12 Mile Bayou, Shreveport, Louisiana, P. L. 84-99 Emergency Bank Stabilization, West Agurs Levee Sta. 196+90 & 427+10
Solicitation number
Not on record
Issued by

About this file

This document is a determination for consolidation of contract requirements for general repair and construction along 12 Mile Bayou in Shreveport, Louisiana under the P.L. 84-99 Emergency Bank Stabilization program. The U.S. Army Corps of Engineers Vicksburg District plans to award a firm fixed price contract to stabilize riverbanks at West Agurs Levee Stations 196+90 and 427+10 through a total small business set-aside solicitation. The work involves construction of a longitudinal stone dike and stone bank paving at the sites. Consolidating the requirements into one contract is necessary and justified to efficiently coordinate work, realize cost savings over multiple contracts, accommodate construction windows, and allow contractors to organize work more efficiently. Market research indicates sufficient small businesses exist to compete for the consolidated requirements, valued at $2,142,335.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE ARMY

U.S. ARMY CORPS OF ENGINEERS, VICKSBURG DISTRICT

DETERMINATION FOR CONSOLIDATION

W912EE22B0007 FIRM FIXED PRICE FOR GENERAL REPAIR AND

CONSTRUCTION ALONG 12 MILE BAYOU, SHREVEPORT, LOUISIANA, P.L. 84-99

EMERGENCY BANK STABILIZATION, WEST AGURS LEVEE STA. 196+90 & 427+10

COORDINATION PAGE:

The following signatures indicate concurrence with the contents of this document.

Amanda J. Proctor Assistant District Counsel

R. Ellis Screws Contracting Officer, Construction and A-E Branch

CONSOLIDATION OF CONTRACT REQUIREMENTS DETERMINATION

(As prescribed by FAR 7.107-2 and AFARS 5107.107-2)

DEPARTMENT OF THE ARMY

U.S. ARMY CORPS OF ENGINEERS, VICKSBURG DISTRICT

W912EE22B0007 FIRM FIXED PRICE FOR GENERAL REPAIR AND

CONSTRUCTION ALONG 12 MILE BAYOU, SHREVEPORT, LOUISIANA, P.L. 84-99

EMERGENCY BANK STABILIZATION, WEST AGURS LEVEE STA. 196+90 & 427+10

Rationale

(1) Consolidation may provide substantial benefits to the Government. However, because of the potential impact on small business participation, before conducting an acquisition that is a consolidation of requirements with an estimated total dollar value exceeding $2 million, a written determination shall be made that the consolidation is necessary and justified in accordance with 15 U.S.C. 657q, after ensuring that--

(a) Market research has been conducted;

(b) Any alternative contracting approaches that would involve a lesser degree of consolidation have been identified;

(c) The determination is coordinated with the agency's Office of Small Disadvantaged Business Utilization or the Office of Small Business Programs;

(d) Any negative impact by the acquisition strategy on contracting with small business concerns has been identified; and

(e) Steps are taken to include small business concerns in the acquisition strategy.

2. Introduction:

U.S. Army Corps of Engineers (USACE), Vicksburg District (MVK), plans to solicit offers for 12 Mile Bayou, Shreveport, Louisiana, P.L. 84-99 Emergency Bank Stabilization, West Agurs Levee Stations 196+190 and 427+10. MVK has conducted analysis and market research that demonstrates consolidation of requirements in this procurement is both necessary and justified. FAR 2.102 defines consolidation as

(1) a solicitation for a single contract, a multiple-award contract, a task order, or a delivery order to satisfy -- (i) two or more requirements of the Federal agency for supplies or services that have been provided to or performed for the Federal agency under two or more separate contracts, each of which was lower in cost than the total cost of the contract for which offers are solicited; or (ii) requirements of the Federal agency for construction projects to be performed at two or more discrete sites; or;

(2) separate contract as used in this definition, means a contract that has been performed by any business, including small and other than small business concerns.

