SEE ADDENDUM
(No Collect Calls)
W90VN920R0038 29-Jun-2020
b. TELEPHONE NUMBER
315-763-5698
8. OFFER DUE DATE/LOCAL TIME
01:00 PM 29 Jul 2020
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W90VN99. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
MS. CHONG, HYE-YONG
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
0011490917
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED ORX
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
411TH CONTRACTING SUPPORT BRIGADE, KOREA
RCO DAEGU, UNIT #15682
APO AP 96218-5682
UNITED STATES
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE W91QHB 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
CDR, MEDDAC-K
CDR, MEDDAC-K
UNIT: 15281
APO AP 96205-5281
KOREA, SOUTH
TEL: 315-737-1618 FAX:
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$41,500,000
NAICS:
511210
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF47
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W90VN920R0038
Section SF 1449 - CONTINUATION SHEET
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 12 Months UPS Maintenance Service
FFP
The Contractor shall provide all necessary resources for this requirement in accordance with (IAW) Performance Work Statement (PWS) and terms and conditions of this contract contained herein.
Base Period: 10 August 2020 thru 09 August 2021 FOB: Destination
PURCHASE REQUEST NUMBER: 0011490917
PSC CD: D310
NET AMT
0002 2 Each Semi-Annual Preventative Maintenance
FFP
of UPS Systems IAW Paragraph 4 in PWS Base Period: 10 August 2020 thru 09 August 2021 FOB: Destination
PURCHASE REQUEST NUMBER: 0011490917
Contractor Manpower Report (CMR)
FFP
CMR requirement must be reported by 31 October of each calendar year during the life of the contract. See Para. 8. of PWS for CMR requirement herein. NOTE: Not to exceed 20 Man hours for data collection and report.
FOB: Destination
Estimated War Hazard Losses
FFP
is zero (0)
1001 12 Months OPTION UPS Maintenance Service
FFP
The Contractor shall provide all necessary resources for this requirement in accordance with (IAW) Performance Work Statement (PWS) and terms and conditions of this contract contained herein.
Base Period: 10 August 2021 thru 09 August 2022
1002 2 Each OPTION Semi-Annual Preventative Maintenance
FFP
of UPS Systems IAW Paragraph 4 in PWS Base Period: 10 August 2021 thru 09 August 2022
OPTION Contractor Manpower Report (CMR)
FFP
CMR requirement must be reported by 31 October of each calendar year during the life of the contract. See Para. 8. of PWS for CMR requirement herein. NOTE: Not
OPTION Estimated War Hazard Losses
FFP
2001 12 Months OPTION UPS Maintenance Service
FFP
The Contractor shall provide all necessary resources for this requirement in accordance with (IAW) Performance Work Statement (PWS) and terms and conditions of this contract contained herein.
Base Period: 10 August 2022 thru 09 August 2023
2002 2 Each OPTION Semi-Annual Preventative Maintenance
FFP
of UPS Systems IAW Paragraph 4 in PWS Base Period: 10 August 2022 thru 09 August 2023
OPTION Contractor Manpower Report (CMR)
FFP
CMR requirement must be reported by 31 October of each calendar year during the life of the contract. See Para. 8. of PWS for CMR requirement herein. NOTE: Not
OPTION Estimated War Hazard Losses
FFP
SPECIAL NOTE
NOTICE TO BE INSERTED IN LOCAL SOURCE REQUIREMENTS:
1. All sources may submit a proposal or quote as applicable. However, the Republic of Korea (ROK)-United States (U.S.) Status of Forces Agreement (SOFA), precludes the U.S. Government from granting Invited Contractor or Technical Representative status to any offeror, for this requirement. All sources submitting a proposal or quote, as applicable, including U.S. sources, must already have, or obtain the requisite business licenses directly from the ROK Government, and conduct business in accordance with all applicable ROK laws, including but not limited to, rules and policies regarding labor, taxation, and immigration. Any contractor not already doing business in Korea as a local source, must submit adequate verification in its initial proposal or quote, that it has the requisite authorization and capacity to compete for the requirement as a local source, and to perform the contract as a local source. If an initial proposal does not fully demonstrate this authorization and capacity, it will not be further considered for award. Whether an offeror qualifies as a local source shall be determined by the Contracting Officer.
2. LOCAL CONTRACTORS:
The proposed acquisition will be limited to local contractors. All required material, labor, transportation, and facilities and these services are available locally. There is nothing inherently difficult about the project that requires the presence of invited contractors.
3. The Price Proposal should be Korea Won (₩).
4. The following quantities of each CLIN are estimated because it cannot predetermine the precise quantities of service. Individual delivery order will be issued based on actual quantities provided from Requiring Activity (RA).
