A2 - Performance Work Statement - Final.pdf
PDF 725 KB Posted
- Attached to
- Philpott Lake Restroom Replacement
- Solicitation number
- PANSAD-26-P-0000032497
About this file
This is a Performance Work Statement (PWS) for the replacement of two precast concrete vault toilet restrooms at Philpott Lake in Virginia. The contract requires delivery and placement of Carson Vault Toilet buildings with gabled-style roofs at two locations: "Peewees" (1058 Philpott Dam Road, Bassett, VA 24055) and "Tail Race" (3000 River Brook Road, Henry, VA 24102). All work must be completed within 180 calendar days of contract award, with work scheduled between 7:00 AM and 4:30 PM, Monday through Friday, excluding Federal Holidays. The contractor must comply with Virginia Engineering and Building Codes, OSHA regulations, EM 385-1-1 US Army Corps of Engineers Safety and Health Manual, and manufacturer specifications.
The restroom specifications include precast concrete construction with 5000 PSI minimum 28-day compressive strength, single-component monolithic wall and floor panels with no vertical joints, and post-tensioned roof and floor design. Building exterior dimensions are 11'–11" x 17'–6" x 9'–11" with gabled roof featuring 3/12 pitch and simulated cedar shake finish. Interior finishes include water-based polyamide epoxy flooring, with exterior walls featuring Barn board finish in Neutral Balance Tan and roofs in Cedarwood Brown. Fixtures include waterless ADA-compliant toilets, stainless steel grab bars, 304 stainless steel doors (3'–0" x 6'–8" entry doors and 2'–8" x 6'–8" chase doors), windows with Lexan glazing, and toilet paper dispensers. Each restroom requires a 2,000-gallon minimum concrete vault with protective cover. Execution includes site preparation with 4-inch minimum crushed stone base compacted to 1,500 PSF, asphalt paving from existing roads to building foundations (approximately 750 square feet at Peewees, 400 square feet at Tail Race), positive drainage, and removal of all debris upon completion.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
Philpott Lake
Replacement Restrooms
PART 1 – GENERAL REQUIREMENTS
1.1 Summary of Work
These work sites are located at Philpott Lake in Bassett, Virginia and Henry, Virginia.
Service to be provided under this contract shall include all equipment, labor, supervision, and materials. This project includes the replacement of two (2) vault toilets at the following locations:
• Replacement Restroom (1) - "Peewees": Located at 1058 Philpott Dam Road, Bassett, VA 24055
• Replacement Restroom (2) – “Tail Race”: Located at 3000 River Brook Rdoad, Henry, VA
24102
1.2 Objective of Work
The purpose of this contract is the delivery and placement of two (2) precast concrete prefabricated restrooms that are approved by the Contracting Officer's Representative (COR). All work must be performed in accordance with the requirements and specifications below.
1.3 Period of Performance
All work must be completed within 180 calendar days after contract award. Work must be scheduled between 7:00 AM and 4:30 PM, Monday through Friday, excluding Federal Holidays. Any work performed outside this timeframe must be approved in advance by the
COR.
1.4 Work Requirements
All work must be performed in accordance with Virginia Engineering and Building Codes.
The contractor must comply with all current OSHA regulations and requirements contained in the EM 385-1-1 US Army Corps of Engineers Safety and Health Manual. Materials shall be installed in accordance with the manufacturer’s specifications, details, and workmanship requirements.
The contractor shall be responsible for protecting Government property and undisturbed land not intended for modification. Any damaged property shall be repaired to its original condition by the contractor at their own expense. The contractor is responsible for removing all trash, debris, and excess materials upon job completion.
1.5 Public Safety
The contractor is responsible for safeguarding the work site at all times. The contractor shall provide adequate signage and barricades and take necessary safety measures to protect the public during all construction operations. At the close of each workday, the contractor shall ensure all materials and equipment are locked and secure, and the worksite does not pose any potential hazards to the general public.
1.6 Antiterrorism/Operations Security (AT/OPSEC) Requirements
The Contractor will be required to adhere to the following conditions:
• Access and General Protection/Security Policy and Procedures: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
• AT Level I Training: All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change).
• Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/ eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
1.7 Storage of Equipment and Materials
The contractor shall store materials and equipment only in areas approved by the Government. The Government will provide the contractor with a storage area near the construction site. However, the Government is not responsible for any theft, vandalism, or damage. The contractor must store all materials per the manufacturer’s recommendations.
1.8 Pre-Bid Site Visit
No formal site visits are scheduled; however, site visits may be arranged during normal duty hours by contacting:
Name: Neal Ingram
Address: Philpott Lake Visitors Center, 1058 Philpott Dam Rd., Bassett, Virginia 24055
Telephone: 276-629-4512
PART 2 – PRODUCT SPECIFICATIONS
Carson Vault Toilet - Gabled Style Roof
2.1 Summary
Contractor shall furnish two (2) precast concrete transportable restrooms. Buildings are to be delivered and placed on crushed stone foundations in accordance with the manufacturer’s recommendations. The Precast Restroom Model Carson Vault Toilet-Gabled Style Roof buildings will be supplied and delivered with all necessary openings as specified by the contractor in conformance with the manufacturer’s structural requirements.
2.2 References
• A. ACI-318-11: Building Code Requirements for Structural Concrete and Commentary
• B. ASCE/SEI 7-10: Minimum Design Loads for Buildings and Other Structures
• C. IBC 2012: International Building Code
• D. PCI Design Handbook, 7th Edition
• E. Concrete Reinforcing Institute, Manual of Standard Practice
• F. UL-752 (Test Method level 5) for bullet resistance certified by a military-approved laboratory
• G. 2010 ADA Standards for Accessible Design
• H. International Plumbing Code (IPC) and National Electrical Code (NEC)
• I. USDA Forest Service Publication: In-depth Design and Maintenance Manual for Vault Toilets (Incorporating FAN™ Natural Ventilation System)
2.3 System Description & Design Requirements
2.3.1 Building Dimensions:
• Exterior: 11’-11” x 17’-6” x 9’-11” (tallest point)
• Interior: 6’-10” x 17’-0” x height (varies)
2.3.2 Design Loads: Design cases correspond to the design criteria indicated in the aforementioned codes for the geographical location of the project.
2.3.2.1 Seismic Design Category ‘D’, Risk Design Category III
2.3.2.2 Roof Live Load (Snow) – 150 PSF
2.3.2.3 Floor Live Load – 150 PSF
2.3.2.4 Standard Wind Loading (precast components only) – 165 MPH
2.3.3 Roof: Gabled style roof. Roof panels shall overhang on all sides to prevent water intrusion. The pitch of the roof shall be 3/12. The roof standard finish is a simulated cedar shake.
2.3.4 Wall & Floor Panels: Roof panels, floor, and wall panels must each be produced as single-component monolithic panels. No floor or vertical wall joints will be allowed, except at perimeter interfaces, corners, and partitions. Wall panels shall be set on top of the floor panel.
2.3.5 Interior Joints: Wall-to-Floor interior surface joints along the perimeter of each restroom and partitions (if precast) must contain the locked-in, easy clean-out radius coving. The 3/8” (recessed) x 2” cove must be continuous around the interior of the restroom and along the sides of any precast partitions. Apply 5,000 PSI (minimum) non-shrink, non-metallic grout to the cove, finishing the grout to form a flush 1” minimum radius.
2.3.6 Chase Area: Center section known as the chase shall have a floor cut out of 10” by 10” in the rear center of the floor 4” from the back wall. Customer will provide conduit for the up-right to be placed in the base through the access hole.
2.4 Materials
2.4.1 Concrete: Steel-reinforced, 5000 PSI minimum 28-day compressive strength, air-entrained (ASTM C260).
2.4.2 Reinforcing Steel: ASTM A615, grade 60 unless otherwise specified. Welded wire fabric:
ASTM 185, Grade 65.
2.4.3 Post-tensioning Strand: 41K Polystrand CP50, ½” 270 KSI Seven-Wire strand, enclosed within a greased plastic sheath (ASTM A416). Each roof and floor shall be post-tensioned by a proprietary, second-generation design using a single, continuous tendon to ensure a watertight design. No alternate methods shall be substituted for post-tensioning.
