These Special Instructions outline the requirements for vista clearing work along the Blue Ridge Parkway in 2024, with specific environmental and operational constraints. Key restrictions include:
Seasonal work limitations: No vista clearing is permitted in Virginia from April 15th to August 15th, in North Carolina from May 1st to August 15th, and during the entire month of October. Work is prohibited between dusk and dawn. Contractors must submit a proposed cutting schedule at least 14 days prior to starting work, which the Park will review for compliance with natural resource requirements. Payment will be reduced by 50% for cutting unauthorized plants, and vistas not completely cut will not receive partial payment until fully accepted. Additional requirements include leaving cut vegetation on-site to decompose, confining staging and parking to designated areas, and placing traffic signage at work sites.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Blue Ridge Parkway Vista Clearing 2024 Special Instructions
Due to seasonal variations in the environmental compliance regulations affecting Park resources, the following must be adhered to by the Contractor for successful completion of the required work.
1. No vista clearing work shall be performed in the time periods listed as follows:
a. Virginia - April 15th thru August 15th
b. North Carolina- May 1st thru August 15 th
c. No clearing during the month of October
d. Sites with indicated wetlands and/or T&E species safe dates must be cut during the available timeframe. Restrictions due to the available work window shall be considered in the estimates.
2. No vista clearing work shall be performed between dusk and dawn.
3. At least 14 days prior to starting work, the Contractor shall submit a proposed schedule for vista cutting indicating what dates each vista will be cut. The Park will review for compliance with timing of natural resource requirements. The Park may require revision of the schedule to meet these natural resource requirements or elimination of certain vistas from the work.
4. Cutting of plants not identified to be cut per the contract or vista log instructions will result in a
50% reduction in payment for the vista.
5. Vistas not cut completely based on Park inspection will not be paid any partial payment until completed and accepted by the Government. Acceptance requires, but is not limited to:
a. Cutting all vegetation to within 6 to 8 inches above the ground
b. Cutting and removing all plants growing under or within a reserved plant
6. All vegetation cut shall be left on site to decompose.
7. Staging and parking for vehicles, equipment and materials shall be confined to paved overlooks and parking areas. Other areas utilized shall be only as designated approved by the CO and/or
COR.
8. Traffic signage must be in place at work sites to alert drivers on Parkway of activity.