PWS
PERFORMANCE WORK STATEMENT
for
Uninterruptible Power Supply (UPS) Maintenance Service 65th MED BDE EOC at Camp Carroll
1. GENERAL: The Contractor shall provide all personnel, tools, equipment, supplies, transportation, and other items including replacement of hardware/battery or services necessary for semi-annual preventative maintenance and repair of Uninterruptible Power Supply (UPS) system at 65th MED BDE Emergency Operation Center (EOC) in Camp Carroll building 710.
1.1. The Contractor shall provide 24/7 technical support and 8 hours response time to onsite troubleshoot. The hardware/parts replacements shall be supplied by the contractor and completed within 4 hours of determining that part replacement is required.
1.2. The Contractor shall provide 24-hour emergency maintenance restoration due to the critical nature of the network and medical servers protected by this UPS system that provide medical services to all service members and their families throughout the Korea. Also the Contractor shall provide semi-annual preventive maintenance services.
The services must performed by an American Power Corp authorized service contractor with proper certifications to service the APC Symmetra UPS systems located in the 65th MED BDE EOC in Camp Carroll Building 710.
2. CONTRACTOR QUALIFICATION: The Contractor must be an APC UPS authorized dealer in Korea to conduct the UPS maintenance business in USFK.
2.1. The Contractor must have an APC UPS service license in Korea and submit certificate.
2.2. The Contractor shall maintain the service license and a certification from APC (American Power Corp) to perform UPS maintenance service.
2.3. The Contractor personnel shall have a minimum one (1) year experience with preventative maintenance and repair of APC UPS in medical environment or similar service relevant to this requirement.
2.4. The Contractor shall ensure employees have a current and valid driver’s license before allowing the employee to operate a contractor-owned vehicle on the base. A copy of all licenses shall be provided to the Contracting Officer Representative (COR)/Contracting Officer within ten (10) days after contract award.
2.5. All personnel employed by the Contractor in the performance of this contract, or any representative of the contractor entering the Government installation, shall abide by all the regulations of the installation which may be in effect during the contract period.
2.6. The Contractor shall perform services described in this PWS Para 4 for one (1) year base period from the date of contract award plus two (2) option periods.
3. HOURS OF OPERATION:
3.1. Hospitals and Medical Centers provide services 24 hours a day, 365 days a year.
3.2. Operation Hours of Information Management Division (IMD), 65th MED BDE/MEDDAC-K. 0730 – 1630, Monday to Friday.
4. SPECIFIC TASKS:
4.1. The Contractor shall provide technical support 24 hours a day, 365 days a year by telephone, web, or email when needed.
4.2. The Contractor shall have a technical certification from the American Power Corp to perform the proper service to the APC Symmetra UPS systems.
4.3 The Contractor shall provide the onsite troubleshoot within 8 business hours from the trouble call received.
4.4. Hardware repair/replacement shall be completed within 4 hours of determining that part replacement is required during a standard work week. (24 hours per day, 7 days per week)
4.5. The Contractor shall replace any required parts with the same original manufacture parts for following system:
MODEL No. SYSTEM
APC Symmetra Sy40K40F Camp Carroll CMR UPS
APC Symmetra Sy8K8RM x 2ea Camp Carroll CMR UPS
4.6. Semi-annually system preventive maintenance and cleaning to include updating/replacing system components and software as required. System Maintenance and cleaning shall include, but is not limited to:
4.6.1 Perform Visual Inspection: Inspect the UPS and/or PDU solution to ensure that all system components are clean and functioning within designed specifications.
4.6.2. Perform Mechanical/Electrical Inspection: Inspect all power and control wire termination points as well as all UPS and/or PDU system components.
4.6.3. Detailed Battery Inspection: Validates battery system performance guaranteeing optimal battery operation and system runtime.
4.6.4. Implement Updates: Verify and implement all required Field Advisories and Field Modifications and check all circuit board revisions and update as required.
4.7. Routine System battery replacement:
4.7.1. Provide guideline or recommendation and cost for replacement of defective batteries with new batteries approved by APC for the APC Symmetra Sy40K40F and APC Symmetra Sy8K8RM UPS. The cost should be paid by 65th MED BDE since the batteries are dispensable items and the cost for purchasing new batteries is not included in this contract. The cost include removal, replace, and dispose of the old batteries in accordance with local regulations and laws
4.7.2. Configure and Calibrate the UPS D/C buss and set to Factory Specifications.
Complete functional tests after the service intervention validating that the battery system is functioning to factory specification.
4.8. 24-hour emergency maintenance restoral. At the time of notification of a system failure, the Contractor is required to respond within 24-hours to the site to begin evaluation of the issue and the required resolution.
