A21 - RTA-Specs5-W912PM23B0012-CSRM-Wrightsville-Masonboro.pdf
PDF 23 MB Posted
- Attached to
- FY24 Wrightsville Beach CSRM Dredging
- Solicitation number
- W912PM23B0012
About this file
This document provides details for a federal solicitation seeking dredging services. The U.S. Army Corps of Engineers Engineering District Wilmington is soliciting proposals under number W912PM23B0012 for dredging services in Wrightsville Beach, North Carolina as part of a Coastal Storm Risk Management project. Offerors should provide their responses by the date listed on the FedBizOpps website, with work to be completed by December 2024. Dredging services will be required to maintain the beach and shoreline in compliance with the specified technical requirements. Pricing should be submitted on a firm-fixed price basis. This is a small business set-aside solicitation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY24 COASTAL STORM RISK
MANAGEMENT
WRIGHTSVILLE BEACH, NORTH
CAROLINA
RTA SPECIFICATIONS
16-JUNE-2023
Solicitation No. W912PM23B0012 Contract No. W912PM23XXXXX
FY24 CSRM WRIGHTSVILLE BEACH W912PM23B0012 RTA
MASONBORO INLET
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 10 00.10 38 01/13 SUPPLEMENTARY SPECIAL CONTRACT
REQUIREMENTS
01 32 01.00 10 02/15 PROJECT PROGRESS SCHEDULE
01 33 00 05/11 SUBMITTAL PROCEDURES
01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 07/04 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 11/16, CHG 2: 11/21 QUALITY CONTROL
01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 50 00 11/20 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 11/15 TEMPORARY ENVIRONMENTAL CONTROLS
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 94 00 10/18 DUNE STABILIZATION
DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON
35 20 23 04/98 DREDGING AND BEACH-FILL WORK
35 20 23.33 02/22 NATIONAL DREDGING QUALITY MANAGEMENT
PROGRAM - PIPELINE HYDRAULIC DREDGE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 10 00.10 38
SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS
01/13
PART 1 GENERAL
1.1 REFERENCES
1.2 DEPARTMENT OF ARMY MANDATED SECURITY REQUIREMENTS
1.3 SUBMITTALS
1.4 PERFORMANCE AND PAYMENT BONDS
1.5 WATER CONSERVATION
1.6 NOTICE TO MARINERS
1.7 SEAGOING BARGE ACT
1.8 ACCOMMODATIONS AND MEALS FOR INSPECTORS
1.9 RETAINAGE FOR UNTIMELY SUBMISSION OF SUBCONTRACTING REPORTS
1.10 SURVEY DATA
1.11 BEACH SURVEYS AND SURVEY PERSONNEL REQUIREMENTS
1.12 FINAL EXAMINATION AND ACCEPTANCE OF BEACH FILL
1.13 SYSTEM AS-BUILT DRAWINGS
1.14 WORK IN QUARANTINED AREA
1.15 NCDOT SPECIFICATIONS
1.16 DEFINITIONS FOR NCDOT SPECIFICATIONS
1.17 PLANT LOCATION
1.18 PLANT
1.19 PUBLIC CONVENIENCE AND SAFETY
1.19.1 Roads To Be Closed
1.19.2 Storage of Materials
1.20 MAINTENANCE DURING CONSTRUCTION
1.20.1 Maintenance When Work is Suspended
1.20.2 Spilled Materials
1.21 SIGNAL LIGHTS
1.22 PARTNERING
1.23 LOAD RESTRICTIONS
1.24 BARRICADES, DANGER, WARNING, AND DETOUR SIGNS
1.24.1 Removal of Barricades And Warning Signs
1.24.2 Replacement of Signs
1.24.3 Cost of Protective Devices
1.25 PROTECTION OF EXISTING FACILITIES
1.26 CONTRACT AREA AND TRESPASSING
1.27 COORDINATION WITH OTHER CONTRACTORS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 10 00.10 38 Page 1
SECTION 01 10 00.10 38
SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS
01/13
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
NORTH CAROLINA DEPARTMENT OF TRANSPORTATION (NCDOT)
NCDOT Standard Specifications For Roads And Structures
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1110-1-5 Plant Pest Quarantined Area and Foreign Soil Samples
1.2 DEPARTMENT OF ARMY MANDATED SECURITY REQUIREMENTS
The Contractor shall be required to comply with the following security requirements mandated by the Department of the Army:
Short-term employees (working on site less than or equal to 6 months): If a criminal history is found, the employee MAY not be allowed to work at the project site at the sole discretion of the Government.
