A10_2024-05_Model_Contract_Exh_A_-_Scope_of_Work.docx

DOCX document 60 KB Posted

Attached to
IFB 2024-05: Platform Holly Caretaker Services
Solicitation number
0000032810
Issued by
Santa Barbara County, Santa Barbara City, University of California-Santa Barbara CDP, California

About this file

This document is a Scope of Work for a Model Contract issued by the California State Lands Commission (Commission) for caretaker services on Platform Holly located in the Santa Barbara Channel. The contract requires a contractor to provide transportation, maintenance, and inspection services for the platform after it has been hardened to eliminate regular staffing needs. The services include bimonthly half-day and full-day trips to the platform to inspect and maintain navigation aids, the platform's solar power system, security fencing and cameras, and to conduct visual inspections of the platform. The contract term is one year with the possibility of renewals to allow the contractor to complete the work.

The contractor must be able to safely transport Commission staff and up to four others to and from the platform using properly permitted, insured, and licensed watercraft. The contractor will be required to respond to platform safety needs with 48-hour notice throughout the year. Pricing is based on the billing rates provided in Exhibit B. The contract has a mandatory 3% participation requirement for Disabled Veteran Business Enterprises. No additional funding or amendments to the contract are guaranteed.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MODEL CONTRACT IFB Number 2024-05 Page 1 of 4 State Lands Commission | [Contractor Name] Platform Holly Caretaker Services

EXHIBIT A

SCOPE OF WORK

Introduction and Background Comment by Shrestha, Dev@SLC: Bidder to update the header of this Model Contract Exhibit A with the Bidder's business name.

Established in 1938, the California State Lands Commission (Commission) is composed of the Lieutenant Governor, the State Controller, and the Governor’s Director of Finance. The Commission is primarily a land and resource trust manager. It manages approximately 4 million acres of California's sovereign Public Trust lands and resources that were received upon admission into the Union in 1850. It also manages other lands that the federal government conveyed to the state (commonly known as school lands) and oversees the management of Public Trust lands legislatively granted in trust to over 70 local jurisdictions. The Commission also enforces the protections of the Public Trust Doctrine, the State’s property rights, and important environmental quality and marine pollution prevention laws.

Platform Holly stands in 211 feet (64 m) of water approximately two miles (3.2 km) southwest of Coal Oil Point (34°23'23.7"N 119°54'22.5"W). The platform was installed in 1965 and, until 2015, produced oil and gas from the South Ellwood Oil Field which was transported via subsea pipelines, to an onshore facility for processing and downstream transport to market. The platform was shut-in after the 2015 Refugio Oil spill near Gaviota and since 2017, has been under the control of the State of California, through the Commission.

The SLC has plugged and abandoned the platform’s 30 wells, including removing the conductor casing, and is planning to decommission the platform sometime after 2025. In the interim, the Commission is hardening the platform to eliminate regular staffing needs by decoupling the platform from any shore-based utilities or power, removing oil production equipment, eliminating sources of spill risk, and installing solar power, security monitoring equipment, and navigation hazard avoidance equipment.

Purpose The purpose of this contract is to provide a contractor to provide caretaker services for the Platform after hardening is complete.

1) Location of Work – Platform Holly, located in the Santa Barbara Channel, two miles from Coal Oil Point, in Santa Barbara County, California.

2) Services and Deliverables

a) Contractor shall provide all labor, equipment, transportation, supplies, materials, incidentals, licenses, and permits necessary to complete the services described herein.

b) Contractor shall maintain facility emergency and response plans, such as the spill response plans, and other plans as directed by the Commission.

c) Billing rates shall be pursuant to Exhibit B, Tables B-1 and B-2

d) Services (detailed below) will include providing transportation (for Contractor staff and at least 4 others) and services to inspect and provide repair and maintenance of the equipment installed during platform hardening (see below).

e) Schedule: The inspection schedule may vary by needs but is anticipated to require one trip every two months (the “Work”) lasting 8-10 hours.

f) Task 1: Half-Day Transportation to and from Platform Holly

i) Contractor will be required to procure waterborne transportation for Contractor staff and at least 4 others (CSLC or its agents) to and from Platform Holly to perform the Work.

