This document is Appendix C of federal contract opportunity A27-0621, containing detailed specifications for a 1500°C two-zone tube furnace system integrated with a glovebox and purification system.

The furnace is intended for sintering and heat treatment of rare-earth-based magnetic alloys, specifically NdFeB sintered magnets. The tube furnace must achieve a maximum working temperature of 1500°C (minimum acceptable 1200°C) with a durable metal alloy tube and an inner diameter of at least 3.15 or 4 inches. The system must achieve and maintain a vacuum level of approximately 10⁻³ Pa (10⁻⁵ torr) during sintering and heat treatment processes at 900–1100°C, and after reaching high vacuum, it must allow controlled backfilling with high-purity argon from an external cylinder to a partial pressure of 1 atmosphere or positive 2 psi. Rapid cooling (quenching) is required after heat treatment, achievable either by transferring samples to a room-temperature cold zone (preferred) or by moving the furnace away along a track with forced-air cooling; therefore, a horizontal rather than vertical tube furnace configuration is mandatory. The sample holder must accommodate 6–10 lab-scale samples per batch, and the overall system length must not exceed 6 meters. Power requirements are 208–240 VAC single phase 50/60 Hz at 6 kVA for the tube furnace and 110–120 VAC single phase 50/60 Hz at 1.5 kVA for the glovebox. The entire system must be NRTL certified.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A27-0621

Appendix C - Specifications

1500 °C Two-Zone Tube Furnace Integrated with Glovebox and Purification System

This tube furnace will be used for the sintering and heat treatment of rare-earth-based magnetic alloys, such as NdFeB sintered magnets. The key specification requirements are below.

Tube Furnace Requirements:

1. The two-zone furnace is preferred to have a maximum working temperature of 1500 °C (minimum acceptable: 1200 °C). A durable metal alloy tube is strongly preferred over mullite, Al₂O₃, or quartz tubes. The inner diameter (ID) of the furnace tube should be at least ~ 3.15 inches or 4 inches.

2. The system must be capable of achieving and maintaining a vacuum level of approximately 10⁻³ Pa (i.e., 10⁻⁵ torr) before and during sintering and heat treatment processes (~900– 1100 °C).

3. After reaching high vacuum (e.g., better than 5 × 10⁻³ Pa), the system should allow backfilling with high-purity argon (Ar) from an external gas cylinder to a controlled partial pressure (such as 1 atm or positive 2 psi). This enables heat treatment to be conducted either under high vacuum or in a partial-pressure Ar atmosphere.

4. Rapid cooling (quenching) after heat treatment is required. This can be achieved either by:

o Transferring the sample to a room-temperature cold zone (preferred).

o or Moving the furnace away from the tube along a track, followed by forced-air cooling (e.g., fan-assisted cooling) Therefore, a horizontal tube furnace configuration is required rather than a vertical one.

The sample holder (tray) should accommodate multiple (e.g., 6–10) lab-scale samples per batch.

The overall length of this system should be shorter than 6m to fit our lab space.

Power : * Tube furnace: 208-240 VAC, single phase, 50/60 Hz, 6 kVA

* Glove box: 110-120 VAC, single phase, 50/60 Hz, 1.5 kVA

The entire system must be NRTL certified.