4.9. The Contractor shall submit to the COR written report of any warranty service within 24 hours after completion.
5. SAFETY:
5.1 Safety Requirements. The Contractor shall insure that safety precautions are taken during the performance of this contract to protect the lives of contractor personnel, the property of the U.S. Government, the Republic of Korea, as well as the private individuals and other personnel who may be exposed to or endangered by the contractor’s actions to maintain minimal accidents/incident, zero loss of life and minimal damage to property. The contractor shall submit safety plan to the COR for review not later than 14 calendar days after contract award. The safety plan shall clearly describe the Contractor’s Safety training, safety method, and practices such as standardized procedures to monitor performance, identify discrepancies, and take corrective action to prevent re-occurrence of any safety issue. The safety plan shall be confirmed and accepted by COR within 5 working days if there is any changes after award. The safety plan shall comply with EM385-1-1, the US Army Corps of Engineers Safety and Health Requirements Manual and the Korean Occupational Safety and Health Act (KOSHA).
5.2. Accident investigations reports, and logs: The safety plan shall include a copy of the contractor’s accident investigation reporting format, and logs. Report all accidents as soon as possible but not more than 30 minutes of accident occurrence to the Contracting Officer/Representative (KO/COR). The contractor shall thoroughly investigate the accident and submit the findings of the investigation along with appropriate corrective actions to the KO/COR in the accident investigation reporting format as soon as possible but no later than five (5) working days following the accident Implement corrective actions as soon as reasonably possible. The accident investigation reporting format shall include at a minimum.
(1) Contract number and contract name/description
(2) Name of contractor
(3) Date/Time of accident
(4) Data report was completed
(5) Detail description of events that lead to the accident
(6) Root cause of accident
(7) Corrective action(s) to prevent recurrence
5.3. The following require immediate accident notification and written accident report
(1) A fatality
(2) A permanent total or permanent partial disability
(3) The hospitalization of three or more people resulting from a single occurrence
(4) Property damage of $200 or more
6. SECURITY:
6.1. Installation Access. The Contractor shall comply with the local installation and access to data centers must be escorted by MEDDAC-K IMD personnel. The Charge of Quarters (CQ) will be in building #975, Camp Carroll for 24X7. The CQ can be reached at 737-4404, commercial 05033-37-4404.
6.2. Vehicle Registration. The data centers are located on restricted access military installations. The Contractor shall comply with the local installation requirements for vehicle registration and operation on the military installation. The Contractor must register their vehicles with the office responsible for vehicle registration to gain access onto the military installation. A valid driver’s license, government-furnished civilian identification, proof of insurance and current registration must be presented to the Provost Marshal’s Office, at which time a DoD decal will be issued. The decal shall be placed on the vehicle’s front windshield in accordance with instructions.
6.2.1. All vehicles, with or without a DoD decal, are subject to search. The Contractor may encounter long delays for vehicle inspection and identification checks upon entering and exiting the installation. The Government will not reimburse the contractor for time spent at installation checkpoints. Delays at these checkpoints will not relieve the Contractor of its obligation to perform services at the locations and at the times required under this contract.
6.2.2. The Contractor shall follow installation procedures for removal and turn-in of the vehicle decal upon termination of services under this contract.
7. Performance Requirements Summary (PRS)
The Government will use these standards to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL). The contract will provide a report of the line item in the PRS.
This report will consist of:
Performance Objective/PWS Para
Performance Standard Performance
Threshold/ AQL Method of
Surveillance Remedy
4.1. Technical
Support and Assistance
Provide 24/7 Technical Support and Assistance by telephone, web or email when needed.
95 % Random
1) Contract Deficiency Report issued.
2) Corrective action taken immediately after CDR issued.
3) Progress meetings by
KO
4.3. Onsite Support
to troubleshoot and Repairs
Onsite troubleshoot must occur within 8 business hours.
100% Random
4.4. Hardware
repair/Replacement
Hardware repair/replacement shall be completed within 4 hours of determining that part replacement is required during a standard work week. (24 hours per day, 7 days per week) After replacing any UPS parts, the system should be operable condition. Monitoring power input and output and notify any malfunction.
100% 100%
Inspection
4.5. Semi-annual
Preventive Maintenance Services
Preventive maintenance and cleaning to include updating/replacing system components and software as required.
100% 100%
Inspection
8. Antiterrorism (AT) and Operations Security (OPSEC)
8.1. AT Level I Training: All Contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level I awareness training within 14 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The Contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the KO, if a COR is not assigned within 14 calendar days after completion of training by all employees and subcontractor personnel.
8.2. Access and General Protection/Security Policy and Procedures: The Contractor and all associated sub-contractors’ employees shall comply with applicable installation, facility, and area commander installation/facility access and local security policies and procedures (provided by government representative). The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshall Office, Director of Emergency Services, or Security Office.
Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
8.3. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
8.4. iWATCH Training: The Contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 14 calendar days of contract award and within 14 calendar days of new employees commencing performance with the results reported to the COR NLT 14 calendar days after contract award.
8.5. For Contracts that Require OPSEC Training: Per AR 530-1, Operations Security, new contractor employees must complete Level I OPSEC training within 30 calendar days of their reporting for duty and annually thereafter.
8.6. For Information assurance (IA) /Information technology (IT) training. All contractor employees and associated sub-contractor employees must complete the DoD IA awareness training before issuance of network access and annually thereafter. All contractor employees working IA/IT functions must comply with DoD and Army training requirements in DoD 8670.01, DoD 8570.01-M and AR 25-2 within six months of appointment to IA/IT functions.
8.7. For Information assurance (IA)/Information technology (IT) certification. Per DoD 8570.01-M, DFARS
252.239.7001 and AR25-2, the contractor employees supporting IA/IT functions shall be appropriately certified upon contract award. The baseline certification as stipulated in DoD 8570.01-M must be completed upon contract award.
9. ACCOUNTING FOR CONTRACT SERVICES: Contractor Manpower Reporting (CMR) Requirement
The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the Contractor will report ALL Contractor manpower (including sub-Contractor manpower) required for performance of this contract. The Contractor is required to completely fill in all the CMR information in the format using the following web address: https://cmra.army.mil. However, before the Contractor can begin reporting CMR data in this website, he must first register as a User. In order to register, the Contractor must have a Cage Code.
CMR Reporting. The information required to be reported in the CMR website includes:
(1) Contracting Office, Contracting Officer, Contracting Officer’s Technical Representative (COTR) or Contracting Officer’s Representative (COR);
(2) Contract Number, including Task and Delivery Order Number(s);
(3) Beginning and Ending Dates covered by reporting period;
(4) Contractor Name, Address, Phone Number, E-Mail address, Identity of Contractor Employee entering data;
(5) Estimated Direct Labor Hours (including sub-Contractors’ hours);
(6) Total Payments (including sub-Contractors’ payments);
(7) Predominant Federal Service Code (FSC) reflecting services provided by Contractor (and separate
Predominant FSC for each sub-Contractor if different);
(8) Estimated data collection cost;
(9) Organizational Title associated with the Unit Identification Code (UIC) for the Army Requiring Activity reporting this information (the Army Requiring this information);
(10) Locations where Contractor and sub-Contractors perform the work (specified by zip code in the United States and nearest City and Country when in an overseas location, using standardized nomenclature provided on website);
(11) Presence of Deployment or Contingency Contract language; and
(12) Number of Contractor and sub-Contractor employees deployed in theater this reporting period (by Country).
As part of its submission in response to a solicitation or modification request which includes a contract line item number (CLIN) for this CMR reporting requirement, the Contractor shall also provide the estimated total cost (if any) incurred to comply with this reporting requirement on the associated CMR CLIN. Reporting period will be the period of performance not to exceed 12 months ending September 30 of each Government fiscal year and must be reported by 31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a Contractor’s systems to the secure website without the need for separate data entries for each required data element at the website. The specific formats for the XML direct transfer may be downloaded from the website.
CMR reporting is a requirement mandated by the Department of Army. Failure of the Contractor to comply with this requirement will be noted as Past Performance information about the Contractor to be used on future procurements for the same or similar services
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A Government 0002 N/A N/A N/A Government 0003 N/A N/A N/A Government 0004 N/A N/A N/A Government 1001 N/A N/A N/A Government 1002 N/A N/A N/A Government 1003 N/A N/A N/A Government 1004 N/A N/A N/A Government 2001 N/A N/A N/A Government 2002 N/A N/A N/A Government 2003 N/A N/A N/A Government 2004 N/A N/A N/A Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 10-AUG-2020 TO
09-AUG-2021
N/A CDR, MEDDAC-K
CDR, MEDDAC-K
UNIT: 15281
APO AP 96205-5281
KOREA, SOUTH
315-737-1618
W91QHB
0002 POP 10-AUG-2020 TO
09-AUG-2021
N/A (SAME AS PREVIOUS LOCATION)
0003 POP 10-AUG-2020 TO
N/A (SAME AS PREVIOUS LOCATION)
0004 POP 10-AUG-2020 TO
N/A (SAME AS PREVIOUS LOCATION)
1001 POP 10-AUG-2021 TO
09-AUG-2022
N/A (SAME AS PREVIOUS LOCATION)
1002 POP 10-AUG-2021 TO
N/A (SAME AS PREVIOUS LOCATION)
1003 POP 10-AUG-2021 TO
N/A (SAME AS PREVIOUS LOCATION)
1004 POP 10-AUG-2021 TO
N/A (SAME AS PREVIOUS LOCATION)
2001 POP 10-AUG-2022 TO
09-AUG-2023
N/A (SAME AS PREVIOUS LOCATION)
2002 POP 10-AUG-2022 TO
N/A (SAME AS PREVIOUS LOCATION)
2003 POP 10-AUG-2022 TO
N/A (SAME AS PREVIOUS LOCATION)
2004 POP 10-AUG-2022 TO
N/A (SAME AS PREVIOUS LOCATION)
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011
52.204-13 System for Award Management Maintenance OCT 2018 52.212-1 Instructions to Offerors--Commercial Items JUN 2020 52.212-3 Offeror Representations and Certifications--Commercial
Items
JUN 2020
52.212-4 Contract Terms and Conditions--Commercial Items OCT 2018 52.225-14 Inconsistency Between English Version And Translation Of
Contract
FEB 2000
52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications.