(1) 4-hour duration

(2) Transportation must be from Santa Barbara Harbor or another facility.

(3) For purposes of bidding, access from the Goleta Pier or Ellwood Pier cannot be assumed as available.

(4) The watercraft provided under this task shall be properly permitted, insured, licensed, and of an industry-standard quality necessary to ensure safety during boarding and off-boarding and of size appropriate to crew and staff necessary to complete tasks.

(5) All watercraft must be crewed by qualified staff including, at a minimum, the captain and the first officer.

ii) Transportation will be a round trip to and from the Platform once every two months or on a schedule that is agreed upon by the CSLC.

(1) In addition, Contractor will be required to obtain transportation to respond to Platform Holly safety needs with 48-hour notice, throughout the year.

iii) Rope Swing Safety - Platform Holly has four decks and is accessed by a rope swing from a crewed vessel. Vessels will likely need to tie up at a nearby buoy during the inspections. The Platform has one platform crane that will be operational. The crane is capable of lifting 60,000 lbs and can be used as necessary to move personnel or equipment to/from the vessel. The Platform will remain unstaffed so contingencies must be developed by Bidders to safely perform the Work in the absence of platform-based personnel to assist. Swing rope transfers are a method for offshore oil and gas workers to move between vessels and platforms. The Contractor must follow all training, safety protocols, and best practices when conducting swing rope transfers including, but not limited to:

(1) Preparation: Ensure the transfer area is clear of obstructions and has non-slip deck coating. The captain should have clear visibility of the transfer area, either directly or via CCTV.

(2) Personnel: Verify personnel competencies and ensure they understand safety aspects. Personnel should wear a securely fastened floatation vest. Never transfer alone.

(3) The Ropes: Inspect swing ropes for wear and damage, and conduct load tests. One rope is used to transfer from boat to platform, anchored above the platform's landing area. The other rope transfers personnel from platform to boat, anchored over the water.

(4) The transfer: Grab the rope above the middle knot or at eye level. Swing only when ready, and don't swing with extra weight. Pass baggage over first.

g) Task 2: Full-Day Transportation to and from Platform Holly

i) Contractor will be required to procure waterborne transportation for Contractor staff and at least 4 others (CSLC or its agents) to and from Platform Holly to perform the Work.

(1) 8-hour duration

(2) Transportation must be from Santa Barbara Harbor or another facility.

(3) For purposes of bidding, access from the Goleta Pier or Ellwood Pier cannot be assumed as available.

(4) Watercraft provided under this task shall be properly permitted, insured, licensed, and of an industry-standard quality necessary to ensure safety during boarding and off-boarding and of size appropriate to crew and staff necessary to complete tasks.

(5) All watercraft must be crewed by qualified staff including, at a minimum, the captain and the first officer.

ii) Transportation will be a round trip to and from the Platform once every two months or on a schedule that is agreed upon by the CSLC.

(1) In addition, Contractor will be required to obtain transportation to respond to Platform Holly safety needs with 48-hour notice, throughout the year.

iii) Rope Swing Safety - The Contractor must follow all training, safety protocols, and best practices when conducting swing rope transfers including, but not limited to:

(1) Preparation: Ensure the transfer area is clear of obstructions and has non-slip deck coating. The captain should have clear visibility of the transfer area, either directly or via CCTV.

(2) Personnel: Verify personnel competencies and ensure they understand safety aspects. Personnel should wear a securely fastened floatation vest. Never transfer alone.

(3) The Ropes: Inspect swing ropes for wear and damage, and conduct load tests. One rope is used to transfer from boat to platform, anchored above the platform's landing area. The other rope transfers personnel from platform to boat, anchored over the water.