Long-term employees (working on site more than 6 months):
ALL of the following is required WHEN REPORTING FOR WORK -
a) A completed OMB Form No. 3206-0182 (also designated as Optional Form 306).
b) A completed OMB Form No. 3206-0191 (also designated as Standard Form 85P).
c) A resume.
The Government will use all provided information to perform a National Agency Check and Inquiries (NACI) check and will pay the required fee.
The Contractor shall be responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer or his/her designated representative. All prescribed identification shall immediately be delivered to the Contracting Officer or his/her designated representative for cancellation upon the release of any employee.
(End of Clause)
SECTION 01 10 00.10 38 Page 2
1.3 SUBMITTALS
Government approval is required for submittals with a "G, A" designation;
submittals not having a "G, A" designation are for information only. When used, a designation following the "G, A" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
Beach Surveys
SD-02 Shop Drawings
Beach Surveys; G
SD-07 Certificates
U.S. Coast Guard Certification
SD-11 Closeout Submittals
SYSTEM AS-BUILT DRAWINGS; G, A
1.4 PERFORMANCE AND PAYMENT BONDS
Each bidder shall include his premiums for performance and payment bonds under the appropriate, "Performance and Payment Bonds" contract line item of the Bidding Schedule. Payment to the Contractor therefore, shall not exceed the bid price and shall be made in accordance with the Contract Clause entitled "PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS." Any additional amount bid in excess of the actual bond premium will be included in the final pay estimate for this contract.
(End of Clause)
1.5 WATER CONSERVATION
Water is one of our valuable natural resources. Accordingly, the Contractor shall be judicious in its use in the performance of the work as specified. Water needed for compaction of roadway and/or foundation materials, and dust control shall be obtained from uncontrolled stream flow instead of potable supply sources to the extent available and suitable as determined by the Contracting Officer or his/her designated representative.
(End of Clause)
1.6 NOTICE TO MARINERS
(a) The Contractor shall coordinate Local Notice to Mariners with the U.S. Coast Guard, and provide dredging schedule and location by shoal/tangent/section by contacting USCG Sector North Carolina Waterways Management.
(b) Should the Contractor, during dredging operations, encounter any objects on the channel bottom which could be a hazard to navigation, the Contractor shall notify the Coast Guard immediately as to the location of said object and any other information necessary for a Notice to Mariners. The Contractor shall provide copies of this information to the
SECTION 01 10 00.10 38 Page 3
Contracting Officer or his/her designated representative.
USCG Sector North Carolina Waterways Management, (910) 251-4525.
USCG Fifth District Aids to Navigation, (757) 398-6230.
1.7 SEAGOING BARGE ACT
(1979 OCE)
The Seagoing Barge Act (46 U.S.C. et sq.) applies to this project. In the event the low bidder contemplates using plant that requires U.S. Coast Guard certification to comply with the Act, the low bidder shall within ten (10) calendar days after bid opening submit a copy of said certificate to the Contracting Officer or his/her designated representative. Failure to produce the certificate within the required time shall subject the bidder to a determination of nonresponsibility.
(End of Clause)
1.8 ACCOMMODATIONS AND MEALS FOR INSPECTORS
(a) The Contractor shall furnish regularly to inspectors, for office purposes and sleeping purposes, when applicable, a suitable separate room onboard the dredge or other craft upon which they are employed. If no suitable office space is available thereon, the Contractor shall furnish suitable alternate accommodations ashore at a location approved by the Contracting Officer or his/her designated representative and furnish suitable transportation between the alternate accommodations and the dredge or other craft upon which they are employed.
(b) If the Contractor maintains an establishment for the subsistence of his own employees, he shall, when required, furnish to inspectors employed on the work, and to all Government agents who may visit the work on official business, meals of a quality satisfactory to the Contracting Officer or his/her designated representative. The meals furnished shall be paid for by the individual consuming the meal at a rate commensurate with the basic Government subsistence rate of: $7.00 Breakfast; $11.00 Lunch; $23.00 Dinner.