JUN 2020
52.232-23 Assignment Of Claims MAY 2014 52.233-1 Disputes MAY 2014 52.233-2 Service Of Protest SEP 2006 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.237-2 Protection Of Government Buildings, Equipment, And
Vegetation
APR 1984
52.237-3 Continuity Of Services JAN 1991 52.239-1 Privacy or Security Safeguards AUG 1996 52.246-4 Inspection Of Services--Fixed Price AUG 1996 52.247-34 F.O.B. Destination NOV 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
NOV 2011
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting
DEC 2019
252.222-7002 Compliance With Local Labor Laws (Overseas) JUN 1997 252.225-7039 Defense Contractors Performing Private Security Functions
Outside the United States
JUN 2016
252.225-7041 Correspondence in English JUN 1997 252.225-7042 Authorization to Perform APR 2003 252.225-7048 Export-Controlled Items JUN 2013 252.228-7000 Reimbursement for War-Hazard Losses DEC 1991 252.229-7001 Tax Relief APR 2020 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.232-7008 Assignment of Claims (Overseas) JUN 1997 252.232-7010 Levies on Contract Payments DEC 2006 252.233-7001 Choice of Law (Overseas) JUN 1997 252.237-7010 Prohibition on Interrogation of Detainees by Contractor
Personnel
JUN 2013
252.243-7001 Pricing Of Contract Modifications DEC 1991 252.244-7000 Subcontracts for Commercial Items JUN 2013
CLAUSES INCORPORATED BY FULL TEXT
52.212-2 EVALUATION--COMMERCIAL ITEMS (OCT 2014)
(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:
See below Addendum to FAR 52.212-2 EVALUATION – COMMERCIAL ITEMS (OCT 2014)
(b) Options. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).
(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
(End of provision)
ADDENDUM TO FAR 52.212-2
EVALUATION – COMMERCIAL ITEMS (OCT 2014)
In accordance with FAR 15.101-2, the Government will award a contract resulting from this solicitation to the responsible offeror submitting the lowest priced, technically acceptable offer that satisfies all terms and conditions of this solicitation.
Award will be made to the responsible Offeror submitting the Lowest Priced, Technically Acceptable (LPTA) offer that satisfies all terms and condition of the solicitation. Offers will be evaluated for acceptability, but not ranked using non-price factors/sub-factors. All non-price factors and sub-factors will be rated as either “acceptable” or “unacceptable”. In order to be considered for award, there must be an “acceptable” rating in every non-price factor/sub-factor. In other words, a rating of “unacceptable” for any factor or sub-factor will result in the entire offer being rated “unacceptable”.
The following ratings will be used in evaluating all non-price technical factors and sub-factors.
Technical Acceptable/Un-acceptable Ratings Rating Description
Acceptable Proposal clearly meets the minimum requirements of the solicitation.
Unacceptable Proposal does not clearly meet the minimum requirements of the solicitation.
In order to be considered for award, there must be an “acceptable” rating in every non-price factor/sub-factor. In other words, a rating of “unacceptable” for any factor or sub-factor will result in the entire offer being rated “unacceptable”.
FACTOR A – TECHNICAL PROPOSAL
(a) Sub-factor 1 – Contractor’s License and Certificate: The offeror shall be evaluated the submitted an American Power Corp (APC) Uninterruptible Power Supply (UPS) service license in Korea and certificate from APC to performance UPS maintenance service. See paragraph 2 of Performance Work Statement (PWS).
