A11-053: High Efficiency Fans for Underhood Cooling of Military Vehicles

PROJECTED CMMC LEVEL REQUIREMENT:

N/A

TECHNOLOGY AREAS:

Ground Sea

MODERNIZATION PRIORITIES:

KEYWORDS:

Fan, Propulsion, Engine Cooling, Airflow, Thermal Management

ADDITIONAL INFORMATION

OBJECTIVE:

Highly efficient cooling fans that can be integrated for underhood cooling of military combat, tactical and commercial vehicles which will improve vehicle operational capability in hot climates.

DESCRIPTION:

Currently many vehicles in the Army fleet are using inexpensive, low technology, automotive axial flow fans which are in the neighborhood of 43% efficiency (static). More advanced technology mixed-flow fans have been implemented into a few vehicles which are in the neighborhood of 75% efficient. The static efficiency of a fan is a measure of how effectively a fan moves air against the system resistance. Static pressure times the airflow rate times a constant divided by static efficiency equals fan power. If static efficiency is increased, with the same airflow and pressure coming out of the fan, then the horsepower requirement for the fan is reduced, thereby providing more power for mobility. This additional power is significant, and can contribute to upwards of 8% more horsepower to be utilized for other vehicle requirements, or for operating in hot ambient environments. With improved fan efficiencies, more power can be dedicated to powering up hills, along with accelerating along level surfaces, or powering auxiliary equipment. Additionally, better vehicle fuel economy can also be achieved by operating with more efficient fans. Building a compact fan that fits within the tight space-claim of military vehicles is paramount. Military vehicles generally require a cooling system capable of maintaining engine and transmission operating temperatures within specified limits while operating continuously under full load at 0.7 Tractive Effort to Gross Vehicle Weight ratio (TE/GVW) under the maximum conditions of +120 degrees F, and the cooling system must be capable of not exceeding temperature limits while operating at rated engine power (tractive effort is the force exerted at the running gear to propel the vehicle). At the end of Phase 3, meeting this full-load tractive effort at 120 degrees F is the goal of the program for the target vehicles utilizing the fan developed under this SBIR. The fan will target both combat and tactical vehicles. The combat vehicle planned for integration of the fan will be the Paladin Integrated Management (PIM) vehicle, known as the PIM Paladin. The PIM Paladin is targeted for a cooling upgrade. The PIM has a Bradley powerpack with a different integrated cooling pack. Independent PIM TARDEC full-load cooling tests are upcoming within the next year. The tactical vehicle target for integration of the fan will be a Joint Light Tactical Vehicle (JLTV). The JLTV most closely matches the requirements of a commercial truck and thus satisfies the commercialization requirement in the SBIR goals. The SBIRs initial build will be for fans with a minimum static efficiency of 85%. This will be done within a minimal space-claim that will allow for retrofitting into existing military vehicles. The first phase will be a study to define the efficiency and component geometry of an underhood fan using technical engineering analysis which will include a Computational Fluid Dynamics (CFD) study. This CFD modeling will provide a defined envelope for the pressure and flow requirements of the PIM and JLTV vehicles. It will also provide details of the blade and housing design of the fan. In phase 2, an initial prototype will be built and component tested. Additional CFD modeling will occur as the phase 1 modeling will be validated, and improvements and design improvements will be analyzed. Two fans will then be provided to the government for internal testing. In Phase 3, the contractor will be provided a vehicle from the Army for integrating the fan and conducting relevant testing. Testing will focus on maintaining engine and transmission operating temperatures within specified limits while operating continuously under full load at 0.7 Tractive Effort to Gross Vehicle Weight ratio (TE/GVW) under the maximum conditions of +120 degrees F.

PHASE I:

Complete a feasibility study and preliminary design report for a high-efficiency fan build that fits the geometry space claim defined by the Government. This will include a Computation Fluid Dynamics study which will define and develop the fan requirements. Following this study, deliver sufficient initial fan design details to the Government to allow analysis within TARDEC’s CASSI business group.

PHASE II:

Build an initial prototype fan, and component test the fan. Use CFD to refine the fan design. With the lessons learned from this initial prototype, design and build a follow-on fan. Complete the component testing. Make fan available for government testing.

PHASE III DUAL USE APPLICATIONS:

With the vehicles provided by the Army integrate the fan into the vehicles. Complete full-throttle, hot climate testing. If successful, complete engineering change proposal for the Army vehicle(s). Production fans can be then integrated into vehicles, as required. Commercial truck applications which more closely match with the JLTV vehicle will be explored in order to reduce the overall production costs to the government.

REFERENCES:

Fan Handbook: Selection, Application, and Design, Bleier, Frank, Copywrite 1997, ISBN-10: 00700593301.

Introduction to Fluid Mechanics, Fox, R, McDonald, A, and Prichard, P. Copywrite 2004, ISBN: 0-471-20231-22.

Mechanical Engineering Reference Manual for the PE exam, Lindeburg, M. Copywrite 2006, ISBN-13: 978-1- 59126-049-3

3.

AMCP-706-361. Engineering Design Handbook. Military Vehicle Power Plant Cooling.1975, 1998.4.

TECHNICAL POINT OF CONTACT (TPOC):

None