(End of Clause)
1.9 RETAINAGE FOR UNTIMELY SUBMISSION OF SUBCONTRACTING REPORTS
(a) In accordance with Contract Clause 52.219-9, Small Business Subcontracting Plan, and 52.219-16, Liquidated Damages - Subcontracting Plan, retainage will be withheld from progress payments in an amount sufficient to protect the Government's ability to assess liquidated damages in accordance with Clause 52.219-16 for the contractor's failure to timely submit Standard Form 294, Subcontracting Report for Individual Contracts, and Standard Form 295, Summary Subcontract Report, reports.
(b) The retainage will be determined in accordance with the following formula:
Total dollar amount for subcontracting to small business multiplied by percentage of actual progress on the contract shall be withheld from the next progress payment due after the Contractor fails to submit a required report. If one or more reports have been submitted before such failure, formula for determining the amount of retainage will be adjusted by
SECTION 01 10 00.10 38 Page 4 deducting any amounts reported as subcontracted to small business from the total dollar amount proposed to be subcontracted and the difference multiplied by the percentage of actual progress.
(c) Subcontracting plans are not required--
(1) For contracts or contract modifications that will be performed entirely outside of any State, territory, or possession of the United States, the District of Columbia, and the Commonwealth of Puerto Rico; or
(2) For modifications to contracts that do not contain the clause 52.219-8, Utilization of Small Business Concerns (or equivalent prior DAR, FPR, or NASA clauses); e.g., contracts awarded before Pub. L.
95-507 and which are within the scope of the contract.
(End of Clause)
1.10 SURVEY DATA
The Contractor shall maintain complete and accurate field notes, sketches, recordings and computations required in establishing the necessary horizontal and vertical control. All survey data shall be recorded in accordance with accepted standards and as approved by the Contracting Officer or his/her designated representative. All the above data shall be available at all times during the progress of the work for ready examination and use by the Contracting Officer or his/her designated representative. Upon request of the Contracting Officer or his/her designated representative, the Contractor shall furnish a copy of above survey data.
(End of Clause)
1.11 BEACH SURVEYS AND SURVEY PERSONNEL REQUIREMENTS
(a) Survey personnel. All quantity surveys required by the Contractor, except those for any periods for which progress payments are requested, shall be made by personnel of a professional engineering and/or surveying firm experienced in the practice of such work including Global Positioning Systems (GPS) surveys that is independent of the Contractor.
The survey personnel shall have the following minimum qualifications.
(1) Each party chief shall be a Professional Land Surveyor and shall be proficient in the operation of precise and semi-precise instruments. They shall be capable of running horizontal and vertical control of 2nd order accuracy. In the event it is considered advantageous to employ a party chief who is not a Professional Land Surveyor, detailed qualifications of the individual shall be submitted to the Contracting Officer for review and approval.
(2) Instrument men shall be proficient in the operation of precise and semi-precise instruments including transit, level, and alidade, and shall prepare all survey notes in a firm and legible manner.
(3) Surveying technicians shall be familiar with all phases of surveys and the North Carolina State plane coordinate system. Also they shall be well versed in the computation and adjustment of horizontal and vertical control of 2nd and 3rd order survey.
SECTION 01 10 00.10 38 Page 5
(b) Beach Surveys to be furnished by the Contractor as follows:
(1) Pre-placement surveys shall be made of the entire beach baseline (onshore and offshore) area. Such surveys shall be scheduled so that field notes and computations (to include all required deliverables) can be furnished to the Contracting Officer or his/her designated Representatives a minimum of 10 working days in advance of the initiation of dredging and placement of beach fill so that control of quantities and adjustments to the fill template may be made if necessary. The sections shall be taken at intervals of 100 feet and at right angles to the longitudinal alignment of the Corps of Engineers project baseline or as otherwise directed. All sections shall extend from the Corps of Engineers project baseline, as indicated on the drawings to a minimum distance of 1,500 feet seaward of baseline. Elevations and ocean soundings shall be taken generally at 25-foot intervals and at all break points. All data shall be recorded in feet and shall be referenced to NAD 1983 horizontal datum and NAVD 1988 vertical datum.
(2) Post-placement surveys shall be made as soon as possible after placement of the fill but not later than 72 hours after completion of any 1500-foot segment of work. The Contractor shall use the same stations that were used in the preplacement surveys. Elevations and ocean soundings shall be taken at 25-foot intervals and at all break points. All sections shall extend from the baseline to a distance offshore not less than 1,500 feet or as needed to indicate the intersection of beach fill with the preplacement bottom profile. In the event the first examination shows additional work is required in an area prior to its acceptance, additional elevations and/or soundings will be required only in the area where additional work is required. Elevations and soundings will continue to be taken until such area is acceptable. The Contractor shall submit the postplacement survey data to the Contracting Officer or his/her designated representative. The Contracting Officer or his/her designated representative will review the postplacement survey data for acceptance within 10 working days.
