About this file

This statement of work outlines technical requirements for a federal contract to provide corrugated steel pipe for the FY21 Legacy Site Reconstruction project for the US Department of Agriculture Forest Service. The contractor must supply various quantities and sizes of galvanized steel corrugated metal pipe and bands, with materials conforming to applicable AASHTO standards. Delivery of all items is required FOB destination to 1030 S Main St Yreka, Ca within 90 days of award. The contractor will also be responsible for transport of materials from the manufacturing plant to the project delivery site. No key personnel, security requirements, or Section 508 compliance standards are identified.

The related federal contract opportunity on the Forest Service website solicits for the provision of the corrugated steel pipe and metal bands detailed in the statement of work, with a closing date for responses unspecified.

View the file

Other files for this federal contract opportunity

Other files attached to Culvert Pipe and Metal Bands, newest first.
File Type Posted
A6_Commercial_Supplies_CombinedSS_RFQ_AMEND11212023_0001.docx DOCX document
Sol_12970224Q0001_Amd_0001.pdf PDF
A1_DeliverMap.docx DOCX document
Sol_12970224Q0001.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards

Project Fy21 Legacy Site Reconstruction

General Information

1.0 Scope of Work

Provide Corrugated steel pipe for Fy21 Legacy Site Reconstruction project.

2.0 Background.

Contractor Requirements

3.0 Technical Requirements / Tasks

Provide the following:

Class of Material: Galvanized Steel Conforms to AASHTO M36 and either M274, M218 or M289

40 Feet of 14 Gage 24” Galvanized, Corrugated Metal Pipe 80 Feet of 14 Gage 30” Galvanized, Corrugated Metal Pipe 200 Feet of 12 Gage 36” Galvanized, Corrugated Metal Pipe 120 Feet of 10 Gage 48” Galvanized, Corrugated Metal Pipe 100 Feet of 10 Gage 60” Galvanized, Corrugated Metal Pipe 60 Feet of 10 Gage 72” Galvanized, Corrugated Metal Pipe

Note: Pipe shall be 20 Feet in length section per pipe

16 Gage Galvanized Metal Bands in the following sizes:

24”X 12” Need 1 30”X 12” Need 3 36”X 12” Need 8 48” X 12” Need 5 60” X 12” Need 3 72” X 12” Need 2

4.0 Government Furnished

N/A

5.0 Deliverables / Schedule

Deliver to 1030 S Main St Yreka, Ca. Upon Completion of full order. FOB Destination.

Delivery shall occur within 90 days of award.

6.0 Travel.

Travel (transport) from Manufacturing plant to Yreka Service Center

7.0 Contractor’s Key Personnel

N/A

8.0 Security Requirements

N/A

9.0 Data Rights

N/A

10.0 Section 508 – Electronic and Information Technology Standards N/A bobeberle Highlight

Project
General Information
1.0 Scope of Work
2.0 Background.
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel.
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards

File details come from the government source that posted it. Updated .