2.4.4 Sealant: All joints between panels shall be caulked along the exterior and interior surface of the joints. Exterior sealant shall be DOW CORNING 790 silicone sealant or equal.
Interior sealant shall be SIKAFLEX-1A elastic sealant (paintable) or equal. Exterior caulk reveals to be 3/8”x 3/4” deep so that sides of the joint are parallel for proper caulk adhesion. The back of the joint to be taped with bond-breaking tape to ensure adhesion of caulk to parallel sides.
2.4.5 Panel Connections: All panels shall be securely fastened together utilizing cast-in steel embeds and welding. All welding shall be done in conformance with AWS, Structural Welding Code latest revision. Steel is to be of structural quality, hot-rolled carbon complying with ASTM A304. No floating-in of connection plates shall be allowed.
2.4.6 Finishes, Accessories, and Fixtures
2.4.6.1 Stain and Paint:
2.4.6.1.1 Interior: Interior floors will be a two-component, water-based polyamide epoxy floor coating (gray, unless otherwise specified). Approved manufacturers: Sherwin Williams (Floor-Plex 7100), Armor poxy, or equal.
2.4.6.1.2 Exterior: Exterior slab top surface will be a two-component, polyamide epoxy floor coating. Roof shall be simulated cedar shake roof finish with color of Cedarwood Brown (HC103). Approved manufacturers: Sherwin Williams, Armor poxy, or equal.
Exterior walls and roof will be a water-based acrylic, water-repellent penetrating stain. Exterior walls shall be Barn board finish with color of Neutral Balance Tan (HC125). Approved manufacturers: United Coatings (Canyon Tone Stain), Sherwin Williams (H&C Concrete stain) or equal Clear Acrylic anti-graffiti sealer.
2.4.7 Doors and Frames: Comply with SDI-100. Galvanizing in accordance with ASTM A924 and A653 (minimum A60). Restroom entry doors: 3’-0” x 6’-8” x 1-3/4”. Chase door: 2’-8” x 6’-8” x 1-3/4” thick insulated, 18-gauge, metal doors with 16-gauge frames. Factory bonderized, primed, and finished in BOLT BROWN. Level 2, 1¾” heavy duty.
2.4.7.1 Door Hardware:
2.4.7.1.1 Cylindrical Lock: Commercial grade, 45H7AB14J626 Series mortise lock (40H series, ANSI A156.13, Grade 1). Satin Chrome finish. Core will be provided by the Customer. Faceplate: Stainless steel, brass, or bronze
2.4.7.1.2 Hinges: Self-Closing (spring) Hinges. ANSI A156.17 Grade 1 (3 per door). Stainless Steel Grade 304, US32D brushed satin finish.
2.4.7.1.3 Door Sweep: Nylon brush sweep with integral drip edge. ANSI/BHMA certified, UL
10C positive pressure approved.
2.4.7.1.4 Drip Cap: Aluminum drip cap with a minimum projection of 2 ½”.
2.4.7.1.5 Door Stop: ANSI 156.16 approved wall-mounted door stop. US26D brushed chrome finish.
2.4.7.2 Wall Vent: Extruded aluminum, min. .125” thickness, 6063-T5 alloy. Supplied with aluminum mesh insect screen and 204-R1 clear anodized finish.
2.4.7.3 Signs: Braille, characters, and pictograms to meet ADA requirements.
2.4.7.4 Windows: Stainless steel frames. Window glazing will be ¼” translucent Lexan.
2.4.7.5 Grab Bars: 18-gauge, type 304 stainless steel tubing, mounted 1-1/2 inches from the wall.
2.4.7.6 Toilet Paper Dispenser: 3/16” to 1/4” thick 304 stainless steel. Capable of holding three
(3) standard rolls.
2.4.7.7 Plumbing: Waterless Toilet. ADA compliant, 18-gauge type 304 stainless steel riser with seat cover.
2.4.7.8 Vault: Concrete material with a minimum holding capacity of 2,000 gallons. Inside of vault tank(s) to be lined with a coating applied per manufacturer specifications.