(3) Post construction surveys shall be made of the entire beach fill limits (onshore and offshore) following the completion of all the beach fill placement. Such surveys shall be scheduled so that field notes and computations (to include all required deliverables) can be furnished to the Contracting Officer or his/her designated Representatives within 10 working days after the final placement of beach fill as part of this contract is complete. The sections shall be taken at intervals of 100 feet and at right angles to the longitudinal alignment of the Corps of Engineers project baseline or as otherwise directed. All sections shall extend from the Corps of Engineers project baseline, as indicated on the drawings to a minimum distance of 1,500 feet seaward of baseline.
Elevations and ocean soundings shall be taken generally at 25-foot intervals and at all break points. All data shall be recorded in feet and shall be referenced to NAD 1983 horizontal datum and NAVD 1988 vertical datum.
(c) Unless waived in each specific case, all surveys made by the Contractor shall be conducted in the presence of a representative of the Contracting Officer or his/her designated Representatives.
(d) The Government reserves the right to make such surveys as necessary for verification of surveys made by the Contractor.
(e) Deliverables.
SECTION 01 10 00.10 38 Page 6
(1) The Contractor shall furnish to the Government copies of all surveys taken as required on a CD-ROM disk or via electronic mail. The points along the beach survey shall be presented in ASCII data files and in x,y,z coordinates or easting, northing, elevation. Contractor shall also submit a breakline file, if required by Contracting Officer and/or his/her designated representative. The survey information will be used by the Government to control and make adjustments to the volume of beach fill placed along the beach and for measure and payment purposes.
(2) In addition to the above requirements, the Contractor shall compute beach fill volumes for the contract typical sections based on the preplacement surveys as described hereinabove. The Contractor shall also compute beach fill volumes for construction template with a +0.5 foot vertical tolerance and a -0.5 foot vertical tolerance. Paper plots of the profiles along with digital records of the surveys and computations shall be furnished to the Government.
(3) Metadata Record. A FGDC compliant metadata record for all surveys shall be created using Corpsmet 95 metadata software. Corpsmet 95 metadata software can be downloaded free of charge at http://corpsgeo1.usace.army.mil. Appropriate information shall be entered in all required fields. The metadata record shall be submitted on compact disc with all other digital files.
1.12 FINAL EXAMINATION AND ACCEPTANCE OF BEACH FILL
(a) After the completion of each continuous 500-foot length of beach work or any remaining length less than 500 feet which would complete the entire work and in the opinion of the Contracting Officer or his/her designated representative will not be subject to damage by further operations under the contract, the Contracting Officer or his/her designated representative shall thoroughly examine the work by comparing the postplacement surveys with the design template. Should this examination disclose deficiencies of material in the design section, the Contractor shall be required to place additional material at the contract unit price until the fill requirements are met, or if examination shows material has been deposited elsewhere than in places designated or approved by the Contracting Officer or his/her designated representative, the Contractor may be required to remove such misplaced material and deposit where directed at his expense. The Contracting Officer or his/her designated representative shall be notified when soundings and/or surveys are to be made and will be permitted to accompany the survey party. When the beach fill area is found to be in a satisfactory condition, it will be accepted finally.
(b) Final acceptance of the whole or part of the work and the deductions or corrections of deductions made thereon will not be reopened after having once been made, except on evidence of collusion, fraud, or obvious error, and the acceptance of a completed section shall not change the time of payment of the retained percentage of the whole or any part of the work.
1.13 SYSTEM AS-BUILT DRAWINGS
(a) The Contractor shall be responsible for maintaining in good condition one set of reproducible as-built drawings and three copy sets.
Drawings shall be "D" 34 by 22 inches, drawn to the same scale as the contract drawings, with title block similar to the contract drawings.
