This document is an amendment to a solicitation for relief well construction services. The solicitation seeks bids for drilling new relief wells and constructing well pads along a paved ditch to control river stage levels in East St. Louis, Illinois. The amendment provides additional clarification on well locations, allows existing wells to be used for drilling makeup water, permits positive drainage and alternate pad materials, modifies filter pack and casing requirements, addresses overhead power line clearance issues, changes the project magnitude from over $10 million to between $5-10 million, and sets the revised bid due date as August 9, 2021 at 10:00 AM via email. Bidders must submit all bids to the specified contracting officer's email address in accordance with the instructions provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A21 Revised Drawing B-501.pdf | ||
| A21 Site Visit Sheet.JPG | JPG image |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Reference above numbered IFB Solicitation number to reflect the follow ing Amendments:
See Page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 02-Aug-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P921B0006
X 9B. DATED (SEE ITEM 11)
08-Jul-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
02-Aug-2021
CODE
CONTRACTING DIVISION
US ARMY ENGR DIST ST LOUIS
1222 SPRUCE STREET, RM 4.207
ST LOUIS MO 63103-2833
W912P9 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P921B0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 1
1. Are all wells in North section located in center of ditch? RW 36XA – 36XB – 37X appear to be offset. Those 3 wells you listed are offset, the others are in the ditch.
2. Can existing wells be used for make up water for drilling or to lower ground water elevation? Yes
3. In order to drill and install the wells located in the center of paved ditch, the ditch will have to be filled to provide a suitable work platform. If this is approved, would the contractor have to maintain drainage at the ditch flowline elevation, or is that elevation only required when wells are flowing?
Positive drainage around a potential work platform is required at flowline at all times.
4. Bid Schedule Item A009 Crushed Stone. Is this item for constructing drill pads identified in para.
2.4 and 3.1.4 of Section 33 27 15? Yes
5. If Bid Item A009 is for the construction of drill pads, the quantity of 200 ton would allow construction of one 3-4 ft high pad. The contract requires the contractor to work as long as the river stage is below 25 ft. (Elevation 404.58 ft.). Several of the new wells discharge below 404.59
ft. elevation. This will require an unknown number of drill pads to be constructed, some in excess of 10 ft. possibly, in order to meet the 10 ft. differential required by paragraph 3.1.2 of Section 33 27 15. How will the contractor be compensated for this cost? Bid Item A008 Crushed Stone will be changed to “Drilling Pads” and paid by Job.
5a. If drill pads are required in excess of the 200 tons allotted in the contract and the district is not paying for tonnage in excess of 200 tons for the project, can alternate materials such as soils or crane mats or heavy timbers be used for the drill pads or will the contractor be required to use crushed aggregate for all drill pads? Also, can the contractor elect to use alternate materials such as those discussed above be utilized in lieu of crushed aggregate for drill pads? Contractor shall determine drill pad material, see answer to question 5.
6. Plan Sheet B-501 Detail A1 Typical D-Type Relief Well. This detail shows the filter pack terminating 5 ft. above top of screen. Some of the wells would require casings in excess of 45 ft.
long in order to shield the bore after installation of the well. On all our previous St. Louis District projects, we terminated the top of the filter at whatever elevation required to provide for a 20 ft.
seal, the minimum length required by IL well code. This practice allows contractors to utilize standard length casings and eliminates additional equipment required to extract long casings and has no negative impact on the wells performance. Will this be allowed, as long as we meet the required 5 ft. minimum above screen and state well code? Yes this will be allowed, see revised drawing.
7. Section 33 27 15, para. 2.2.2.1, Testing. The filter pack material we intend to use will be supplied in 3 or 4 thousand-pound super sacks. The supplier will not recognize the validity of any test taken after transporting to the job site. Will it be acceptable to sample and test the material at the supplier’s yard before shipping? Yes sampling and testing may be done at the supplier’s yard as long as all other requirements of 33 27 15 para. 2.2.2.1 are met.
W912P921B0006
8. Section 00 08 00, para. 1.3-B Utilities. During the site visit it appeared that there could be numerous locations, primarily along the paved ditch area, where overhead power lines could conflict with well locations.
a. Has the USACE or MESD contacted the owners of these power lines about de-energizing? The line is 4 kv. It is about 2400v phase to ground. Contractor to determine safe distance and provide shielding as necessary. Contractor to coordinate with utility to temporarily de-energize if required.
b. If they cannot be de-energized, would it be resolved in accordance with Paragraph B of
1.3? See answer to 8a.
-MAGNITUDE IS CHANGED FROM MORE THAN $10 MILLION TO $5,000,000.00 - $10,000,000.00
-BIDS SHOULD BE SUBMITTED VIA EMAIL TO THE FOLLOWING ADDRESS:
lisa.white@usace.army.mil
-BID DUE DATE IS NOT EXTENDED, AND REMAINS 9 AUGUST 2021 AT 10:00 A.M.