2.4.7.9 Vault Cleanout Cover: Steel frame with ¼” thick diamond plate steel lid. Hinged and configured for a padlock. Includes perimeter gasket for an airtight seal.
2.4.7.10 Vent Stack: 12” (nominal) diameter High-Density Polyethylene Pipe.
PART 3 – EXECUTION
3.1 Site Preparation (Manufacturer’s Recommendation)
3.1.1 All material, methods of construction, and testing & inspection shall conform to the applicable requirements of the codes and standards listed in the project specifications.
3.1.2 Stone shall be a minimum of 4” thick and down to firm subgrade. The vertical soil capacity under the stone shall be compacted to have a minimum bearing of 1,500 pounds per square foot (PSF). Stone shall be 3/8” or smaller followed by a course or topping of fines for final grading and compaction. Elevations and levelness of the prepared stone base shall be within ¼” in all directions.
3.1.3 Provide positive drainage around the building.
3.1.4 Provide Butyl Sealant between the vault and building floor.
3.2 Site Safety
3.2.1 Comply with all applicable OSHA standards for excavation.
3.2.2 No excavation will be left open without proper shielding or fencing.
3.3 Elevation
3.3.1 Excavate for the placement and installation of the toilet vault tank(s) to a depth that will allow the structure site to be free draining. After installation, the depth should allow for the stone base and leveling course beneath the toilet vault.
3.3.2 Finish floor elevation will be ½ - 1 inch above adjacent paved grade measured at the front (entrance) of the exterior slab.
3.3.3 The back of the building will be raised slightly higher to allow water to freely drain out of the toilet room(s). Positive elevation of ½ to 1 inch in total length of structure. Final building floor elevation to be within ± 0.05 feet of specified floor elevation.
3.4 Backfill and Compaction
3.4.1 Compact natural subgrade at the bottom of the vault excavation to a minimum vertical soil capacity of 1,500 PSF.
3.4.2 Install and compact stone base and leveling course to the specified elevation, ensuring levelness.
3.4.3 Set the vault(s) in place and check for proper alignment and levelness. Backfill around the structure(s) using excavated material suitable for backfilling or stone fill. Rocks or stone larger than 3 inches in maximum dimension shall be discarded.
3.4.4 Lift thickness for backfill material: loose lifts 6 inches for vibratory and static compaction respectively.
3.4.5 Use compaction equipment suited to achieve specified compaction for subgrade, stone base, and backfill. Vibrating equipment is used for compaction of course materials.
3.4.6 Intended final grade is flush with the top of the front floor slab. Allow for placement of topsoil to reach that grade (if required). Grade backfill away from the structure for positive drainage.
3.5 Pavement of Asphalt
The contractor shall lay new asphalt from the preexisting adjacent asphalt road to the foundation of the new structures. This includes the removal of soil to set the depth for replacement base stone and asphalt.
• The soil below shall be compacted to 1,500 PSF.
• A 2-inch layer of aggregate stone #57 will be spread and compacted above.
• The next layer shall consist of 4 inches of base asphalt followed by 2 inches of topping asphalt.
• Each of these layers shall be compacted using a roller to make a smooth surface without any deviation between the elevation of the building concrete pad and the preexisting road.
Site-Specific Asphalt Paving Areas:
• Peewees Site: The area to be paved is approximately 750 sq ft between the restroom and the road, including a tapered angle on the left and right of the building.
• Tail Race Site: The area to be paved is approximately 400 sq ft between the restroom and the road, including a tapered angle on the left and right of the building.
• For both sites: Shoulder stone will be added 6 inches from the edge of the asphalt pavement and taper down allowing for drainage and protection.
Note: Estimated paving amounts are approximate totals and not exact quantities. Due to the complexity of the buildings, the contractor is urged to do a pre-bid visit to determine exact quantities.
3.6 Submittals
The contractor shall submit the following to the COR:
• All manufacturers’ product literature, including methods and materials to be used.
• The manufacturer’s warranty covering the building against failure.
• The manufacturer’s warranty on the finish.