facilities Guide Specifications https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

Current https://www.osha.gov/laws-regs/regulations/standardnumber/1910 https://www.osha.gov/laws-regs/regulations/standardnumber/1910 https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.publications.usace.army.mil/portals/76/publications/engineermanuals/em_385-1-1.pdf https://www.publications.usace.army.mil/portals/76/publications/engineermanuals/em_385-1-1.pdf https://shop.iccsafe.org/codes/2021-international-codes-and-references/2021-international-building-coder.html https://shop.iccsafe.org/codes/2021-international-codes-and-references/2021-international-building-coder.html https://www.wbdg.org/FFC/DOD/UFC/fc_1_300_09n_2014_c6.pdf https://www.wbdg.org/FFC/DOD/UFC/fc_1_300_09n_2014_c6.pdf https://www.nfpa.org/codes-and-standards/all-codes-and-standards/list-of-codes-and-standards/detail?code=101 https://www.nfpa.org/codes-and-standards/all-codes-and-standards/list-of-codes-and-standards/detail?code=101 https://wbdg.org/ffc/dod/unified-facilities-criteria-ufc https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

5. REQUIREMENTS

5.1. Security

Contractors are considered visitors and access to Government facilities or installations is at the discretion of the

Government. The Government reserves the right to rescind access at any time.

Contractors shall comply with all installation badge wearing standards, entry control, emergency and security policies and requirements while on the installation as per the host Physical Security Plan, which will be provided at the task order level.

5.2 Safety

Contractors shall ensure that all work meets Federal and State Occupational Safety and Health Administration

(OSHA) safety standards. The Contractor is responsible for ensuring safe work performance of employees and bears sole responsibility for the safety of its employees. Contractors are expected to take all steps necessary to establish, administer, and enforce safety rules that will meet the current requirement of Federal/State OSHA.

5.3 Environment

Contractors shall ensure their employees receive applicable environmental and occupational health and safety training, and keep up to date on regulatory required specific training for the type of work to be conducted onsite. All onsite Contractor’s personnel, and their subcontractor’s personnel (if applicable), performing tasks that have the potential to cause significant impact shall be competent on the basis of appropriate education, training or experience.

5.4. Work Hours

Normal working hours at all locations are Monday through Friday, 0700 to 1730 (not including Federal or State holidays). Work shall not occur outside those hours unless previously approved by the Contracting Officer, or specified in the task order.

5.5. Contract Minimum/Maximum Value

The minimum/maximum contract value for all orders issued against the contract are identified in the following table.

Minimum Amount Maximum Amount

$500 $42,620,000

6. GOVERNMENT FURNISHED PROPERTY

N/A

7. DELIVERABLES

Deliverables will be determined at the task order level and shall be submitted in accordance with UFGS.