(4) The transfer: Grab the rope above the middle knot or at eye level. Swing only when ready, and don't swing with extra weight. Pass baggage over first.

h) Task 3: Maintenance of Navigation Aids

i) Maintenance and repair of self-contained solar-powered (with battery backup) navigation aids that consist of:

(1) 4 x Self-contained obstruction lights on each corner of the platform

(2) 1 x Self-contained sound signal (foghorn)

(3) 1 Aircraft beacon light on top of the Derrick

ii) Navigation aids will be built for long service life in harsh offshore environments with low maintenance. Navigation aids will have a method for remote monitoring to ensure functionality

i) Task 4: Maintenance of Platform Solar Power

i) Maintenance and repair of a standalone solar array system capable of powering the security and communications systems including battery backup for a minimum of three days. The solar system allows communications via the cloud to monitor power output and battery capacity remotely.

ii) Anticipated Loads:

Item
Quantity
Power (W)
Total Power (W)
Camera System
2
24
48
Camera Network Equipment
1
180
180
Communication Hotspot
1
24
24
Router
1
24
24
Battery Charging
TBC
TBC
TBC
Crane Electric Starter
N/A – self-contained solar system
Navigation aids
N/A – self-contained solar system

Total Load Capacity

Surge Load Capacity

j) Task 5: Inspection and maintenance of a security fence, gate, and platform

i) Inspection for operability and maintenance of a security fence and gate on the main access staircases to prevent access from the boat landings to the platform topsides. The gate will be designed to prevent circumnavigation around or over the fencing.

ii) During each visit, Contractor shall visually inspect the platform for degradation or signs of damage to the above-mentioned items or structural items. A checklist will be provided by the Commission, but will include items such as:

(1) Verification of all 25 anode strings

(2) Bird striping in place

(3) Loose items that could cause damage to the platform, personnel, or environment.

k) Task 6: Inspection of security cameras for operability

i) Inspection for operability and maintenance of two security cameras with audio and motion detection capabilities connected to an online monitoring system able to send alarms to a cellphone:

(1) One covering the main staircase and security gate from the boat landings to the platform.

(2) And another covering the main deck communication & solar inverter equipment.

ii) Motion detection will be capable of detecting personnel on the platform rather than motion from wave or wind forces, as well as from bird landings or marine mammals.

l) Optional work

i) Contractor staff must be qualified to assess, maintain, and repair equipment listed below, and will be expected to document the results of any Work for the Commission. Contractor shall be capable of providing the following services, directly or by subcontract:

(1) Provide services to repair and potentially replace the equipment listed above, in the event the Commission deems it necessary.

(2) Perform ancillary platform inspection services as directed by the CSLC including preparation of Level 1/2/3/4 inspections.

(3) Inspect lifesaving equipment on Platform Holly.

(4) Provide spill plan response and deployment services consistent with prepared and filed plans and work related to stormwater discharge requirements.

(5) Prepare required filings associated with regulatory requirements.

3) Coordinate with ExxonMobil or their subcontractor for crane maintenance.

4) Definitions - The following terms are defined below and will be referenced throughout the scope of work.

a) Contractor: For purposes of the site work, safety, and access standards under this work, the Contractor, Contractor’s personnel, and the Contractor’s equipment and staging, shall be inferred to include all Contractor’s subcontractors and vendors entering the project site. Contractor shall ensure that its subcontractors adhere to the requirements of work as indicated in plans and specifications. Contractor shall ensure that its subcontractors adhere to the requirements of work as indicated in plans and specifications.

b) Commission: California State Lands Commission (CSLC)

c) Commission’s Representative: On-Site Representative of the Commission

5) Safety and Occupational Health terms are defined as follows:

a) High Visibility Accident: Any mishap that may generate publicity and/or high visibility.

b) Medical Treatment: Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. The medical treatment does not include first aid treatment provided by a physician or registered personnel.

c) Recordable Injuries or Illnesses: Any work-related injury or illness that results in:

i) Death, regardless of the time between the injury and death, or the length of the illness;

ii) Days away from work;

iii) Restricted work;

iv) Transfer to another job;

v) Medical treatment beyond first aid;

vi) Loss of consciousness; or

vii) A significant injury or illness diagnosed by a physician or other licensed healthcare professional, even if it did not result in the actions listed above.

