This document is Amendment #2 to RFP PMAA 2026*0020 for Spring Creek Construction Manager General Contractor (CMGC) services, issued by a state or local government entity in conjunction with the U.S. Forest Service (USFS). The amendment addresses clarifications regarding bridge access and weight restrictions for the project site. The RFP requires bidders to submit materials including a sample risk register and high-level schedule as part of their proposal response. According to the amendment, these documents must be included in the main body of the RFP submission rather than in appendices and will be counted toward the overall page limit specified in the original RFP. The document confirms that no specific response dates, due dates, site visit requirements, or award dates are outlined in this amendment.

The amendment provides critical infrastructure information necessary for bid preparation. Bridge access to Spring Creek Dam involves multiple routes with varying weight restrictions: FSR 744 includes Spring Creek No. 1 Bridge rated at 35 tons and Spring Creek No. 2 Bridge rated at 64 tons (both upper bridges were replaced in 2025); FSR 748 and FSR 742 routes include the Texas Creek Bridge rated at 48 tons and Rocky Brook Bridge rated at 48 tons. All load ratings are vehicle-type dependent, and contractors must coordinate with the USFS Regional Bridge Engineer to obtain necessary overload permits. The document clarifies that FSR 748 currently has no weight restrictions. All other terms and conditions of the original RFP remain unchanged by this amendment.

View the file

Other files

File Type Posted
A#1 PreBid Agenda & Discussion.pdf PDF
A#1 Prebid Sign In Sheet.pdf PDF
RFP PMAA 2026_0020 Spring Creek CMGC (1).docx DOCX document
A#1 RFP PMAA 2026_0020 Spring Creek CMGC.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment #2 - Questions & Answers (Q&A)

RFP PMAA 2026*0020

Spring Creek CMGC

A. The following questions, and the answer to each, were received:

1. Please provide any weight restrictions for bridges to the site along CO Rd

744.

i. There are currently no weight restrictions on any of the bridges along FSR 744.

ii. The two upper bridges were replaced in 2025.

iii. The lower two bridges have the following load ratings:

1. Spring Creek No. 1 - 35 tons

2. Spring Creek No. 2 - 64 tons

iv. The load rating above is a general case. The exact rating depends upon the type of vehicle traveling across the bridge, number of axels, etc. The contractor will have to work with the USFS Regional

Bridge Engineer to obtain the necessary overload permits.

2. Please confirm if any bridges or weight restrictions are in place along CO

Rd 742 and FSR 748 for access through Taylor Park Recreation to Spring

Creek Dam.

i. See response from question “1” above for bridges along FSR 744.

There are currently no weight restrictions on any of the bridges along FSR 748.

ii. The following provides a general sense of the current load ratings along the FSR 748 route.

1. FSR 742 / Texas Creek Bridge - 48 tons

2. FSR 748 / Rocky Brook Bridge - 48 tons

iii. The load rating above is a general case. The exact rating depends upon the type of vehicle traveling across the bridge, number of axels, etc. The contractor will have to work with the USFS Regional

Bridge Engineer to obtain the necessary overload permits.

3. The RFP response requests items such as a sample risk register and high-level schedule. If 11x17's and/or additional exhibits are needed, can these be attached as Appendix D and beyond? If so, will those appendices count towards any page limit?

i. The Example Risk Register and high level schedule should be included in the main body of the RFP and not in Appendix D. They will be included in the page limit identified in the RFP.

B. All other terms and conditions of RFP PMAA 2026*0020 remain the same.

Amendment #2 - Questions & Answers (Q&A)
RFP PMAA 2026*0020
Spring Creek CMGC