(b) Sub-factor 2 – Contractor’s Prior Experience: The offeror shall be evaluated on submitted documentation demonstrating at least one (1) year experience with preventative maintenance and repair of APC UPS in medical environment or similar service relevant to this solicitation’s requirement within four (4) years from the closing date of sonication. (See paragraph 2.3 of PWS) The offeror shall provide evidence of prior experience in following format:
The title of the contract/project/employer A brief description of work completed Name of the Client Organization or Requiring Activity (RA) Period of contract/project (year/month/date – year/month/date) Complete name of point of contact at the Client Organization Phone number of the primary point of contact of the Client/RA
FACTOR B - PAST PERFORMANCE: Past performance shall be evaluated on an acceptable/unacceptable basis.
Offerors are authorized to provide information on the problems encountered on the identified contracts and the Offeror’s corrective actions. The Government may ascertain past performance information on the Offeror from sources other than the references provided.
The offeror shall have recent and relevant past performance in care coordination, discharge planning or case management in a medical setting or similar types of services. Recent past performance is within the last five (5) years as of the closing date of the solicitation.
The past performance will be evaluated for all offeror’s proposals by the Contract Specialist/Contracting Officer in the following manner:
(i) Reference will be contacted by phone or e-mail to verify contents in detail explanation and to determine record of compliance with contract requirements, accuracy of reports, technical and quality awards/certificates.
(ii) The Government reserves the right to obtain past performance information from any reasonable source available, including Government database in order to evaluate past performance.
Past Performance Evaluation Ratings Rating Description
Acceptable Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown. (See note below)
Unacceptable Based on the offeror’s performance record, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort.
NOTE: In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305(a)(2)(iv)). Therefore, the offeror shall be determined to have unknown past performance. In the context of acceptability/unacceptability, “unknown” shall be considered “acceptable”
FACTOR C - PRICE: Proposed price will be reviewed to determine if the estimate is adequate, complete, and reasonable to assess the offeror's understanding of the solicitation. The pricing proposals will be evaluated in accordance with FAR 13.106-3(a)(1)&(2).
(End of provision FAR 52.212-2 EVALUATION – COMMERCIAL ITEMS (OCT 2014)
ADDENDUM TO FAR 52.212-1
Addendum to FAR 52.212-1, INSTRUCTIONS TO OFFERORS – COMMERCIAL ITEMS (Jan 2017)
1. Quotations shall be submitted to beta.SAM.gov (https://beta.sam.gov/) Quotation submitted other than beta.SAM.gov will not be considered for award. The technical proposal for specification shall include the company name. All questions should be emailed to hyeyong.chong1.ln@mail.mil within five (5) days after the solicitation is issued. The electronic quotation shall be submitted by 1300 hours (Korean Local Time) on the closing date of RFP.
2. The quotation(s) shall include the following requirements in accordance with (IAW) Para 1 above.
3. Submittal Requirements: A rating of unacceptable for any factor or sub-factor will result in technically unacceptable rating. Failure to provide documents addressed below will result in a rating of “Unacceptable”.
I. Factor A - Technical Proposal: Technical evaluation factors are equal to price.
(a) Sub-factor 1 – Contractor’s License and Certificate: The Contractor must have an American Power Corp (APC) Uninterruptible Power Supply (UPS) service license in Korea and submit certificate from APC to performance UPS maintenance service. See paragraph 2 of Performance Work Statement (PWS).
(b) Sub-factor 2 – Contractor’s Prior Experience: The Contractor personnel shall have a minimum one (1) year experience with preventative maintenance and repair of APC UPS in medical environment or similar service relevant to this solicitation’s requirement within four (4) years from the closing date of sonication. (See paragraph
2.3 of PWS). The offeror shall provide evidence of prior experience in following format:
The title of the contract/project/employer A brief description of work completed Name of the Client Organization or Requiring Activity (RA) Period of contract/project (year/month/date – year/month/date) Complete name of point of contact at the Client Organization Phone number of the primary point of contact of the Client/RA
II. Factor B - Past Performance:
The offeror shall provide recent and relevant past performance in care coordination, discharge planning or case management in a medical setting. Recent past performance is within the last five (5) years as of the closing date of the solicitation. Relevant past performance are those that are the “same or similar” type of services.
(a) Contract references. For each Past Performance submission as required in the below format:
The title of the Project or Contract No for the Commercial or Government performance A clear description of qualifying work experience Length of contract/project (Year/Month/Date – Year/Month/Date) Value of contract/project in KW for total amount Complete POC of employer (including name, phone no, e-mail) and validating POC
(b) The Government may send a Past Performance Questionnaire to the POC listed by the Offeror for each relevant contract, who will subsequently be requested to submit information to the Government no later than 14 days after Government issuance of the questionnaire.