6) General Conditions - Work under this contract will be performed under the jurisdiction of the Commission. Commission staff will execute the contract documents, coordinate with the Contractor as necessary, and conduct inspections to ensure that the work is performed in strict accordance with the Scope of Work and Specifications. No deviations from these Specifications will be permitted without the concurrence and subsequent authorization from the Program Project Coordinator or his representative.

7) Quality Control - The Contractor shall be responsible for the completeness of his/her work. He/she shall be responsible for the progress of his/her work until final completion and acceptance of the same by the State and shall make such checks on the work as may be necessary to assure conformance with these specifications.

a) All materials used and installed for this project shall be new materials.

b) Building materials and systems shall be installed according to State and local building codes and manufacturer’s specifications.

c) Inspection - The State, through any authorized representatives, has the right at all reasonable times to inspect or otherwise evaluate the work performed or being performed hereunder including subcontract-supported activities and the premises in which it is being performed. If any inspection or evaluation is made by the State of the premises of the Contractor or a subcontractor, the Contractor shall provide and shall require their subcontractor(s) to provide all reasonable facilities and assistance for the safety and convenience of the State representatives in the performance of their duties. All inspections and evaluations shall be performed in such a manner as not unduly delay the work.

8) Equipment

a) All equipment needed for the successful completion of the project shall be provided by the Contractor.

b) All equipment shall be in good working condition and suitable for the purpose for which the equipment is to be used.

9) Material or Equipment Specified by Name

a) When any material or equipment is indicated or specified by patent or proprietary name or by the manufacturer’s name of one or more designations, it shall be considered as used for convenience in describing the material or equipment desired. The use of an alternative material or equipment which is of equal quality, operability, maintenance history, and reliability, and of the required characteristics for the purpose intended will be permitted.

b) The Contractor may offer substitutions of products considered to be equal to that specified. The burden of proof as to the quality and suitability of the alternative shall be upon the Contractor. The Commission PC shall be the sole judge as to the quality and suitability of the alternative materials or equipment.

10) Existing Structures and Utilities - Due care shall be exercised to avoid damage to any existing property.

11) Labor and Subcontractors

a) Contract Staff Requirements - The Contractor represents that it has or shall secure at its own expense, all staff required to perform the services described in this Agreement. Such personnel shall not be employees of or have any contractual relationship with the Commission or any other governmental entity.

b) Subcontractors – Contractor must provide a list of subcontractors specifying the function to be performed (Bidder Declaration GSPD- 05-105). Subcontractors must be Certified as Small Business by the State of California, Department of General Services, Office of Small Business (OSDS).

c) Labor – Every part of the work shall be accomplished by workers, laborers, or mechanics especially skilled in the class of work required and workmanship shall be the best. Any person the Project Coordinator deems incompetent or disorderly shall be promptly removed from the work by the Contractor.

d) Prevailing Wage – Contractor shall comply with Labor Code Section 1775. Contractor shall comply with the Labor Code and pay prevailing wage rates recognized in the collective bargaining agreement, applicable in the County in which the work is to be performed and applicable to the particular craft, classification, or type of worker employed on the project.

e) Hours of Labor – Eight hours of labor constitutes a legal day’s work, work performed by employees or contractors in excess of eight hours per day, and 40 hours during one week, shall be permitted upon compensation for all hours worked in excess of eight hours per day at no less than one and one-half time basic rate of pay, as provided in Labor Code Section 1815.

