A1_-_Mt_psigah_cabin_SOW_12122019_(v4)_(1).pdf
PDF 369 KB Posted
- Attached to
- Blue Ridge Parkway REPL. DAMAGED SILL PLATE Federal contract opportunity
- Solicitation number
- 140P5324Q0002
About this file
This statement of work describes required repairs to replace rotted sill plates at a log cabin located in Mount Pisgah Campground on the Blue Ridge Parkway. The contractor will remove and replace approximately 70 linear feet of rotted sill plate with pressure treated lumber, and install flashing and a moisture barrier to prevent future rot. The work must be performed between late October and late March 2024 while the cabin is unoccupied. The contractor must have experience working on log cabin construction and foundations, obtain general liability insurance, coordinate work with park staff, and provide a one-year warranty. The contactor is responsible for travel and lodging costs to complete the work. This statement of work is associated with the National Park Service solicitation to replace the damaged sill plate at the Blue Ridge Parkway for Southeast Region.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Construction_Contract_Administration.docx | DOCX document | |
| A3_-_DOL_Wage_Determination.pdf | ||
| A2_-_Pictures_of_Cabin_for_Slate_Repair.pdf | ||
| Sol_140P5324Q0002.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BLUE RIDGE PARKWAY
HEADQUARTERS IN ASHEVILLE NC
STATEMENT OF WORK
(SOW):
Replacement of Rotted Sill Plate Building B828
DATED:
July 26, 2023
NATIONAL PARK SERVICE
1.0 BACKGROUND
Building B828 is a residence at Mount Pisgah campground, the residence is a log cabin kit constructed in 1993, the residence is a 24X40 log cabin that is used for seasonal housing from April 1st thru November 1st. It is sitting on a block foundation with a non pressure treated sill plate all the way around.
1.1 This project will replace old, compromised sill plate with new code compliant pressure treated material.
2.0 SITE LOCATION
Mt. Pisgah Campground mile post 408.8 on the Blue Ridge Parkway 24 miles Southwest of Asheville NC.
3.0 CONTRACTOR REQUIREMENTS
3.1 The contractor including onsite personnel shall have proven experience and expertise working in construction and repair of log cabins and foundations.
3.2 Prior to submitting a quote for the project, the Contractor is strongly encouraged to perform a site visit to be knowledgeable of the site and the work that needs to be completed.
3.3 Contractor and personnel performing the assessment shall meet one of the following requirements:
3.3.1 Contractor Shall have General Liability insurance.
3.4 The contractor shall coordinate all site work with the park point of contact.
3.5 The assessment will be performed on the day and at a time directed by the park facility personnel.
3.6 The contractor shall be responsible for any damage to the structure or contents because of the assessment.
3.7 The contractor shall be responsible for removing and properly disposing of all debris resulting from the repairs.
3.10 The contractor shall provide onsite supervision of the contract work, including work that may be accomplished using subcontractors.
4.0 PERIOD OF PERFORMANCE
The period of performance for this project shall be in the fall of 2023 late October to late March 2024 while housing is vacant, and the contractor has received a notice to proceed from the park facility personnel.
5.0 DELIVERABLES
5.1 Remove and replace rotted sill plate (NPS best estimate is 70 linear feet, but contractor is responsible for determining quantity for self) upon concurrence with the COR the contractor shall tear out and replace rotted sill plate on the back and right side of the cabin and replace it with code compliant pressure treated lumber the contractor shall provide and install brown or gray colored flashing to match the trim and guttering along with placing a moisture barrier on the ground in the crawl space to help keep the moisture out.
6.0 WARRANTY
6.1 Contractor shall provide a one year warranty for their contract period of performance which includes repair and compensation for damages resulting from the performance of this SOW.
7.0 TRAVEL
7.1 Contractor shall be responsible for all travel related expenses for this project, including mobilization of equipment, tools, materials, manpower, lodging, meals, and per diem.
8.0 CONTACT INFORMATION
For Information and directions Contact Kevin Reeves, 828-348-3437 or 828-772-4636 or by email at kevin_reeves@nps.gov