This document is a draft Performance Work Statement (PWS) for a federal contract opportunity to enhance the Legacy Walk gallery at the National Museum of the Marine Corps (NMMC) by replacing the existing carpet flooring and adding two interactive information kiosks.
The key requirements include: 1) Removing existing carpet squares and vinyl flooring, cleaning and preparing the concrete slab, and installing new carpet squares as specified, and 2) Creating and fabricating two interactive kiosks to match an existing kiosk. The work must be completed within 120 calendar days after contract award. The government will provide the technical point of contact and attachments with additional details. This is a sources sought announcement to determine market capabilities, with interested vendors requested to submit business information, capabilities, and feedback on the draft PWS within 2 pages. The anticipated NAICS code is 238990, and a firm-fixed price contract type is anticipated.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A1. Attachment 1 - D-100 Legacy Walk Plan.pdf | ||
| A1. Attachment 2 - Information Kiosk Drawing.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT Performance Work Statement (PWS) Legacy Walk Gallery Enhancement National Museum of the Marine Corps/ Marine Corps University (NMMC/MCU)
1. Background The National Museum of the Marine Corps (NMMC) has a requirement to enhance the existing Legacy Walk gallery by replacing the existing floor covering and adding two (2) interactive kiosks.
2. Scope The NMMC Legacy Walk gallery flooring is becoming unsightly as, over 17 years, small areas of carpet have been replaced when damaged. This patchwork of repairs is beginning to degrade the overall look of the flooring and NMMC requires a total carpet replacement. In addition, NMMC requires two (2) interactive information kiosks to be built to match the one existing. This will allow NMMC the ability to have media-based directory signage in the gallery.
3. Performance Requirements
3.1. Task: Carpet replacement. The Contractor shall:
3.1.1. Walk job site with Government Technical Point of Contact (TPOC) prior to starting work to better understand requirements and identify any issues that could interfere with the work.
3.1.2. Remove all existing freestanding benches and kiosks in the gallery. NMMC will provide on-site storage for these elements. The Contractor shall reinstall all removed elements after new carpet is installed.
3.1.3. Remove all existing carpet squares and vinyl flooring in the area of work (see Attachment 1). Contractor shall be responsible for disposal of flooring from NMMC property.
3.1.4. Clean and prepare concrete slab for new adhesive and carpet per manufacturer recommendations. The Contractor shall provide all materials needed to include adhesive and carpet.
3.1.5. Install new carpet squares in the area of work shown in Attachment 1. Carpet and flooring adhesive to be installed per manufacturer recommendations.
3.1.6. Replace, as needed, any vinyl baseboard that is damaged or unusable as a result of flooring removal.
3.2. Task: Interactive kiosks. The Contractor shall:
3.2.1. Create and submit fabrication drawings for two (2) interactive kiosks. These are to match the design and functionality of the existing kiosk (see Attachment 2). NMMC will review the submitted drawings and make corrections as needed. The Contractor will revise the drawings per this guidance and resubmit to NMMC for final approval. Drawing(s) shall be C size and created in AutoCAD software.
3.2.2. Contractor shall fabricate the kiosks per the approved drawings. The Contractor is not responsible for providing any audio/video equipment.
3.2.3. Contractor shall deliver the completed kiosks to the NMMC. The Contractor will not be responsible for installation of the kiosks in the gallery.
4. Applicable Information and/or Documents See Attachments 1 and 2 for information and call-outs for the procurement. NMMC is providing a ground plan for the area and call-out of the carpet and elevations with call-outs for the interactive kiosks.
4.1. Government Technical Point of Contact (TPOC): TPOC contact information to be provided at time of contract award.
4.2. Period of Performance: Performance must be complete no later than 120 calendar days after date of contract award (ADC).
4.3. Place of Performance and Delivery Address:
The National Museum of the Marine Corps (NMMC) 1775 Semper Fidelis Way Triangle, VA 22172
4.4. List of Deliverables:
| Deliverable Name |
| Description |
| Frequency or Required Date |
| Method of Delivery |
| Carpet sample |
| 12” square of carpet called-out in Attachment 1 |
| Provide for approval prior to procuring carpet |
| Mail to TPOC |
| Installation plan |
| Contractor’s plan detailing how they will replace carpet without the need to close galleries to the public |
| No more than 30 calendar days after award |
| Email to TPOC |
| Carpet Install |
| Procure the required carpet and install according to the NMMC Attachments |
| Complete installation no more than 120 days after award |
| Install in NMMC Legacy Walk Gallery |
| Interactive kiosk fabrication drawings |
| Drawing(s) as specified in 3.2.1 in .PDF format |
| No more than 30 calendar days after award |
| Email to TPOC |
| Interactive Kiosk |
| Fabricate kiosks according to the approved drawings |
| Provide for approval no more than 120 days after award |
| Deliver to NMMC |
4.5. Hours of Operation: NMMC is open to the public daily from 9AM to 5PM. NMMC has 24-hour manned security allowing the Contractor to work outside normal operating hours if they so choose.
Work will not be permitted during operating hours on the weekends or U.S. Federal Holidays. Visit Federal Holidays (opm.gov) to view the applicable listing of U.S. Federal Holidays.
4.5.1. Work can be performed during normal operating hours, but Legacy Walk cannot be fully closed to visitors. The Contractor will work with the TPOC to agree upon an installation plan to complete the work in sections, if needed, with the understanding that the Contractor cannot perform any work that endangers or disrupts the visitors. NMMC has 24-hour manned security allowing the Contractor to work outside normal operating hours if they so choose.
4.6. Travel: The Government intends to award a Firm-Fixed Price (FFP) contract type. The Contractor is responsible for all travel/per diem related expenses required to perform this contract. Any anticipated travel costs in the performance of this contract shall be included as part of the quoted rate(s). Any travel matters associated with the performance of this contract are the sole responsibility of the Contractor. The Government shall not have any financial responsibility other than paying for the FFP on each line item.
4.7. List of Attachments:
· Attachment 1 - D-100 Legacy Walk Plan
· Attachment 2 - Information Kiosk Drawing (End of PWS)