12) Safety and Accident Prevention – Precautions shall be always exercised for the protection of persons (including employees) and property. These shall include but are not limited to, the installation of adequate safety guards and protective devices for all equipment and machinery, whether used in the performance of work or permanently installed as part of the work. Contractor awarded the agreement shall comply with all applicable laws relating to safety precautions, including the safety regulations of the Division of Industrial Safety, California Department of Industrial Relations. All work shall be performed in accordance with CalOSHA safety statutes, including the use of appropriate personal protective equipment and the presence of a first aid kit. Contractor shall complete work in a manner that allows Commission staff and visitors to safely access the building during construction activities. If at any time the Contractor must block off access to a part of the property for safety, Contractor will communicate this need at least 24 hours in advance, will limit the closure of the area to the time necessary to complete the activity, and will provide adequate signage or warnings to keep individuals from accessing any unsafe areas.

13) Travel and Subsistence Payment - Contractor shall pay travel and subsistence payments to each employee needed to execute the work as such travel and subsistence payments are defined in the applicable collective bargaining agreements filed with the Department of Industrial Relations pursuant to Labor Code Section 1773.8.

14) Apprentices - Properly registered apprentices may be employed in the prosecution of the work. Every such apprentice shall be paid the standard wage paid to apprentices under the regulations of the craft or trade at which he or she is employed and shall be employed only at the work of the craft or trade to which he or she is registered. The Contractor and each subcontractor must comply with the requirements of Labor Code Section 1777.5 and any related regulations regarding the employment of registered apprentices.

15) Record-Keeping - Contractor and subcontractor shall comply with the Labor Code Section 1776 regarding record keeping.

16) Subsequent Solicitation

a) At the Commission’s sole discretion, after the contract award has been made and the contract has been executed, if the contract is terminated with or without cause after the performance has begun, the Commission may engage the next responsible low bidder without performing a subsequent solicitation.

b) Additionally, if at any time during the negotiation of an agreement with the successful bidder, the Commission and Contractor mutually determine they cannot reach an agreement, they may terminate the negotiations and engage the next responsible low bidder without performing a subsequent solicitation.

17) Timeliness - All performance under the Agreement shall be completed on or before the termination date of the Agreement. Timing is of the essence and is material to the performance of the contract.

18) Separate Contracts - The State reserves the right to let other contracts in connection with this work. The Contractor shall afford other contractors reasonable opportunity for the introduction and storage of their materials and the execution of their work and shall properly connect and coordinate his or her work with theirs.

19) Effective Date - The effective date of this Contract is either the start date specified in Paragraph 2 of the Standard Agreement (STD 213) or the approval date by the Department of General Services, Legal Office, whichever is later. No work shall commence until the effective date.

20) Requirements before the commencement of work

a) Mobilization - Have materials, equipment, and personnel required to perform each segment of the work at the site prior to the commencement of the work. Mobilization includes the delivery, and assembly of the equipment.

b) Subcontractors and Personnel Contact List - Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

c) Training - New employees (Contractor and subcontractor) shall be informed of specific site hazards, and additionally they must attend and pass a site safety review before they begin work as called for in Section 01140 Work Restrictions.

d) Documentation of this orientation shall be kept on file at the project site and provided to the Commission's Representative during the first subsequent construction meeting following training.

e) Safety of Structures - The execution of work shall ensure the stability of structures on or at the site of the work.

21) Field Conditions - It shall be the responsibility of the Contractor to inspect the site of the work, prior to bidding, to satisfy himself/herself as to field conditions that may affect the work.

a) Contractor acknowledges having carefully examined the plans of the work sites and specifications. Contractor has investigated the conditions, character, and quality of surface or subsurface materials or obstacles that might be encountered.

b) No additions or increases to the contract amount will be made due to a lack of careful examination of work sites and specifications.

22) Working Hours - There are no limits on working hours except as cited in the permits.

23) Supervision - Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills. Evidence of poor supervision may result in termination of the Agreement if not remedied by mutual agreement within a reasonable time frame.

24) Emergency Medical Treatment - Contractor and subcontractors shall arrange for their own emergency medical treatment. The Commission has no responsibility to provide emergency medical treatment.