SECTION 01 10 00.10 38 Page 7
Reproducible drawings shall be on mylar film. The Contractor shall keep a careful and neat record of all deviations, field changes and modifications from the original contract drawings which are made to each phase of construction as the work progresses. The Contractor is responsible for noting all changes and corrections on these prints promptly as in-place construction activities occur, but in no case less often than on a weekly basis. In addition to the above, the following shall be included:
(1) Actual location of all Contractor installed subsurface utility lines. Type of materials actually installed, major sizes of lines, etc. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered or obscured, the record drawings shall show, by offset dimensions to two permanently fixed surface features, both ends of each run and each change in direction. Valves, splice boxes and similar appurtenances shall be located by dimensions along the utility run from a reference point.
The average depth below the surface of each run shall also be recorded.
(2) Any shop drawings which constitute part of the design shall be included with the record drawings.
(3) The manufacturer and model number of all major items of equipment shall be shown on the record drawings.
(4) Upon completion of all construction, the Contractor will delete by notation all references to features not constructed.
(b) These annotated prints shall be certified as to their correctness by the signature of the Contractor and turned over to the Contracting Officer or his/her designated representative not later than ten (10) days after final acceptance of the work by the Government.
Marked up prints shall be reviewed for approval by the Contracting Officer or his/her designated representative and returned for corrections as necessary.
(End of Clause)
1.14 WORK IN QUARANTINED AREA
USACE and the U.S. Department of Agriculture (USDA) have a compliance agreement requiring measures to prevent the spread of certain plant pests that may be present in the soil (USACE ER 1110-1-5 ). Major portions of all southeastern states are in a quarantine area for such pests, including the imported fire ant. In addition, adjacent states to the north have introduced infestations resulting from movement of soil from infested southeastern states. The Contractor shall thoroughly clean all construction equipment and tools at the previous job site in a manner that ensures that these implements are free from residual soil, egg deposits from plant pests, noxious weeds, and plant seeds. Equipment shall be cleaned using water under pressure, and hand tools shall be thoroughly cleaned by brushing or other means to remove all soil. In addition, all construction equipment and hand tools used for this USACE contract shall be thoroughly cleaned by the Contractor before they are removed from this job site. The Contractor shall consult with the USDA jurisdictional office for additional cleaning requirements that may be necessary.
SECTION 01 10 00.10 38 Page 8
1.15 NCDOT SPECIFICATIONS
The North Carolina Department of Transportation ( NCDOT) "Standard Specifications for Roads and Structures English," (hereinafter referred to as the Standard Specifications) applies to this work when so referenced.
(End of Clause)
1.16 DEFINITIONS FOR NCDOT SPECIFICATIONS
Wherever in the North Carolina Department of Transportation "Standard Specifications for Roads and Structures" or on the drawings the following terms are used, the intent shall be as indicated below unless otherwise modified within the specifications:
State - - - - - - - - - - - - - - - - - U. S. Government Department or Department of Transportation - - - - - - - - - - - Corps of Engineers Engineer or Chief Engineer- - - - - - - Contracting Officer, Corps of Engineers Materials and Test Unit - - - - - - - - Corps of Engineers Division of Highways- - - - - - - - - - Corps of Engineers Board or Board of Transportation- - - - Corps of Engineers
Where NCDOT materials and test unit requirements are referenced in these specifications, they shall be taken as such and not Corps of Engineers Standards unless otherwise stated.
(End of Clause)
1.17 PLANT LOCATION
The Contractor's plant shall be arranged and located in areas approved by the Contracting Officer or his/her designated representative. This requirement includes the construction plant; piping; barges; boats;
offices; shop and storage buildings; housing facilities and all other equipment and materials needed to construct the project.
1.18 PLANT
(a) The Contractor agrees to keep on the job sufficient plant to meet the requirements of the work. The plant shall be in satisfactory operating condition, and capable of safely and efficiently performing the work as set forth in these specifications, and the plant shall be subject to inspection by the Contracting Officer or his/her designated representative at all times. The plant listed on the Plant and Equipment Schedule, Section 00100, contract clause 52.0000-4036, is the minimum which the Contractor agrees to place on the job unless otherwise determined by the Contracting Officer or his/her designated representative, and its listing thereon is not to be construed as an agreement on the part of the Government that it is adequate for the performance of the work.
(b) Dredging shall be by ocean certified hydraulic pipeline dredge.
(c) All pipelines for hydraulic machines must be kept in good
SECTION 01 10 00.10 38 Page 9 condition at all times and any leaks or breaks along their length must be promptly and properly repaired.
