A1. Statement of Work.pdf

PDF 153 KB Posted

Attached to
127EAW23R0030 - Cameron Fire Station Barracks Reroof
Solicitation number
127EAW23R0030
Issued by

View the file

Other files

File Type Posted
A5. Davis-Bacon Act WD # CA20230001.pdf PDF
A7. Fire Plan.pdf PDF
A6. RFI Form.docx DOCX document
A2. Schedule.docx DOCX document
A8. Lead Sampling Report.pdf PDF
Solicitation 127EAW23R0030 - Cameron Fire Station Barracks Reroof.pdf PDF
A3. Specifications.pdf PDF
A4. Maps.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CAMERON FIRE STATION BARRACKS REROOF

STATEMENT OF WORK SECTION C - 1

STATEMENT OF WORK

1 SCOPE OF WORK

This project work includes, but is not limited to the following:

a. Cameron Fire Station Barracks building existing roof type is asphalt composition shingle and is approximately 1500 square feet. Reroof structure by removing all roofing shingles and underlayment down to the substrate material.

b. Remove gutters as necessary and reset after roof work is completed.

c. Remove and replace all existing fascia boards and soffit, approximately 160 linear feet.

d. Repair roof substrate decking material where required to complete necessary work.

An estimated 200 square feet of decking repair work is estimated; however, this quantity may change when substrate material is exposed. All repair work is to be discussed with the Contracting Officer prior to substrate replacement.

Contractors shall submit a Request for Information (RFI) after a site visit if the contractor anticipates a larger area of substrate material needing replacement than what has been indicated in the solicitation.

e. Replace all roof underlayment, shingles, rake and eave flashing, vent, sleeves, and collars, fascia boards, and add an approved moisture protection material and all incidentals.

f. The existing barracks building was constructed in 1936. Recent lead-based paint sampling and testing was completed, and the fascia boards were shown to have lead-based paint. Asbestos sampling and testing were recently completed, and roof and roof components were shown to have no asbestos. See the Specification Section 02 41 00 Demolition, for the guidelines for removal and disposal of hazardous materials.

g. Existing conditions shall be verified by the Contractor. The roof area is approximately 1500 square feet and shall be verified by Contractor. Contractor shall inspect existing roof prior to beginning construction and bring to the attention of the Contracting Officer any discrepancies not covered by contract work listed herein. A site visit is highly recommended prior to bidding.

h. All work shall be performed in a manner to minimize ground disturbance.

i. HAZARDOUS MATERIALS: Hazardous building materials include lead containing materials.

1. The contractor must be a licensed and/or accredited contractor to inspect, handle, and remove and lead in California. The contractor must follow all OSHA, local, California state, and federal regulations for handling, removal, and transportation of the hazardous material.

2. Lead Sampling Report is attached to the solicitation.

Total work time is 24 calendar days from the issuance of the Notice to Proceed.

STATEMENT OF WORK SECTION C - 2

2 PROJECT LOCATION

Cameron Fire Station, San Diego County, Descanso Ranger District

From San Diego travel east on Interstate 8 to Kitchen Creek Road. Turn left on Kitchen Creek Road and travel north ~ .25 mile. The Cameron Fire Station is on the left. The site address is 3110 Kitchen Creek Road, Pine Valley, CA 91962.

3 FOREST CONTACT

For information regarding site conditions, contact Tammie Mather at (858) 674-2972 between the hours of 8:00 am and 4:00 pm, Monday through Friday, except legal holidays.

4 PROJECT MANAGEMENT

The contractor shall appoint a Project Manager to coordinate all Contractor’s activities during construction and to liaise with the Contracting Officer Representative (COR) and/or Contracting Officer (CO), and Project Engineer for the USDA Forest Service. Contractor shall designate in writing an on-site superintendent to be on-site at all times that any construction activities take place and to coordinate all site work and activities.

5 GENERAL INFORMATION

5 - 1 Parking and Storage

The Contractor shall coordinate parking of their vehicles and temporary storage of equipment and materials with the Contracting Officer. Contractor shall have all heavy equipment washed prior to entering the project area to remove soil, seeds and plant material from noxious weeds to prevent the introduction and spread of weeds not already present on Descanso Ranger District or the Cleveland National Forest. Inspections shall be coordinated and scheduled with the Contracting Officer’s Representative at least 2 days prior to equipment arriving on site.

6 SPECIFICATIONS

The Construction Specification Institute (CSI) specifications applicable to this contract are listed below:

00 01 10 TABLE OF CONTENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 31 00 PROJECT MANAGEMENT AND COORDINATION

01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SUBMITTALS

01 40 00 QUALITY REQUIREMENTS

STATEMENT OF WORK SECTION C - 3

01 41 00 REGULATORY REQUIREMENTS

01 57 24 STORMWATER POLLUTION CONTROL

01 71 13 MOBILIZATION

01 74 00 CLEANING AND WASTE MANAGEMENT

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

02 41 00 DEMOLITION

06 10 00 ROUGH CARPENTRY

07 00 00 THERMAL AND MOISTURE PROTECTION

07 31 13 ASPHALT SHINGLES

07 62 00 FLASHING AND SHEET METAL

07 92 00 JOINT SEALANTS

09 90 00 PAINTING

7 DELIVERABLES

7-1 Fire Plan

See the Fire Plan for fire restrictions and requirements, emergency contact information, and fire project activity levels.

7-2 Work Plan

The Contractor(s) shall provide the Government with two (2) copies of the Work Plan for the project prior to mobilization. This Work Plan shall include, but is not limited to, the following:

• A description of how the work will be performed.

• Specific exclusions/ assumptions regarding the specific work to be performed.

• A listing of personnel, including subcontractor(s), working on the project.

• A list of equipment proposed for use on the project.

• A Project Work Schedule.

• Detailed cost estimate/cost breakdown of work to be performed per Specification Section that can be used for partial payments as work is completed and accepted.

7-3 Storm Water Management Plan

Contractor shall develop an Erosion Control/Storm Water Control Plan. Contractor shall identify and address all types and specific locations of erosion control measures.

7-4 Construction Waste Management Plan

Contractor shall develop a proposal on how to collect, segregate, and dispose of all construction wastes and debris produced by the work of this contract, including hazardous materials.

STATEMENT OF WORK SECTION C - 4

7-5 Spill Prevention Control and Countermeasures (SPCC), spill response plan and an emergency response plan for refueling and servicing vehicles.

Identify and use suitable measures around vehicle service, storage and refueling areas, and waste dumps to fully contain spills and avoid or minimize soil contamination and seepage to groundwater. Use suitable measures to avoid spilling fuels, lubricants, cleaners, and other chemicals during handling and transporting. Report spills to the Contracting Officer’s Representative and initiate suitable cleanup action in accordance with applicable State and Federal laws, rules, and regulations.

7-6 Hazardous Materials Abatement Work Plan

Contractor shall develop an Abatement Work Plan for lead-based paint abatement.

END OF STATEMENT OF WORK