25) Drug Prevention Program - Conduct a proactive drug and alcohol use prevention program for all workers, Contractor, and subcontractors, on the site. Ensure that no employee uses illegal drugs or consumes alcohol during work hours. Ensure there are no employees under the influence of drugs or alcohol during work hours. After accidents, collect blood, urine, or saliva specimens and test the injured and involved employees for the influence of drugs and alcohol. A copy of the test shall be made available to the Commission upon request.

26) Regulatory Requirements - In addition to the detailed requirements included in the provisions of this contract, work performed shall comply with the Contractor’s Environmental, Health and Safety Manual, CALOSHA Construction Safety Orders, USACE EM 385-1-1, and other related federal, state, and local, laws, ordinances, criteria, rules, and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements shall apply.

27) DVBE Participation Requirement - This project has a mandatory participation goal of three percent (3%) of the total contract price for qualified Disabled Veteran’s Business Enterprise (DVBE).

a) This three percent (3%) goal may be achieved by a combined effort of the Contractor and sub-contractors.

b) Any business used to meet the DVBE requirement must be certified by or have certification pending with the Department of General Services, Office of Small Business Certification and Resources.

c) Contractor will clearly identify within their proposal, those sub-contractors that are certified DVBEs.

d) The cost estimate will identify the amounts allocated to those sub-contractors who are certified DVBEs in their cost proposal.

e) Contractor has advised that commitment made to achieve disabled veteran business enterprise (DVBE) participation if awarded the contract, Contractor must be within 60 days of receiving final payment under this contract (or within such other time period as may be specified elsewhere in this contract) certify in a report to the awarding department:

i) the total amount the prime contractor received under the contract;

ii) the name and address of the DVBE(s) that participated in the performance of the contract;

iii) the amount each DVBE received from the prime contractor;

iv) that all payments under the contract have been made to the DVBE(s); and

v) the actual percentage of DVBE participation that was achieved.

vi) A person or entity that knowingly provides false information shall be subject to a civil penalty for each violation. (Military & Veterans Code (M&VC) section 999.5(d)).

vii) Contractor understands and agrees that should the award of this contract be based in part on their commitment to using the Disabled Veteran Business Enterprise (DVBE) subcontractor(s) identified in their proposal or offer, per Military and Veterans Code 999.5 (e), a DVBE subcontractor may only be replaced by another DVBE subcontractor and must be approved by the Department of General Services (DGS).

viii) Changes to the scope of work that impact the DVBE subcontractor(s) identified in the proposal or offer and approved DVBE substitutions will be documented by contract amendment.

(1) Failure of Contractor to seek substitution and adhere to the DVBE participation level identified in the proposal or offer may be cause for contract termination, recovery of damages under rights and remedies due to the State, and penalties as outlined in M&VC section 999.9; Public Contract Code (PCC) section 10115.10, or PCC section 4110 (applies to public works only).

ix) For general DVBE contracting assistance, email osdshelp@dgs.ca.gov or call (916) 375-4940.

28) Amendments

a) No amendment or variation of the terms of this Agreement shall be valid unless made in writing, signed by the authorized parties and all State requirements are met, including review by the Department of General Services, Legal Office if necessary. No oral understanding or arrangement not incorporated into this Agreement is binding to either party.

b) Amendments to this Agreement may be proposed by either party and shall be effective by the issuance of a written instrument executed by both parties. The Agreement price may be equitably adjusted to reflect any additional costs or new savings resulting from such amendment(s).

c) Work subject to such amendment(s) shall be performed in accordance with all applicable requirements of this Agreement, including any amendments thereto. No guarantee is made hereby that any change(s) or additional work will be authorized or required.

29) Renewals - The Initial Term of this Agreement is for a total of one (1) year. Further renewals for this agreement may be granted by the Commission in order to allow the Firm to complete work under this Agreement that was approved by the Commission.

30) Additional Funding - If mutually agreed by the Commission and the Contractor, this contract may be amended to include additional funding at the same rates provided in the Bidder’s original proposal.