(d) No reduction in the capacity of the plant employed on the work shall be made except by written permission of the Contracting Officer or his/her designated representative. The measure of the "capacity of the plant" shall be its actual performance on the work to which these specifications apply.
(End of Clause)
1.19 PUBLIC CONVENIENCE AND SAFETY
1.19.1 Roads To Be Closed
The Contractor shall obtain the Contracting Officer's approval before closing any roads. Barricades, danger, warning and detour signs, as required, shall be erected before closing any roads.
1.19.2 Storage of Materials
Materials and equipment shall not be stored within roadway rights-of-way or in such a manner as to pose possible danger or obstruction to the traveling public.
(End of Clause)
1.20 MAINTENANCE DURING CONSTRUCTION
The Contractor shall be responsible for maintaining all barricades, danger, warning, and detour signs and lights as specified hereinafter.
When no pay item for such maintenance is shown in the Bidding Schedule, the cost of maintenance shall be included in the price bid for other pay items, and no separate payment will be made.
1.20.1 Maintenance When Work is Suspended
If construction is suspended for any reason, the Contractor shall place the work in such condition as the Contracting Officer or his/her designated representative directs, before suspension, and shall maintain it in a condition satisfactory to the Contracting Officer or his/her designated representative throughout the period of the suspension.
1.20.2 Spilled Materials
The Contractor shall not allow spilled materials to remain on the beach.
Spillage sufficient to create a hazard shall be removed immediately.
(End of Clause)
1.21 SIGNAL LIGHTS
The Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Department of the Army and the Coast Guard governing lights and day signals to be displayed by towing vessels, tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipes or vessels involved in submarine or bank protection operations. The Contractor must also be in accordance with those regulations governing lights to be
SECTION 01 10 00.10 38 Page 10 displayed on dredge pipeline and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel and the passing by other vessels of floating plant working navigable channels, as approved by the Secretary of the Army and Commandant, U.S. Coast Guard.
(End of Clause)
1.22 PARTNERING
In order to most effectively accomplish this contract, the Government proposes to form a cohesive partnership with the Contractor and its subcontractors. This partnership would strive to draw on the strengths of each organization in an effort to achieve a quality project done right the first time, within budget and on schedule. Integral to the partnership would be a joint Contractor/Government effort to settle any disputes that may arise without costly and time consuming litigation. To that end, a non-binding procedure such as the Alternate Dispute Resolution process could be developed and agreed upon by both parties when it is determined to be necessary. This partnership would be bilateral in make-up and participation will be totally voluntary. Any cost associated with developing this partnership will be agreed to by both parties and will be shared equally with no change in contract price.
(End of Clause)
1.23 LOAD RESTRICTIONS
The Contractor shall comply with all legal load restrictions in the hauling of materials on public roads beyond the limits of the project. A special permit will not relieve the Contractor of liability for damage which may result from such hauling. The Contractor shall not operate equipment of such weight or so loaded as to cause damage to drainage structures or the roadway, or to any other type of improvement, either completed or under construction. Hauling of materials over the existing surface shall be limited as directed, and in no case shall legal load limits be exceeded unless permitted in writing. The Contractor shall repair, at his own expense, all damage to the work caused by his equipment.
(End of Clause)
1.24 BARRICADES, DANGER, WARNING, AND DETOUR SIGNS
The Contractor shall provide, erect, and maintain all necessary traffic control devices in substantial conformance to "Manual on Uniform Traffic Control Devices for Streets and Highways" (latest edition) as published by the U.S. Department of Transportation, Federal Highway Administration, and available from AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO), U. S. DEPARTMENT OF TRANSPORTATION (DOT). This requirement shall include flagman as shown in the manual when necessary and the use of electric flashers as conditions of construction may require during hours of darkness. The Contractor shall take all necessary precautions for protection of the work and for the safety of the public at or near the site of construction. Signing, barricades, lights, and other devices shall be well maintained and repositioned or removed as the progress of the work requires. No substandard, poorly maintained device will be acceptable. Particular attention shall be given to the following:
SECTION 01 10 00.10 38 Page 11
1.24.1 Removal of Barricades And Warning Signs
As soon as construction advances to the extent that temporary barricades, and signs such as "Detour", "One Way Traffic," etc. are no longer needed to inform the traveling public, such signs shall be removed promptly.
1.24.2 Replacement of Signs
When new work is necessary during any period of construction or maintenance, necessary signs shall be replaced as are needed to adequately warn and protect the public in accordance with the provisions outlined above. As soon as the project has been accepted for maintenance, all temporary barricades and warning signs shall be removed promptly.