3. Description of the Procurement Action:

(1) Project Description:

MVK provides rehabilitation to active levees in the PL 84-99 Rehabilitation and Inspection Program (RIP). West Agurs Levee Stations 196+90 & 427+10 are located along Twelve Mile Bayou in Caddo Parish, Shreveport, Louisiana. Due to bank erosion issues along Twelve Mile Bayou, the levee section is threatened. While some level of protection is provided by the existing section (at the time of the existing ground survey), it is not believed that the levee would perform to capacity in the event of a project design flood. The high-water event of 2018, where the Red River remained at flood stage for 61 days, created the need for repairs at the two (2) sites. During this high-water event, the riverbank began to cripple, causing USACE to intervene in the rehabilitation of the bank at levee stations 196+90 & 427+10. This project requires the bank to be stabilized with a longitudinal stone dike and stone bank paving at the levee stations.

(2) Acquisition Strategy/Procurement Summary:

The procurement will be advertised as a Total Small Business Set-Aside under Solicitation No. W912EE22B0007, with the intent to award one (1) Firm Fixed Price (FFP) contract in accordance with FAR 16.202-2. The estimated value of this procurement is $2,142,335.00. This procurement will meet repair and construction mission requirements under North American Industry Classification System (NAICS) code 237990, Other Heavy and Civil Engineering Construction with a size standard of $39.5M. The construction period will not exceed two (2) years. MVK has historically utilized this type of contract for similar requirements to successfully execute projects on tight schedules at reasonable costs. Use of a FFP contract is in the best interest of the Government with respect to timeliness, oversight, and administrative costs.

(3) Applicability of Consolidation:

This requirement meets the definition of consolidation requirements, which is described as a solicitation of a single contract to satisfy the requirements of the Federal agency for construction projects to be performed at two or more discrete sites.

The total estimated value of the requirements exceeds the $2M threshold. MVK intends to consolidate the requirements in the PL 84-99 Rehabilitation and Inspection Program (RIP): Twelve Mile Bayou in Shreveport, Louisiana, P.L. 84-99, West Agurs Levee

Stations 196+190 and 427+10. By consolidating these requirements, MVK will be able to efficiently coordinate and respond to the dynamic requirements of the bank stabilization at a significant savings of cost and time. Additionally, consolidation will allow MVK to accommodate the stone placement scheduling window which is affected by high and low water events and the timing of funding from Congress. This also allows contractors to organize their work more efficiently, offer lower unit cost with a more effective economy of scale, and more efficiently schedule their equipment for the best regional approach to meet the needs of the Corps of Engineers bank stabilization program.

4. Results of Market Research:

Current Market Research

(1) Dynamic Small Business Search: DSBS search parameters included all SBA Economic Group Categories, in the states of Arkansas, Louisiana, Mississippi, and Tennessee and produced a listing, where at least one word of the capabilities’ narrative, “Bank Stabilization”, with NAICS code 237990, randomized by original start time of search: 2022-04-06, received which received matches as seen below:

PARAMETERS:

NAICS 237990

Locations: Arkansas, Louisiana, Mississippi, and Tennessee Keywords: Bank Stabilization

RESULTS:

Small Business Sub‐ Category

No. of SBs Registered

HUBZone Certified 3 8(a) 2

SDB Certified 0 Woman or Women Owned 4 Service-Disabled Veteran 1

Veteran 2

The search returned a total of nine (9) firms within the above Economic Group Categories; however, seven (7) of the firms identified as a combination of two or more Small Business Sub-Categories.

Procurement History

(2) There are no previous requirements specifically for West Agurs Levee Station for bank stabilization and/or levee construction. However, within the last five (5) years (FY 2018- 2022), there have been six (6) requirements awarded for Bank Stabilization and Levee Construction. The solicitations were advertised and awarded to a combination of both Large and Small Business Concerns. Details are listed below:

Table A. Historical Construction Contract Awards:

Contract#

Contractor

LG/

SM

Procurement Method

Contract Type

Contract Value

# of Bids

W912EE21C0008 Keller North America

LG Unrestricted FFP $9,118,587.50 5

W912EE21C0007 Wilco Inc. SM Total Small FFP $546,180.00 7 W912EE21C0006 Anderson

Construction Co.

SM Total Small FFP $5,889,000.00 2

W912EE19C0005 Riverside Construction Co.