Note: Offerors are reminded that while the Government may elect to consider data obtained from other sources, the Government does not assume the duty to search for data to cure problems it finds in the proposals. The burden of providing thorough and complete past performance information rests with the Offeror.
III. Factor C - Prices. Price Proposal: The offeror shall complete the pricing information for each Contract Line Item Numbers (CLIN) and Sub Contract Line Item Numbers (SLIN) as specified in the solicitation.
IV. FAR Clause 52.212-3 Alt I, Offeror Representations and Certifications – Commercial Items. The offeror shall complete 52.212-3 Alt I, paragraph (h) and (k).
V. Local Clause 5152.204-4032 – Representations and Certifications. The offeror shall complete local clause 5152.204-4032.
VI. Local Clause 5152.209-4009, Notice of Evaluation of Past Performance shall complete.
VII. Name(s) and telephone number, and e-mail address of person(s) authorized to conduct discussions/negotiations and to financially bind the company.
(End of provision FAR 52.212-1, INSTRUCTIONS TO OFFERORS – COMMERCIAL ITEMS (Jan 2017)
CLAUSES INCORPORATED BY FULL TEXT
52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR
EXECUTIVE ORDERS--COMMERCIAL ITEMS (JUN 2020)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.
113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) (Section 1634 of Pub. L. 115-91).
(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (AUG 2019) (Section 889(a)(1)(A) of Pub. L. 115-232).
(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).
(5) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(6) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77 and 108-78 (19 U.S.C. 3805 note)).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items: (Contracting Officer check as appropriate.)
__X_ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (JUN 2020), with Alternate I (Oct 1995) (41 U.S.C. 4704 and 10 U.S.C. 2402).
____ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (JUN 2020) (41 U.S.C. 3509).
____ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (JUN 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)
___ (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L.
109-282) (31 U.S.C. 6101 note).
___ (5) [Reserved]
___ (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div.
C).
_X__ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub.
L. 111-117, section 743 of Div. C).
___ (8) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (JUN 2020) (31 U.S.C. 6101 note).
____ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) (41 U.S.C. 2313).
____ (10) [Reserved]
____ (11)(i) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (MAR 2020) (15 U.S.C. 657a).
____ (ii) Alternate I (MAR 2020) of 52.219-3.
____ (12) (i) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (MAR 2020) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).
____ (ii) Alternate I (MAR 2020) of 52.219-4.
____ (13) [Reserved]
____ (14)(i) 52.219-6, Notice of Total Small Business Set-Aside (MAR 2020) (15 U.S.C. 644).
____ (ii) Alternate I (MAR 2020).
____ (15)(i) 52.219-7, Notice of Partial Small Business Set-Aside (MAR 2020) (15 U.S.C. 644).
____ (ii) Alternate I (MAR 2020) of 52.219-7.
____ (16) 52.219-8, Utilization of Small Business Concerns (OCT 2018) (15 U.S.C. 637(d)(2) and (3)).
____ (17)(i) 52.219-9, Small Business Subcontracting Plan (JUN 2020) (15 U.S.C. 637(d)(4)).
____ (ii) Alternate I (NOV 2016) of 52.219-9.
____ (iii) Alternate II (NOV 2016) of 52.219-9.
____ (iv) Alternate III (JUN 2020) of 52.219-9.
____ (v) Alternate IV (JUN 2020) of 52.219-9.
____ (18) 52.219-13, Notice of Set-Aside of Orders (MAR 2020) (15 U.S.C. 644(r)).
____ (19) 52.219-14, Limitations on Subcontracting (MAR 2020) (15 U.S.C. 637(a)(14)).
____ (20) 52.219-16, Liquidated Damages—Subcontracting Plan (Jan 1999) (15 U.S.C. 637(d)(4)(F)(i)).
____ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (MAR 2020) (15 U.S.C. 657f).
____ (22) (i) 52.219-28, Post Award Small Business Program Rerepresentation (MAR 2020) (15 U.S.C. 632(a)(2)).
____ (ii) Alternate I (MAR 2020) of 52.219-28.
____ (23) 52.219-29, Notice of Set-Aside for, or Sole Source Award to, Economically Disadvantaged Women- Owned Small Business (EDWOSB) Concerns (MAR 2020) (15 U.S.C. 637(m)).
____ (24) 52.219-30, Notice of Set-Aside for, or Sole Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (MAR 2020) (15 U.S.C. 637(m)).