1.24.3 Cost of Protective Devices
Unless otherwise shown in the Bidding Schedule, the cost of furnishing, erecting, maintaining, and removing protective devices will not be paid for as separate bid items. Where the Contractor is required to perform any of these functions, the cost thereof shall be included in the overall bid submitted. Ownership of the temporary warning devices shall remain with the Contractor provided the devices are removed promptly after completion of the work as specified above. If such warning devices are left in place for more than 30 days after the specified time for removal, the Government shall have the right to remove such devices and to claim possession thereof.
(End of Clause)
1.25 PROTECTION OF EXISTING FACILITIES
The Contractor will not be responsible for any alterations to existing structures or utilities except those made by him for his convenience. The Contractor shall protect all existing structures, including bridges, roadway embankments, utilities, jetties and improvements from damage, and, in the event of damage as a result of his operations, the Contractor shall be responsible for their repair, restoration, or for all cost of damage resulting therefrom. In addition, the Contractor shall be responsible for any damage to bridge, jetty or culvert structures or railway embankments or track caused by the unauthorized excavation or excavation beyond the project dimensions shown on the plans. If the Contractor elects to have alterations made to any existing structure, utility or other improvements for his convenience, he shall make arrangements with the owner of the facility for such alterations and the agreement shall be reviewed and approved by the Contracting Officer or his/her designated representative prior to their alteration.
(End of Clause)
1.26 CONTRACT AREA AND TRESPASSING
Property owners have signed easements which will allow the Contractor to enter and perform the work required by these specifications upon all land lying within the right-of-way limits. The Contractor's operation shall be confined solely to those areas for which permission has been granted by the owners to enter. The Contractor shall not inflict damage upon land outside the contract area by unwarranted entry upon, passage through, or disposal of material on such land. The Contractor may make a separate agreement with any other party, regarding the use of, or right to, lands
SECTION 01 10 00.10 38 Page 12 or facilities outside the contract area. If such an agreement is made, it shall be in writing and a copy shall be furnished the Contracting Officer or his/her designated representative. The Contractor shall hold and save the Government, its officers, and agents free from liability of any nature or kind arising from any trespassing or damage occasioned by his operations.
(End of Clause)
1.27 COORDINATION WITH OTHER CONTRACTORS
Other Contractors may be working in the vicinity during the time period of this contract. The Contractor shall coordinate the contract operations with other Contractors performing work in the area as needed to avoid conflicts and delays. As a minimum the Contractor shall schedule weekly or as necessary coordination meetings between the Contractor, Contracting Officer or his/her designated representative, local Town officials and their Contractors that are working within the project area to discuss the progress of work and current activities.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 10 00.10 38 Page 13
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01.00 10
PROJECT PROGRESS SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
PART 2 PRODUCTS
2.1 SOFTWARE
2.1.1 Government Default Software
2.1.2 Contractor Software
2.1.2.1 Primavera
2.1.2.2 Other Than Primavera
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.2.1 Level of Detail Required
3.2.2 Activity Durations
3.2.3 Procurement Activities
3.2.4 Mandatory Tasks
3.2.5 Government Activities
3.2.6 Standard Activity Coding Dictionary
3.2.6.1 Workers Per Day (WRKP)
3.2.6.2 Area of Work Coding (AREA)
3.2.6.3 Modification Number (MODF)
3.2.6.4 Bid Item Coding (BIDI)
3.2.7 Contract Milestones and Constraints
3.2.7.1 Project Start Date Milestone and Constraint
3.2.7.2 End Project Finish Milestone and Constraint
3.2.7.3 Interim Completion Dates and Constraints
3.2.7.3.1 Start Phase
3.2.7.3.2 End Phase
3.2.8 Calendars
3.2.9 Open Ended Logic
3.2.10 Default Progress Data Disallowed
3.2.11 Out-of-Sequence Progress
3.2.12 Added and Deleted Activities
3.2.13 Original Durations
3.2.14 Leads, Lags, and Start to Finish Relationships
3.2.15 Retained Logic
3.2.16 Percent Complete
3.2.17 Remaining Duration
3.2.18 Early Completion Schedule and the Right to Finish Early
3.3 PROJECT SCHEDULE SUBMISSIONS
SECTION 01 32 01.00 10 Page 1
3.3.1 Initial Project Schedule Submission
3.3.2 Periodic Schedule Updates
3.4 SUBMISSION REQUIREMENTS
3.4.1 Data
3.4.2 Network Diagram
3.4.2.1 Continuous Flow
3.4.2.2 Project Milestone Dates
3.4.2.3 Critical Path
3.5 WEEKLY PROGRESS MEETINGS
3.6 REQUESTS FOR TIME EXTENSIONS
3.6.1 Justification of Delay
3.6.2 Time Impact Analysis (Prospective Analysis)
3.6.3 Fragmentary Network (Fragnet)
3.6.4 Time Extension
3.6.5 Impact to Early Completion Schedule
3.7 FAILURE TO ACHIEVE PROGRESS
3.7.1 Artificially Improving Progress
3.7.2 Failure to Perform
3.7.3 Recovery Schedule
3.8 OWNERSHIP OF FLOAT
3.9 TRANSFER OF SCHEDULE DATA INTO RMS/QCS
3.10 PRIMAVERA P6 MANDATORY REQUIREMENTS
SECTION 01 32 01.00 10 Page 2
SECTION 01 32 01.00 10
PROJECT PROGRESS SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G
Initial Project Schedule; G
Periodic Schedule Update; G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting requirements of this specification.