31) Conflict - The parts of this Contract are complementary, describe, and provide for the completion of the work specified herein. This standard Contract, including Exhibit A through D, makes up the entire Contract between the parties. No document or communication passing between the parties hereto shall be deemed a part of this Contract unless expressly identified as being a part of it.

32) References. This exhibit makes references to the below. The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

a) Health and Safety References

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI Z359.1
Safety Requirements for Personal Fall Arrest Systems, Subsystems, and Components

ASME INTERNATIONAL (ASME)

ASME B30.5
Mobile and Locomotive Cranes ASME
B30.8
Floating Cranes and Floating Derricks
ASME B30.22
Articulating Boom Cranes

OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA)

29 CFR 1910
Safety and Health Regulation in General Industry
29 CFR 1910.120
Hazardous Waste Operations and Emergency Response
29 CFR 1926
Safety and Health Regulations for Construction
29 CFR 1926.65
Hazardous Waste Operations and Emergency Response
29 CFR 1926.500
Fall Protection

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1
Safety and Health Requirements Manual

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10
Portable Fire Extinguishers
NFPA 70
National Electrical Code
NFPA 241
Safeguarding Construction, Alteration, and Demolition Operations

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910
Occupational Safety and Health Standards
29 CFR 1910.120
Hazardous Waste and Emergency Response
40 CFR 112
Oil Pollution Prevention
40 CFR 122.26
EPA National Pollutant Discharge Elimination System Permit Regulations
40 CFR 241
Guidelines for Disposal of Solid Waste
40 CFR 268
Land Disposal Restrictions
40 CFR 273
Universal Waste Management
40 CFR 279
Used Oil Regulations
40 CFR 355
Emergency Planning and Notification
40 CFR 716
Health and Safety Data Reporting

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA 832-R-92-005
Storm Water Management for Construction Activities

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1
2008 U.S. Army Corps of Engineers Safety and Health

33) Notices - Written notice shall be deemed to have been duly served if delivered in person to the individual or a member of the firm or to an officer of the corporation for whom it is intended or if delivered at or sent by registered mail to the last business address known.

34) Responsibilities of Project Coordinator

a) The Commission Project Coordinator and Contractor Project Representative shall be the day-to-day representatives for the administration of this Contract. Except as otherwise expressly provided, all communications relative to this Contract shall be given to each Parties’ Project Coordinator. Either party shall have the right to change its Project Coordinator upon written notice to the other party.

b) The Party’s Agents for this Project are: Comment by Shrestha, Dev@SLC: Bidder to update their company contact information in the 3 sections in red text.

i) Commission Project Coordinator

(1) Palani Chandrasekaran

(2) Associate Engineer, Petroleum Structures

(3) 301 Ocean STE 550 Long Beach CA 90802-8833

(4) 562-590-3132

(5) palani.chandrasekaran@slc.ca.gov

(6) www.slc.ca.gov

ii) Contractor Project Coordinator

(1) Name

(2) Title

(3) Address

(4) Phone

(5) Email

(6) Website address 35)

a) Direct all Agreement inquiries to:

i) Commission Contract Buyer

(1) Dev Shrestha

(2) Contract Buyer

(3) 100 Howe Ave., Suite 100-S, Sacramento CA 95825

(4) 916-432-9052

(5) dev.shrestha@slc.ca.gov

(6) www.slc.ca.gov

ii) Contractor Contracting Contact

(1) Name

(2) Title

(3) Address

(4) Phone

(5) Email

(6) Website address

iii) Commission Accounting Contact

(1) Accounts Payable

(2) AP

(3) 100 Howe Ave., Suite 100-S, Sacramento CA 95825

(4) 916-574-1800

(5) CSLC.AccountsPayable@slc.ca.gov

(6) www.slc.ca.gov

iv) Contractor Accounting Contact

(1) Dept

(2) Name

(3) Address

(4) Phone

(5) Email

(6) Website