SM Total Small FFP $989,625.00 5

W912EE18C0016 Luhr Bro. Inc. LG Unrestricted FFP $28,117,000.00 5 W912EE18C0011 BIS Services SM HUBZone FFP $ 1,061,690.00 4

TOTAL: $45,722,082.50

During the internal historical review period, in any one instance of responding to a bank stabilization establishment Invitation for Bid, two or more small business firms have submitted bids. Hence, there is sufficient reason to believe competition will result in receipt of two or more bids.

There are no negative impacts by the acquisition strategy on contracting with small business concerns. Small businesses have been determined responsible, awarded, and successfully completed this type of work approximately 80% of the time within the last four (4) years. Current and historical participation of small business concerns for this type of procurement is well represented. This project is mission critical and procuring this award as a 100% Total Small Business Set-Aside allows for maximum practicable participation by small business concerns.

Further market research was conducted to sufficiently document that it was in the Government’s best interest to solicit this acquisition as a total small business set-aside.

Out of the nine (9) companies identified, only four (4) of the companies actually possess the capabilities of completing this type of work. Neither of those 4 companies identified as capable fall into the same socioeconomic category. Also, the lack of past history for this type of work being performed in this area led to the recommendation that this procurement be set aside for total small business. This market research indicates a high expectation of a two or more bid response from one of the socioeconomic groups.

5. Alternative Contracting Approaches and Rationale for Rejection:

(1) In identifying that one (1) stand-alone FFP contract as the best solution for satisfying this requirement, the district also considered utilizing a SATOC. SATOCs were not considered in detail as an alternative contracting approach because SATOCs have not been used for this type of work in the past and there is not sufficient time to compete the MATOC awards. Additionally, after award, there is no competition under a SATOC, which makes it difficult to negotiate agreements. The intent of this analysis was to address all alternative contracting approaches that would involve a lesser degree of consolidation, or no consolidation.

The following analysis addresses alternative contracting approaches in detail:

a. Alternative 1: Two (2) Individual FFP Contracts: The consolidation of one (1)

FFP contracts would substantially exceed the benefits of having two (2) individuals to perform the work along the West Agurs Levee. The benefits may include cost savings, quality improvements, reductions in acquisition cycle times, better terms and conditions, and any other identifiable benefits. Though awarding two (2) individual contracts could provide a lesser degree of consolidation, or no consolidation at all, the benefits of awarding one (1) consolidated contract substantially exceed the benefits of two (2) individual contracts for the reasons outlined below.

(i) Quality. The iterative process of working with experienced contractors tends to generate a more thorough shared understanding between the contractor and Government for the government’s requirements. While the potential exists for two (2) individual contract holders to offer competition, one (1) contractor is afforded a greater opportunity to better understand the expectations of the Government in an effort to build project experience and capability for follow on support.

(ii) Acquisition Cycle. According to the PALT, the average time to acquire two

(2) individual contracts is approximately 120 calendar days. Each contract takes, on average, 60 calendar days to award. Some projects may require a significant amount of back and forth in the process of clarifications. Conversely, the average time to award one FFP is 60 calendar days. This is possible due to all pre-award processes being captured within the base contract. The estimated procurement lead time saved is 60 days on the contract. The awardee has the proper clearance and can be provided access to information regarding the project as soon as it’s available to MVK.

Table B – Time Savings Comparison of In-house Procurement to Award One (1) FFP versus Two (2) FFP Individual Contracts.

One (1) FFP Contracts Two (2) Individual Contracts IFB (60 days) X 1 contracts 60 IFB (60 days) X 2 contracts 120

Total – 60 120

(iii) Cost Savings. Per 15 U.S.C. § 657q(c)(2)(B), “savings in administrative or personnel costs alone do not constitute a sufficient justification for a consolidation of contract requirements” unless the total amount of the cost savings is expected to be substantial in relation to the total cost of the procurement.

(a) Table 1 below compares the estimated administrative and personnel costs required for a consolidated FFP contract (historically IFB). These costs are based on standard labor costs developed by MVK Contracting for FY18procurements, along with historical average procurement support costs for Cost Engineering Division, Programs and Project Management Division (PPMD), and Engineering and Construction Division for acquisition coordination, document review, IGE development and site visit attendance. In addition, the average design and procurement costs provided by the Vicskburg District Project Manager for in-house labor required for the engineering and design, drafting, and review of a FFP contract by engineering, cost engineering, and construction branch is approximately $60,000. The in-house costs were derived from historic FFP contract acquisitions for this type of work using the labor rates for the different disciplines mentioned above and the combined total costs associated for each activity required from project conception to award.