SECTION 01 32 01.00 10 Page 3
2.1.1 Government Default Software
The Government intends to use Primavera P6 and/or Microsoft Project Professional 2016.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required SDEF file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
2.1.2.2 Other Than Primavera
If the contractor chooses software other than Primavera P6 or Microsoft Project Professional 2016, that is compliant with this specification, the contractor must request permission from the Government to use the software prior to submission of associated submittals.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM)
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.2.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
- Dredging sequencing
SECTION 01 32 01.00 10 Page 4
- Dredging plant(s) type, size, and anticipated daily production rate(s)
- Environmental windows to include applicable mobilization and demobilization of equipment to include but not limited to pipeline
- Acceptance Sections (by Reach per contract drawings and/or contractor requested areas approved by the Government)
- Mobilization and demobilization durations
- Minimum of one activity per CLIN
- Disposal Area Work (if applicable)
- Submitted schedule timeline calendar days for each month matches the calendar days per month for the respective year
3.2.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.2.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.2.4 Mandatory Tasks
Include the following activities/tasks, if applicable, in the initial project schedule and all updates f or each r espect i ve dr edge ar ea or r each.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each to include but not limited to QCP, APP, and EPP).
b. Acceptance Sections (as approved by Govt)
c. Placement Area & Spillway Survey and Inspections - Pre-Dredge
d. Placement Area & Spillway Survey and Inspections - Post-Dredge
e. Beach Placement Inspection w/ Agencies - Pre-Dredge
f. Beach Placement Inspection w/ Agencies - Post-Dredge
g. Mobilization
h. Demobilization
3.2.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: environmental permit approvals by State regulators, inspections, surveys (before dredge (B/D) and after dredge (A/D)) and Notice to Proceed (NTP) for phasing requirements.
SECTION 01 32 01.00 10 Page 5
3.2.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil .
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 AREA 4 Area of work (Government approved Acceptance Section)
3 MODF 6 Modification Number
4 BIDI 6 Bid Item (CLIN)
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.2.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.2.6.2 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the Govt approved Acceptance Section in which the activity occurs.
Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.
3.2.6.3 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.2.6.4 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs. An activity can have only one BIDI (CLIN) Code.
SECTION 01 32 01.00 10 Page 6
3.2.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or effect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.2.7.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.2.7.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.2.7.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates (to include applicable Environmental Windows) to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.2.7.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.2.7.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.2.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, Environmental Windows, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop Seasonal Calendar(s) and assign to seasonally affected activities as applicable.
SECTION 01 32 01.00 10 Page 7
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated adverse weather delay work days provided in the Special Contract Requirements.
Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends .
3.2.9 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.2.10 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
3.2.11 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer.
Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.2.12 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
3.2.13 Original Durations
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.2.14 Leads, Lags, and Start to Finish Relationships
Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.
a. Leads (negative lags) are prohibited.
SECTION 01 32 01.00 10 Page 8
b. Start to Finish (SF) relationships are prohibited.
3.2.15 Retained Logic
Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.
3.2.16 Percent Complete
Update the percent complete for each activity started,…