____ (25) 52.219-32, Orders Issued Directly Under Small Business Reserves (MAR 2020) (15 U.S.C. 644(r)).
____ (26) 52.219-33, Nonmanufacturer Rule (MAR 2020) (15 U.S.C. 637(a)(17)).
____ (27) 52.222-3, Convict Labor (JUN 2003) (E.O. 11755).
__X__(28) 52.222-19, Child Labor--Cooperation with Authorities and Remedies (JAN 2020) (E.O. 13126).
____ (29) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
____ (30)(i) 52.222-26, Equal Opportunity (SEPT 2016) (E.O. 11246).
____ (ii) Alternate I (FEB 1999) of 52.222-26.
__X__ (31)(i) 52.222-35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212).
____ (ii) Alternate I (JUL 2014) of 52.222-35.
____ (32)(i) 52.222-36, Equal Opportunity for Workers with Disabilities (JUN 2020) (29 U.S.C. 793).
____ (ii) Alternate I (JUL 2014) of 52.222-36.
____ (33) 52.222-37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212).
____ (34) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) (E.O.
13496).
____ (35)(i) 52.222-50, Combating Trafficking in Persons (JAN 2019) (22 U.S.C. chapter 78 and E.O. 13627).
____ (ii) Alternate I (MAR 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).
____ (36) 52.222-54, Employment Eligibility Verification (OCT 2015). (E. O. 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in 22.1803.)
____ (37)(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA–Designated Items (MAY 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
____ (ii) Alternate I (MAY 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
____ (38) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (JUN 2016) (E.O. 13693).
____ (39) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners
(JUN 2016) (E.O. 13693).
____ (40) (i) 52.223-13, Acquisition of EPEAT® Registered Imaging Equipment (JUN 2014) (E.O.s 13423 and 13514).
____ (ii) Alternate I (OCT 2015) of 52.223-13.
____ (41)(i) 52.223-14, Acquisition of EPEAT® Registered Televisions (JUN 2014) (E.O.s 13423 and 13514).
____ (ii) Alternate I (JUN 2014) of 52.223-14.
____ (42) 52.223-15, Energy Efficiency in Energy-Consuming Products (DEC 2007) (42 U.S.C. 8259b).
____ (43)(i) 52.223-16, Acquisition of EPEAT®-Registered Personal Computer Products (OCT 2015) (E.O.s 13423 and 13514).
____ (ii) Alternate I (JUN 2014) of 52.223-16.
____ (44) 52.223-18, Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) (E.O.
13513).
____ (45) 52.223-20, Aerosols (JUN 2016) (E.O. 13693).
____ (46) 52.223-21, Foams (JUN 2016) (E.O. 13693).
____ (47)(i) 52.224-3, Privacy Training (JAN 2017) (5 U.S.C. 552a).
____ (ii) Alternate I (JAN 2017) of 52.224-3.
____ (48) 52.225-1, Buy American--Supplies (MAY 2014) (41 U.S.C. chapter 83).
____ (49) (i) 52.225-3, Buy American--Free Trade Agreements--Israeli Trade Act (MAY 2014) (41 U.S.C. chapter 83, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, Pub. L. 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43.
____ (ii) Alternate I (MAY 2014) of 52.225-3.
____ (iii) Alternate II (MAY 2014) of 52.225-3.
____ (iv) Alternate III (MAY 2014) of 52.225-3.
____ (50) 52.225-5, Trade Agreements (OCT 2019) 19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).
__X__ (51) 52.225-13, Restrictions on Certain Foreign Purchases (JUN 2008) (E.O.'s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
____ (52) 52.225-26, Contractors Performing Private Security Functions Outside the United States (OCT 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).
____ (53) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (NOV 2007) (42 U.S.C. 5150
____ (54) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (NOV 2007) (42 U.S.C.
5150).
____ (55) 52.229-12, Tax on Certain Foreign Procurements (JUN 2020).
____ (56) 52.232-29, Terms for Financing of Purchases of Commercial Items (FEB 2002) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).
____ (57) 52.232-30, Installment Payments for Commercial Items (JAN 2017) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).
__X__ (58) 52.232-33, Payment by Electronic Funds Transfer—System for Award Management (OCT 2018) (31 U.S.C. 3332).
____ (59) 52.232-34, Payment by Electronic Funds Transfer—Other than System for Award Management (JUL 2013) (31 U.S.C. 3332).
____ (60) 52.232-36, Payment by Third Party (MAY 2014) (31 U.S.C. 3332).
____ (61) 52.239-1, Privacy or Security Safeguards (AUG 1996) (5 U.S.C. 552a).
____ (62) 52.242-5, Payments to Small Business Subcontractors (JAN 2017)(15 U.S.C. 637(d)(13)).
____ (63)(i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006) (46 U.S.C.
Appx. 1241(b) and 10 U.S.C. 2631).
____ (ii) Alternate I (APR 2003) of 52.247-64.
____ (iii) Alternate II (FEB 2006) of 52.247-64.
(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items: (Contracting Officer check as appropriate.)
_____ (1) 52.222-41, Service Contract…