(b) Based on information provided by the Vicksburg District Contracting Division, as shown in Table 2 below, the total cost required to award one (1) FFP contract equal $640,000.00. As shown in Table 3 below, awarding two (2) individual FFP contracts would cost $710,00.00. The one (1) single FFP method would reduce the procurement/close-out cost by $355,000.00.

6. Consolidation Benefit Analysis:

Table 1 – Cost to Award One (1) Consolidated FFP Contract

ORGANIZATION LABOR

Contracting ($30K each) $30,000 Cost Engineering ($30K each) $30,000 Engineering ($30K each) $30,000 Construction ($30K each) $30,000 Mobilization and Demobilization ($200K each) $200,000 Subtotal $320,000 Total Cost to Award One (1) Consolidated FFP

$320,000

Table 2 – Cost to Award Two (2) Individual FFP Contracts

ORGANIZATION LABOR

Contracting ($30K each) $60,000 Cost Engineering ($30K each) $60,000 Engineering ($30K each) $60,000 Construction ($30K each) $60,000 Mobilization and Demobilization ($200K each) $400,000 Subtotal $640,000 Total Cost to Award Two (2) Individual Contracts $640,000

Table 3 – Cost Savings Comparison of In-house Labor for One (1) Consolidated FFP contract vs Two (2) Individual FFP contracts

Acquisition Approach

1 Consolidated FFP Contract Cost

2 Individual Contracts Cos

Cost per Procurement of FFP contract $320,000 $640,000 Contract Close Out ($5K each) $5,000 $10,000 Subtotal $325,000 $650,000 Other In-House Labor ($30K each) $30,000 $60,000

Total 355,000 $710,000 Cost Savings to Award One (1) Consolidated Contract vice Two (2) Individual Contracts $355,000

Dollars are based on actual number of FY18 procurements and the current projections for FY22. As demonstrated in Table 3, the costs of awarding two (2) contracts are approximately 50% of the cost of awarding two (1) consolidated contract. In sum, MVK estimates that the use of one (1) consolidated FFP contract would generate $355,000.00 in labor savings for the life of the consolidated contract. A FFP contract maximizes the opportunity to acquire high quality, professional services at competitive prices, while minimizing acquisition time, and performance and schedule risks.

Table 4 – Analysis Summary

BENEFIT 1 Consolidated FFP 2 Individual FFP

Quality High High

Acquisition Cycle 30 days 60 days

Administrative Cos Low High

7. Bundling:

Bundling (FAR 7.107-3) and/or Substantial Bundling (FAR 7.107-4) are not applicable to this procurement. A bundled requirement is considered necessary and justified if the agency would obtain measurably substantial benefits as compared to meeting its agency’s requirements through separate smaller contracts or orders. Substantial Bundling is any bundling that results in a contract with an estimated value of $8 million or more for the Department of Defense. This acquisition does not meet the definition of bundling since the government is not attempting to consolidate two or more requirements previously provided or performed under separate contracts into a single contract unsuitable for small business. The selected approach is capable of fulfilling all requirements under the FFP contract.

8. Considerations, Facts, Reasoning Supporting the Determination:

DD2579 has been signed by the Contracting Officer, Deputy for Small Business and SBA Procurement Center Representative. All concur that consolidation of this requirement is both necessary and justified. Consolidation will allow the districts to efficiently coordinate and respond to the dynamic requirements of these MR Stone Placement, bank stabilization, and Levee setback requirements. Consolidation will result in a significant savings of cost and time, as well as accommodate river stage dependent construction and environmental windows. Consolidation will also allow river contractors to more effectively organize their work, lower unit costs due to economy of scale, and more efficiently schedule their equipment and resources to achieve an efficient regional approach to meet the needs of the Corps of Engineers Mississippi River dike and stone navigation structure programs. Moreover, consolidation of this requirement is both necessary and justified because the benefits of consolidation are critical to the success of MVK’s mission and the procurement strategy provides participation to small businesses to the maximum extent practicable.

