This document is a Sources Sought Notice (SSN) issued by the National Park Service (NPS) for the ACAD 312014 - Park Loop Road project. The purpose is to conduct market research and obtain information from both large and small businesses regarding their qualifications and interest in the work.
The project is located at Acadia National Park in Maine and consists of pavement improvements and other site work on the Park Loop Road, Egg Rock Overlook, and Precipice Parking Area. The construction magnitude is estimated between $1,000,000 and $5,000,000, and the NPS anticipates issuing a Request for Proposals in winter 2024. Bid, performance, and payment bonds will be required.
The NPS is requesting information from interested businesses, including company details, business size/socioeconomic status, bonding capacity, relevant experience, and intentions to submit a proposal. Responses are due by noon Mountain Time on 12/05/2024. The NPS will use the information to develop an acquisition strategy and determine if a small business set-aside is appropriate.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
12795 W. ALAMEDA PKWY
P.O. BOX 25287
DENVER, COLORADO 80225-0287
In Reply Refer to:
D5215 (DSC-CS)
ACAD 312014
Date: 11/21/2024
To: General Public (Via the Government’s Point Entry)
From: Brenda Smith, Contracting Officer, National Park Service, Denver Service Center
Subject: Sources Sought Notice
Reference: ACAD 312014 – Park Loop Road
This is a Sources Sought Notice (SSN) for the purpose of conducting market research. Proposals are NOT being requested, nor accepted at this time. Responses are being requested from both large and small businesses.
Purpose: The purpose of this notice is to gain knowledge regarding the type of interested businesses and their qualifications. The National Park Service (NPS) will use information obtained through this notice to develop an acquisition strategy.
The Government anticipates conducting a competitive acquisition for this requirement. The amount of interest or lack thereof will determine the possibility of a small business or other socio-economical small business set-aside for the solicitation. Analysis of the quality of responses to this source sought announcement will be considered in the market research being conducted, and in the making of any small business set-aside determination for this requirement.
Additional Information: No proposal package, solicitation, specification or drawings are available with this notice.
Cost Reimbursement: Response to this announcement is strictly voluntary; no reimbursement will be made for any costs associated with providing information in response to this sources sought announcement or any follow-up information requests.
North American Industry Classification System (NAICS) code: 237310
Small Business Size Standard: $45,000,000
Solicitation: The NPS anticipates issuing a request for proposals in the winter of 2024.
Bonding: The NPS anticipates bid, performance and payment bonds will be required.
Project Description:
Project Conditions:
The project is located at Acadia National Park on Mount Desert Island: Hancock County, Maine.
IAW FAR 36.204, the construction magnitude is between $1,000,000 and $5,000,000.
The surrounding area is rural with staging areas in locations mutually acceptable to the Contractor and the Contracting Officer.
The construction site is 05 miles from nearest suppliers and lodging facilities.
The Park will remain open during construction, thus contract activities and logistics must be structured and scheduled to minimize visitor impact.
The site requires protective measures to ensure the surrounding area remains undisturbed.
The project requires the expertise of a historic masonry rehab contractor with demonstraited experience and qualifications to repair stone and brick masonry structures.
The anticipated period of performance of 180 calendar days including any potential weather shutdown.
There are periodic federal holiday shutdowns mandated through the construction season.
Project Scope:
The work consists of:
1. Pavement improvements and other site improvements at the following roads and parking areas within Acadia National Park.
a. Park Loop Road, from the intersection with Paradise Hill Road at Mile Post 0.0 to Mile Post 5.0
b. Egg Rock Overlook
c. Precipice Parking Area
2. The major elements of work include:
a. Mobilization and demobilization.
b. Installation, maintenance, and removal of maintenance of traffic and erosion control measures.
c. Road and parking area pavement improvements including pavement crack sealing, transition milling, partial and full depth pavement patch repairs, pavement milling, and hot mix asphalt (HMA) pavement overlay.
d. Existing swale/ditch cleaning and/or restoration including regrading and repairs to stone lining.
e. Construction of new stone-lined and paved swales/ditches.
f. Resetting guardwall stones and placement of aggregate topsoil to regrade shoulders and back up pavement edges.
g. New striping and pavement markings.
h. Replacement, rehabilitation, and cleaning of selected culverts of various types at several locations, including regrading near inlets and/or outlets and, as necessary to facilitate culvert replacement, removal and resetting/reconstruction of stone masonry culvert headwalls.
i. Rehabilitation of selected brick drop inlets, dry-laid stone masonry drop inlets, and dry-laid stone masonry stone culverts.
j. Replacement of permanent traffic control signs, including posts.
Submittal Contents: Interested (small and large) businesses should submit the following information:
(1) Company name, SAM UEI, address, point of contact, telephone number, and email address.
(2) Business type: Classification as a Large or Small Business under the above listed NAICS, Small Business
Administration (SBA) certified Historically Underutilized Business Zone (HUBZone), Veteran-Owned Small Businesses (VOSB), Service-Disabled Veteran-Owned Small Businesses (SDVOSB), SBA certified Woman Owned Small Business (WOSB), Economically Disadvantaged Woman Owned Small Business (EDWOSB). The size of a small business firm includes all parents, subsidiaries, affiliates, etc.—see 13 CFR 121.108.)
Misrepresentation of size status can result in penalties.
(3) Statement regarding your company’s bonding capacity. Letters from bonding companies are not required at this time.
(4) Information demonstrating experience and capability on projects of same or similar size, scope and magnitude, and constructed under similar conditions.
(5) In addition businesses may submit existing marketing materials such as capability statements and brochures.
Submittal Due Date/Time: Noon Mountain Time, 12/05/2024
Submit To: brenda_smith@nps.gov, tyler_joseph@nps.gov
Sources Sought – Survey Questions
Project Description and PMIS: ACAD 312014
1) What is your experience as the Prime contractor for Federal Government constructions contracts?
2) What is your experience as a Subcontractor for Federal Government constructions contracts?
3) How does your firm intend on complying with local construction building licensing and permitting for Maine?
4) This project will require insurance and Performance and Payment Bonds. What is your firms *stated bonding capacity (no letters required)?
5) This project will contain Division 1 submittal requirements that must be completed prior to receiving the Notice to Proceed. How is your firm prepared for this requirement?
6) What is your company’s recent experience with asphalt pavement, pavement markings, culvert repair, and historic masonry restoration/preservation. (please list the last 5 projects, project description, year construction)?
7) What is your company’s experience working in Park lands with visitors?
8) This project will contain clauses for Construction Warranty and Liquidated damages. How is your firm prepared for this requirement?
9) What estimated percent of this work will your company self-perform?
a. ☐100%
b. ☐about 75%
c. ☐about 50%
d. ☐about 25%
e. ☐about 15%
10) What is your company’s commitment to submit a proposal for this project if and when a Construction solicitation is posted?
a. ☐100%
b. ☐50%
c. ☐Less than 50%
11) What will influence your company’s commitment for submitting a proposal for this project?
*Please check all applicable boxes.
a. ☐Solicitation posting (approximately January 2025)
b. ☐Schedule completion date for all construction by October 2025.
c. ☐Details of the specs and drawings for the Request for Proposal
d. ☐Other commitments/contracts
e. ☐Other (write in)
Submittal Due Date/Time: Noon Mountain Time, 12/05/2024