9. Summary:

(1) Although this total small business FFP solicitation constitutes consolidation of stone bank stabilization and construction requirements at two (2) discrete sites into one (1) consolidated FFP contract, this approach provides the best combination of competitive procedures, timely acquisition, cost efficiency, quality, and capable prime contractors to execute maintenance bank stabilization on the MVK navigation channels.

(2) For the reasons indicated above this consolidation is necessary and justified and is critical to the agency’s mission success. While there is a minimum of $355,00.00 in cost benefits associated with this consolidation, these necessary and justifiable benefits significantly increase the likelihood of mission success, reduce acquisition cycle times, provide improved quality that will enhance performance or efficiency, as outlined in FAR 7.107-2(c), and are substantial. The bank stabilization program is critical to the mission of USACE in that it provides navigable Federal waterways which are vital to many aspects of Louisiana’s economies.

(3) Other alternatives noted above were considered, however, they would result in significantly higher costs and increased acquisition cycle time. Additionally, it is significantly less burdensome for the District’s Contracting and Operations Divisions to administer a consolidated scope of work for the West Agurs Levee Stations than numerous stand-alone contract actions. The findings of the market research and the documentation provided herein support the conclusion that consolidation of requirements is both necessary and justified, based on sound business judgment in view of the size, complexity, and potential number of efforts to be executed in support of MVK’s Civil Works program, and the consolidated approach provide advantages that substantially exceed the benefits of an approach that provides less consolidation.

10. Program Manager/Requiring Activity Justification: Market research has been conducted utilizing dynamic online searches in conjunction with a comparison of historical data from previous procurements of similar size, scope and complexity and the determination has been made that there is a reasonable expectation of receiving offers from (2) two or more responsible small business concerns that are competitive in terms of fair market prices, quality, and delivery. The market research does not support a further set-aside of the requirement into any specific socio-economic programs beyond a total small business set-aside.

Pursuant to AFARS 5119.202-1(1), I hereby support the consolidation of 12 Mile Bayou, Shreveport, Louisiana, P.L. 84-99 Emergency Bank Stabilization, West Agurs Levee Sta. 196+90 & 427+10.

Milton Beverly Date Signed Project Manager

11. Office of Small Business Program Coordination: Pursuant to FAR 7.107-2(a)(3), I agree that a consolidated requirement for 12 Mile Bayou, Shreveport, Louisiana, P.L.

84-99 Emergency Bank Stabilization, West Agurs Levee Sta. 196+90 & 427+10 is justified and necessary.

Demetric Erwin, Deputy Date Signed Office of Small Business Programs

DETERMINATION

Based on the foregoing rationale, I hereby determine, pursuant to the Federal Acquisition Regulation Supplement 7.107-2 and Army Federal Acquisition Regulation Supplement 5107.107, that the consolidation of the requirements for 12 Mile Bayou, Shreveport, Louisiana, P.L. 84-99 Emergency Bank Stabilization, West Agurs Levee Sta. 196+90 & 427+10 is both necessary and justified and will serve the best interests of the Government. In accordance with AFARS 5119.202-1, all preference program (socio-economic programs) were considered, and it has been determined to be in the best interest of the Government to advertise this consolidated requirement as a total small business set-aside.

Davita S. Baloue Chief, Vicksburg District Contracting Office

Attachments:

Market Research DD Form 2579 Informal Acquisition Plan

DEPARTMENT OF THE ARMY
W912EE22B0007 FIRM FIXED PRICE FOR GENERAL REPAIR AND CONSTRUCTION ALONG 12 MILE BAYOU, SHREVEPORT, LOUISIANA, P.L. 84-99 EMERGENCY BANK STABILIZATION, WEST AGURS LEVEE STA. 196+90 & 427+10
COORDINATION PAGE:
The following signatures indicate concurrence with the contents of this document.
2022-07-06T16:00:00-0500
SCREWS.ROBERT.1384614503
2022-07-07T07:41:01-0500
BEVERLY.MILTON.JR.1268010773
2022-07-08T08:10:18-0500
ERWIN.DEMETRIC.THOMPSON.1230772092
2022-07-08T09:22:39-0500
PROCTOR.AMANDA.JANE.1604271360
2022-07-13T13:36:50-0500
BALOUE.DAVITA.S.1230771460

File details come from the government source that posted it. Updated .